Loading...
HomeMy WebLinkAbout20151229 Ver 1_401 Water Quality Certification Report_20151130401 WATER QUALITY CERTIFICATION REPORT HAECO FACILITY IMPROVEMENTS PROJECT Submitted on Behalf of.• Piedmont -Triad International Airport Prepared by: WK Dickson & Co., Inc. 720 Corporate Center Drive Raleigh, North Carolina 27607 November 2015 Table of Contents 1. Introduction.......................................................................................................................1-1 1.1. Project Description.....................................................................................................1-1 2. Hydrology and Hydraulics.............................................................................................. 2-1 2.1. Methodology..............................................................................................................2-1 2.2. Hydrology................................................................................................................... 2-1 2.2.1 Drainage Areas................................................................................................. 2-1 2.2.2 Rainfall...............................................................................................................2-2 2.2.3 Land Use............................................................................................................ 2-2 2.2.4 Hydrograph Translation................................................................................. 2-2 2.2.5 NRCS Curve Numbers.................................................................................... 2-3 2.2.6 Channel/Storage Routing................................................................................ 2-4 2.2.7 Summary of Hydrologic Results....................................................................2-4 2.3. Hydraulics..................................................................................................................2-4 2.3.1 Energy Loss Coefficients.................................................................................2-5 2.3.2 Starting Water Surface Elevation...................................................................2-5 2.3.3 Model Run Descriptions................................................................................. 2-5 2.3.4 Hydraulic Evaluation of Radar Road............................................................2-5 2.3.5 Evaluation of Downstream Flooding............................................................ 2-6 2.3.6 Closed Drainage Systems............................................................................... 2-7 2.3.7 Outfall Protection for Closed Drainage System .......................................... 2-7 3. Water Quality Compliance............................................................................................. 3-1 3.1. Overview..................................................................................................................... 3-1 2.3.1 Proposed Impervious Areas...........................................................................3-1 2.3.2 High Flow Rate Bioretention Pond Design Criteria .................................... 3-2 2.3.3 Water Quality Volume (WQV)...................................................................... 3-2 2.3.4 Pond Design Summary................................................................................... 3-3 3.2. Conclusion...................................................................................................................3-6 HAECO Facility Improvements Project Page i Stormwater Report Tables Table 1: Summary of Area Required for Treatment............................................................1-1 Table 2: Summary of Water Quality Treatment Credits.....................................................1-2 Proposed Concept Plan Table 3: Design Storm Rainfall Depths.................................................................................. 2-2 Table 4: Summary of Hydrologic Input Data....................................................................... 2-3 Table 5: Comparison of Peak Flows at Radar Road............................................................. 2-4 Table 6: Energy Loss Coefficients........................................................................................... 2-5 Table 7: Bend Loss Coefficients.............................................................................................. 2-5 Table 8: Culvert Performance for at Radar Road................................................................. 2-6 Table 9: Hydraulic Summary of Harris Teeter Open Channel .......................................... 2-6 Table 10: Minimum Area of Impervious Cover Required for Treatment ......................... 3-1 Table 11: Proposed Impervious Cover to SCM.................................................................... 3-1 Table 12: Calculated Storage Volumes.................................................................................. 