HomeMy WebLinkAboutNCC240948_ESC Approval Submitted_20240404 w .,
ROY COOPER4r It
Governor
ELIZABETH S.BISER 'V‹ s _
Secretary g
WILLIAM E. TOBY VINSON,JR. NORTH CAROL.INA
Interim Director Environmental Quality
December 1, 2023
LETTER OF APPROVAL WITH MODIFICATIONS
Duke Energy Carolinas, LLC
Attention: Jeffery Goto, Senior Manager
525 South Tryon Street
Charlotte,North Carolina 28202
RE: Project Name: Flay Retail 44kV GOAB Replacement
Project ID: CELVE-2024-015
Acres Approved: 10.20
County: Cleveland
City: Lawndale
Location: Kadesh Church Rd
River Basin: Broad
Stream Classification: Other
Submitted By: Duke Energy LLC
Date Received by LQS: November 3, 2023
Plan Type: New
Dear Mr. Goto:
This office has reviewed the subject erosion and sedimentation control plan. We find the plan to be
acceptable with modifications and hereby issue this letter of Approval with Modifications. The
Modifications Required for Approval are listed on the attached page. This plan approval shall expire three
(3) years following the date of approval, if no land-disturbing activity has been undertaken, as is required
by Title 15A NCAC 4B .0129.
As of April 1, 2019, all new construction activities are required to complete and submit an electronic
Notice of Intent(eNOI) form requesting a Certificate of Coverage (COC)under the NCG010000
Construction General Permit. After the form is reviewed and found to be complete, you will receive a link
with payment instructions for the $120 annual permit fee. After the fee is processed, you will receive the
COC via email. As the Financially Responsible Party shown on the FRO form submitted for this
project, you MUST obtain the COC prior to commencement of any land disturbing
activity. The eNOI form may be accessed at deq.nc.gov/NCG01. Please direct questions about
the eNOI form to the Stormwater Program staff in the Raleigh central office. If the owner/operator of this
project changes in the future, the new responsible party must obtain a new COC.
Title 15A NCAC 4B .0118(a) and the NCGOI permit require that the following documentation be kept on
file at the job site:
North Carolina Department of Environmental Quality Division of Energy,Mineral,and Land Resources
Mooresville Regional Office',610 East Center Avenue,Suite 301 Mooresville,North Carolina 28115
ataw 704-663-1699
Letter of Approval with Modifications
Duke Energy Carolinas, LLC
December 1, 2023
Page 2 of 3
1. The approved E&SC plan as well as any approved deviation.
2. The NCG01 permit and the COC, once it is received.
3. Records of inspections made during the previous 30 days.
Also, this letter gives the notice required by G.S. 113A-61.1(a) of our right of periodic inspection to
ensure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Act is performance-oriented, requiring protection of
existing natural resources and adjoining properties. If, following the commencement of this project, it is
determined that the erosion and sedimentation control plan is inadequate to meet the requirements of the
Sedimentation Pollution Control Act of 1973 (North Carolina General Statute 113A-51 through 66),this
office may require revisions to the plan and implementation of the revisions to ensure compliance with the
Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and State water
quality laws, regulations, and rules. In addition, local city or county ordinances or rules may also apply to
this land-disturbing activity. This approval does not supersede any other permit or approval.
Please note that this approval is based in part on the accuracy of the information provided in the Financial
Responsibility Form, which you provided. You are requested to file an amended form if there is any
change in the information included on the form. In addition, it would be helpful if you notify this office of
the proposed starting date for this project.
Your cooperation is appreciated.
Sincerely,
el1
Kathryn S. Peterson
Assistant Regional Engineer I
Land Quality Section
KSP
Enclosure: Certificate of Approval
Modifications Required for Approval
NCGO1 Fact Sheet
c: Duke Energy Carolinas, LLC
Attention: Jeffery Goto, Senior Manager
525 South Tryon Street
Charlotte, North Carolina 28202
4111 North Carolina Department of Environmental Quality Division of Energy,Mineral,and Land Resources
Mooresville Regional Office,610 East Center Avenue,Suite 301 Mooresville,North Carolina 28115
704-663-1699
Letter of Approval with Modifications
Duke Energy Carolinas, LLC
December 1, 2023
Page 3 of 3ttt
MODIFICATIONS REQUIRED FOR APPROVAL
Project Name: Flay Retail 44kV GOAB Replacement
Project ID: CLEVE-2024-015
County: Cleveland
Reviewed by: Kathryn S. Peterson
1. Wattles should be used on the North side of the bridge crossing on sheet P 1 B, as well as on the
stream crossing on Sheet PIA.
2. No work is permitted to occur"in the wet". Temporary stream crossings must be maintained
throughout the project to ensure no stream disturbances.
3. Additional measures may be required - The applicant is responsible for the control of sediment on-site. If
the approved erosion and sedimentation control measures prove insufficient, the applicant must take
those additional steps necessary to stop sediment from leaving this site. [15A NCAC 4B .0115]
Ref: G.S. 113A-54.1 through G.S. 113A-57
Sections 15A NCAC 04A.0101 through 15A NCAC 04E.0504
General Permit NCG 010000 NPDES for Construction Activities
North Carolina Department of Environmental Quality;Division of Energy,Mineral,and Land Resources
Mooresville Regional Office 610 East Center Avenue,Suite 301 Mooresville,North Carolina 28115
704-663-1699
t
'
cl
fir,,;,.; a
I
Pm 14
` ' in.
-
.
--4,, 4
F.
;4,k4 A:s - a4 'fir 8 0. 6
1E4
iffil
6
col c Ca 1-4 ®- PC Z
.
6
• . 0 0,0
.
e o
.
• too
6 C Cr) et C0P)
® .
6
6