HomeMy WebLinkAbout20201937 Ver 3_Dead Tree Phase B Comments and Approval_20240401Re: [External] RE: Monitoring Report MY2 Review - Dead Tree Phase B
Friedman -Herring, Andrew <andrew.friedman herring @deq.nc.gov>
Mon 4/1/2024 2:43 PM
To:Matthew Harrell <Matthew.Harrell@davey.com>
Cc:Merritt, Katie < katie.merritt@deq.nc.gov>; Barrett Jenkins <Barrett.Jenkins@davey.com>
Hi Matthew,
Thank you for attaching the height info and addressing the other comments about the site in the
reuploaded report. After review, the Dead Tree Phase B MY2 report is officially approved.
Please provide confirmation of bond renewal through next year's monitoring period. DWR approves a
20% reduction in bond amount to $60,000. Once DWR receives your bond renewal, we can proceed
issuing the credit release for this task.
Let me know if you have any other questions.
Best,
Andrew Friedman -Herring
Environmental Specialist II
Division of Water Resources - 401 & Buffer Permitting
North Carolina Department of Environmental Quality
(919)-707-3644
andrew.friedmanherring@deq.nc.gov
From: Matthew Harrell <Matthew.Harrel I@davey.com>
Sent: Thursday, March 21, 2024 9:39 AM
To: Friedman -Herring, Andrew <andrew.friedmanherring@deq.nc.gov>
Cc: Merritt, Katie <katie.merritt@deq.nc.gov>; Barrett Jenkins <Barrett.Jenkins@davey.com>
Subject: [External] RE: Monitoring Report MY2 Review - Dead Tree Phase B
CAUTION: External email. Do not click links or open attachments unless verified. Report suspicious emails with the Report
Message button located on your Outlook menu bar on the Home tab.
Andrew,
I just uploaded the final monitoring report for Dead Tree Phase B to Laserfiche, including comment
responses and additional data. Please let me know if you have any additional questions or comments.
Thanks,
Matthew
From: Friedman -Herring, Andrew <andrew.friedmanherring@deq.nc.gov>
Sent: Thursday, March 14, 2024 5:00 PM
To: Matthew Harrell <Matthew.Harrell @davey.com>
Cc: Merritt, Katie <katie.merritt@deq.nc.gov>
Subject: Monitoring Report MY2 Review - Dead Tree Phase B
Hi Matthew,
DWR has completed the review of Dead Tree Phase B and have the following comments:
1. A requirement for an easement boundary check to be performed every year is noted in
section 5.2 but does not seem to be included in the monitoring report. Include this
information as a response to this comment and make sure that this information is
included in all future monitoring reports even if no encroachments were observed — it is
recommended that this information be included as a stand-alone section either within,
before or after "Parcel Maintenance".
2. No stem height or vigor data is included in this report, despite being required as per the
relevant BPDP Section 5.1 which states "Species Composition, height, and survival rates
will be evaluated on an annual basis by plot". RS needs to submit the missing data in
response to this comment. DWR will accept the CVS Vegetation Monitoring Data (VIVID)
datasheets with raw data to meet this requirement. It is not required to export vigor and
height into tables.
3. Section 5.1 states that 96 out of 105 plots are meeting the success criteria. This is
incorrect, as it is only true for the density success criteria of 260 stems/acre and does not
take into account the diversity criteria. Only 73 of the 105 plots are meeting all of the
vegetation success criteria. Failing diversity success criteria will not always result in the
necessity for an AMP, but it is data that is required to be recorded and acknowledged as a
performance standard to accurately reflect the site characteristics.
4. The number of plots failing either density or diversity requirements has increased from
MY1 to MY2. The 9 plots newly failing in MY2 are Plots 1, 9, 17, 27, 28, 33, 40, 69, and
104. Is another AMP being considered to address the trajectory of these plots and site as
a whole?
5. Additionally, plots failing density requirements of 260 stems/acre are not specified in
Figure 2. Make sure to color code which plots are failing density success criteria in Figure
2 in all future monitoring reports.
Thank you for your attention to these comments. Please provide an adequate response to all items above along
with supporting documents if required.
Once DWR receives a response to the comments above, issuance of monitoring report approval and credit
release can be determined. Let me know if you have any further questions.
Best,
Andrew Friedman -Herring
Environmental Specialist II
Division of Water Resources - 401 & Buffer Permitting
North Carolina Department of Environmental Quality
(919)-707-3644
andrew.friedmanherring@deq.nc.gov
Email correspondence to and from this address may be subject to the North Carolina Public Records Law and may be disclosed to third parties by an
authorized state official.