3-2 Table 13: Water Surface Elevations at Proposed Pond ........................................................ 3-3 Table 14: Summary of Flow Splitter Design......................................................................... 3-4 Table 15: Flow Splitter Performance...................................................................................... 3-4 Appendices Appendix A Proposed Concept Plan Appendix B Input Data for SWMM Appendix C Existing and Proposed Conditions Drainage Area Maps Appendix D Existing and Proposed Conditions Land Use Mapping Appendix E CD with Digital Copy of EPA SWMM Models Appendix F Outlet Protection Calculation Appendix G Water Quality Calculation and Stage -Storage Relationship for SCM Appendix H Anti -Floatation Calculation for Riser Appendix I Detention Time Calculation Appendix J Maintenance and Operation Plan HAECO Facility Improvements Project Page ii Stormwater Report Section 1: Introduction 1.1 Project Description This report supports the design of the stormwater control measures (SCMs) needed to develop the HAECO Facility Improvements project at the Piedmont Triad International Airport in compliance with the North Carolina Department of Environmental Quality (NCDEQ) regulatory requirements for new development at an airport. A 0.8 -acre high flow rate bioretention pond is being proposed to meet the regulatory water quality requirements for NCDEQ. This bioretention pond was designed to infiltrate runoff generated from the 1St inch of rainfall at a relatively high rate to satisfy the water quality requirements outlined in Session Law 2012-200. As shown in the concept plans included in Appendix A, the airport is proposing a 15.9 -acre site development project including the construction of the following: ♦ 5.06 acres of new impervious area associated with the proposed HAECO hangar; ♦ 5.51 acres of new impervious area associated with the proposed HAECO apron; ♦ 0.32 acres of new impervious area associated with the proposed HAECO fire lanes flanking the proposed hangar; ♦ 0.09 acres of new impervious area associated with the proposed HAECO sidewalks; ♦ Removal of an existing fire suppression pond; ♦ Removal of an existing 1.1 -acre wet pond being used for detention and water quality; and ♦ Construction of a new 0.7 -acre high flow rate bioretention pond that will result in infiltration of the water quality rainfall event. In addition to providing treatment for the proposed new impervious areas associated with the HAECO Facility Improvements project, the SCM will replace the treatment being provided by an existing wet pond located on the eastern side of the site. This existing wet pond has a contributing drainage area of 15.29 acres with 14.04 acres of impervious cover. In total, the proposed SCM will need to provide treatment for 24.61 acres of impervious cover as shown in the following table: Table 1: Summary of Area Required for Treatment Location Proposed Hangar Proposed Apron Proposed Access Route Proposed Sidewalk Existing HAECO Site (Wet Pond) HAECO Facility Improvements Project Stormwater Report Impervious Cover (acres) 5.06 5.11 0.32 0.09 14.03 TOTAL = 24.61 acres Page 1-1 Section 1: Introduction As outlined in this report, the proposed SCM will provide water quality treatment for a total of 44.52 acres of impervious cover which exceeds the minimum required for treatment (24.61 acres). As a result, the airport is formally requesting water quality treatment credits to offset a site development project in the future with up to 19.91 acres of impervious surface. The following table summarizes the water quality treatment credits being requested: Table 2: Summary of Water Quality Treatment Credits Description Impervious Area (acres) Required Area for Treatment 24.61 Provided Area for Treatment 44.52 DIFFERENCE = 19.91 acres Also provided in this report is an evaluation of downstream flooding resulting from the proposed site changes. The analysis showed that the proposed project will cause increases to peak flows downstream but will not flood insurable structures, roads, or cause damage to existing property or the existing Harris Teeter detention pond. HAECO Facility Improvements Project Page 1-2 Stormwater Report Section 2: Hydrology and Hydraulics 2.1 Methodology The Environmental Protection Agency (EPA) Storm Water Management Model 5.0 (SWMM) was used to size the proposed collection system, flow splitters, and bioretention pond with riser. SWMM simulates the surface runoff response to precipitation for an interconnected system of surfaces, channels, closed pipe systems, culverts, flow splitters, and ponds. SWMM is an ideal model for a complex drainage system such as the one seen at the HAECO site as it combines hydrology and hydraulics and allows the user to not only size on-site improvements but also evaluate downstream flooding. Combining hydrology and hydraulics eliminates the need to iterate between a hydrologic model and a hydraulic model which eliminates the potential for errors. 2.2 Hydrology Input data for the model was developed using topographic, landuse, and soils maps in GIS to delineate and calculate the basin areas, percent impervious, and Natural Resources Conservation Service (NRCS) hydrologic parameters. The precipitation data for the 24-hour duration, Type II storm was used to represent the synthetic rainfall event. SWMM estimates surface runoff for a sub -basin based on percent impervious, basin width, basin slope, and NRCS curve number for the unconnected pervious areas. A copy of the SWMM input values for the existing and proposed conditions is provided in Appendix B. Unit hydrographs are translated using the watershed basin and slope parameters. This is unique to SWMM. 2.2.1 Drainage Areas Drainage area maps for the existing and proposed conditions have been included with this report in Appendix C. Drainage areas were delineated using the following topography: ♦ 2 -foot contour interval existing conditions topographic mapping from Guildford County GIS; ♦ 1 -foot contour interval topographic mapping provided by Michael Baker & Associates titled "ADP Mapping (May 2014).dwg"; ♦ Inventory mapping of pipes and catch basins provided by Michael Baker & Associates titled "ADP Mapping (May 2014).dwg"; and ♦ 1 -foot contour interval proposed conditions topographic mapping generated by WK Dickson. 2.2.2 Rainfall Rainfall distributions for the SWMM model were derived using the NRCS Type II standard distribution. Total rainfall depths for the modeled frequency storms were HAECO Facility Improvements Project Page 2-1 Stormwater Report Section 2: Hydrology and Hydraulics obtained online from the NOAA's Nation Weather Service website. Table 3 shows the total rainfall depths used for this study. Table 3: Design Storm Rainfall Depths Design Storm Rainfall Depth (in) 2 -year, 24-hour 3.31 10 -year, 24-hour 4.77 25 -year, 24-hour 5.65 50 -year, 24-hour 6.35 100 -year, 24-hour 7.07 Source: NOAA's Nation Weather Service website 2.2.3 Land Use Land use is the watershed cover condition as it relates to the actual type of development within the watershed. Land use influences the runoff characteristics of a sub -basin, and combined with other basin characteristics is used to determine the percent impervious and NRCS curve number for the basin. Appendix D shows the existing and proposed conditions land use mapping for this project. Input data for the existing and proposed percent impervious values is found in Table 4. 2.2.4 Hydrograph Translation NRCS methodologies typically use a time of concentration parameter to help calculate the response of the watershed to rainfall. SWMM uses watershed basin width and slope parameters to create the unit hydrograph used in the model that will translate the rainfall into runoff. The watershed width is a parameter unique to SWMM that helps define the watershed shape by taking the watershed area and dividing it by the length of the longest flow path. Additionally, SWMM requires input of a basin slope in the calculations used to translate the hydrograph. The basin slope is the maximum grade change from the upstream end of the watershed to the downstream end divided by the length of the longest flow path. The sub -basin slopes and widths are included in Table 4. HAECO Facility Improvements Project Page 2-2 Stormwater Report Section 2: Hydrology and Hydraulics Table 4: Summary of Hydrologic Input Data 2.2.5 NRCS Curve Numbers The NRCS curve number approach was used in computing the runoff response in SWMM. Runoff curve numbers (RCNs) were generated for the pervious areas of the sub -basins using the NRCS document entitled Urban Hydrology for Small Watersheds, dated June 1986 and commonly referred to as TR -55. This method relates the drainage characteristics of soil group, land use category, and antecedent moisture conditions to assign a runoff curve number. The runoff curve number and an estimate of the initial surface moisture storage capacity are used to calculate a total runoff depth for a storm in HAECO Facility Improvements Project Page 2-3 Stormwater Report Existing/ Existing Proposed Proposed Proposed Drainage Drainage Proposed Percent Percent Basin Basin Basin Area Pervious Impervious Impervious Slope Width ID (acre) RCN (M M M (feet) 10 77.1 74 31% 31% 0.6% 1019 20 28.8 74 34% 34% 0.8% 995 30 19.3 74 40% 40% 1.0% 454 40 4.1 74 44% 44% 1.1% 176 50 3.6 74 21% 21% 1.9% 301 60 5.2 74 8% 8% 1.7% 269 70 9.2 74 100% 100% 1.3% 331 80 14.3 71 99% 100% 1.9% 568 90 8.9 74 24% 82% 2.0% 286 100 19.3 74 82% 43% 0.6% 573 110 6.1 74 43% 29% 1.3% 531 120A 13.95 74 92% 85% 1.6% 409 120B 2.43 74 92% 50 3.3 165 130 4.5 74 92% 47% 3.7% 207 142 9.9 74 44% 32% 5.0% 608 144-A 0.84 74 2% 100% 0.5% 266 144-B 0.86 74 2% 100% 0.5% 302 144-C 0.75 74 2% 100% 0.5% 239 144-D 0.88 74 2% 100% 0.5% 252 144-E 0.51 74 2% 100% 0.5% 126 144-F 0.47 74 2% 100% 0.5% 201 144-G 0.54 74 2% 100% 0.5% 220 144-H 1.74 74 2% 42% 0.5% 320 146-A 0.81 74 2% 100% 0.5% 86 146-B 1.71 74 2% 100% 0.5% 184 146-C 1.53 74 2% 100% 0.5% 164 146-D 1.99 74 2% 100% 0.5% 193 146-E 0.67 74 2% 28% 0.5% 274 148 1.08 74 2% 10% 16.2% 171 2.2.5 NRCS Curve Numbers The NRCS curve number approach was used in computing the runoff response in SWMM. Runoff curve numbers (RCNs) were generated for the pervious areas of the sub -basins using the NRCS document entitled Urban Hydrology for Small Watersheds, dated June 1986 and commonly referred to as TR -55. This method relates the drainage characteristics of soil group, land use category, and antecedent moisture conditions to assign a runoff curve number. The runoff curve number and an estimate of the initial surface moisture storage capacity are used to calculate a total runoff depth for a storm in HAECO Facility Improvements Project Page 2-3 Stormwater Report Section 2: Hydrology and Hydraulics a basin. 2.2.6 Channel/Storage Routing Flood peaks attenuate, or reduce, as they travel downstream due to the storage characteristic of the channel itself. Channel routing was simulated in the hydraulic block of SWMM. Routing was modeled using dynamic wave routing. Dynamic wave routing uses the actual shape and condition of the stream channel input into the hydraulic model to calculate the attenuated downstream flows. 2.2.7 Summary of Hydrologic Model Results The EPA SWMM model was used to compute peak runoff for the 2-, 10-, 25-, 50- and 100- year design storms for the existing and proposed conditions. The results of the existing conditions hydrologic model are summarized in Table 5. A CD containing the digital files for the SWMM model is included in Appendix E. Table 5: Comparison of Peak Flows at Radar Road Condition WQ Event 2 -year (cfs) (cfs) Existing 12 63 Proposed 40 288 Storm Event 10 -year 25 -year 100 -year (cfs) (cfs) (cfs) 108 138 185 420 466 513 Although Session Law 2012-200 precludes the project from having to provide detention, a detailed hydrologic and hydraulic evaluation was performed to confirm there are no adverse impacts to downstream properties with regards to flooding. A summary of this evaluation is found in the following Hydraulics section of the report. 2.3 Hydraulics EPA SWMM 5.0 was chosen as the hydrologic/hydraulic model because of its ability to model complex drainage systems and to evaluate downstream flooding. The project involves the construction of a single central high flow rate bioretention pond to provide water quality treatment for the proposed site development. The airport desires to reduce the potential for bird strikes by eliminating two existing wet ponds referred to in this report as the fire suppression wet pond and the existing HAECO site wet pond. The existing conditions SWMM model attenuates peak flows through these two ponds to more accurately determine the proposed projects effects on peak flows. To fully evaluate the project's impacts on downstream properties, the SWMM model was extended through the Harris Teeter distribution site and immediate downstream open channel. In addition, a HEC -RAS model was developed to provide a quality control measure for the changes to water surface elevations developed using EPA SWMM. HAECO Facility Improvements Project Page 2-4 Stormwater Report Section 2: Hydrology and Hydraulics 2.3.1 Energy Loss Coefficients Contraction and expansion of flow produces energy losses caused by transitioning. The magnitude of these losses is related to the velocity and the estimated loss coefficient. Where the transitions are gradual, the losses are small. At abrupt changes in cross- sectional area, the losses are higher. Energy losses resulting from expansion are greater than losses associated with contraction. Energy loss coefficients used for the SWMM models are presented in Table 6: Table 6: Energy Loss Coefficients Type of Transition Expansion Contraction None 0 0 Manhole/Inlet 0.35 0.25 Culvert 1.0 0.9 - Projecting from fill CMP Open Channel 0.3 0.1 Additional energy losses for structures having bends were divided between the two joining pipes. The bend losses used for this project are based on NCDOT values, and are shown below in Table 7. Table 7: Bend Loss Coefficients Angle (°) Loss Coefficient Angle (°) Loss Coefficient 90 0.70 40 0.38 80 0.66 30 0.28 70 0.61 25 0.22 60 0.55 20 0.16 50 0.47 15 0.10 2.3.2 Starting Water Surface Elevation The downstream limit of the HAECO Facility Improvements study area is located near the mouth of Horsepen Creek. The starting water surface elevations for the SWMM models were generated using the normal depth method based of the channel slope at the outfall (0.008 ft/ft). 2.3.3 Model Run Descriptions The EPA SWMM model was used to compute flood elevations at each structure located in the HAECO Facility Improvements project study area for the water quality event, 2-, 10-, 25-, 50- and 100 -year storm events. A digital copy of the SWMM model is included on the CD provided in Appendix E. 2.3.4 Hydraulic Evaluation of Radar Road The following table summarizes the performance of the twin 8.9' x 6.6' corrugated metal pipe (CMP) arches at Radar Road: HAECO Facility Improvements Project Page 2-5 Stormwater Report Section 2: Hydrology and Hydraulics Table 8: Culvert Performance for at Radar Road Flood Culvert Invert Elevation levation (feet NAVD 1988) Roadway Elevation (feet NAVD 1988) Existing Water Surface Elevations (feet NAVD 1988) Proposed Water Surface Elevations (feet NAVD 1988) WQ Event 831.29 840.90 831.76 832.14 2 -Year 831.29 840.90 832.38 834.07 10 -Year 831.29 840.90 832.72 835.59 25 -Year 831.29 840.90 832.89 836.23 100 -Year 831.29 840.90 833.19 837.18 Although there are increases to peak flows, the downstream drainage system can accommodate these increased flows. The existing twin 9.8' by 6.6' arched CMPs pass 896 cfs when flowing full. The 104" diameter closed CMP located at the Harris Teeter distribution center conveys 753 cfs when flowing full. The Radar Road culverts and Harris Teeter closed pipe will be flowing approximately half full during a 100 -year storm event therefore there are no impacts to the performance of either of these drainage systems. 2.3.5 Evaluation of Downstream Flooding Approximately 85 feet from the top of bank (in the left overbank) is the toe of the water quality pond embankment for the Harris Teeter distribution center. For this reason, a check was made to confirm that the additional flows from the HAECO Facility Improvements project would not cause adverse impacts to the existing water quality pond embankment. Table 9 summarizes the size, slope and hydraulic characteristics of the channel located immediately downstream of Harris Teeter. Table 9: Hydraulic Summary of Harris Teeter Open Channel Bottom Top Side Channel Channel Floodplain Depth Width Width Slopes Slope Capacity Capacity (feet) (feet) (feet) (ft/ft) (ft/ft) (cfs) (cfs) 10 25 4 2:1 0.014 300 2,150 Assumed Manning's 'n' value= 0.06 Floodplain capacity is the flow needed to inundate the toe of the existing Harris Teeter pond As shown in Table 9, the existing channel can almost convey the proposed conditions 10 -year flood without overtopping its banks. The flow needed to inundate the lowest toe elevation of the Harris Teeter pond is 2,150 cfs which is significantly more than the 513 cfs that will leave the proposed HAECO site. This existing open channel extends approximately 290 feet downstream of the Harris Teeter culvert prior to entering Horsepen Creek which is a FEMA stream with an 832 - acre (1.3 square miles) drainage area and 100 -year peak flow of 1,598 cfs. On the upstream side of Radar Road (along Horsepen Creek), the drainage area increases to HAECO Facility Improvements Project Page 2-6 Stormwater Report Section 2: Hydrology and Hydraulics 1,344 acres (2.1 square miles) with a 100 -year peak flow of 3,018 cfs. A field walk and inspection of aerial topography shows this reach of Horsepen Creek does not have any insurable structures located in the reach upstream of Radar Road where the 329 cfs increase would be roughly 10% of the total flow in Horsepen Creek. As shown in this report, the proposed HAECO Facility Improvements Project will not adversely cause flooding downstream to an insurable structure or road. Figure 1: FEMA FIRM Panel 2.3.6 Closed Drainage Systems Closed systems were designed to pass the 10 -year flood without surcharging the pipe. With the exception of the SCM underdrain system, all drainage pipes are reinforced concrete (RCP). 2.3.7 Outfall Protection for Closed Drainage System Rip -rap pads are proposed at two locations in the high flow rate bioretention. These outfalls are located where the flows enter back into the natural drainage system or the bioretention ponds. The NY DOT method was used to design the length, width, depth and size of the rip -rap pads. Appendix F shows the calculation used to size the rip -rap pads. HAECO Facility Improvements Project Page 2-7 Stormwater Report Section 3: Water Quality Compliance 3.1 Overview To satisfy the water quality requirements outlined in Session Law 2012-200, a proposed 0.8 -acre high flow rate bioretention pond is being proposed. Session Law 2012-200 requires runoff generated from the 1st inch of rainfall for a development project shall be infiltrated into the ground. There are no specific requirements to remove total suspended solids (TSS), nitrogen, or phosphorus. In addition, there are no requirements to detain the 1 -year or any other storm event to at or below pre -project conditions. As shown in this report, the proposed high flow rate bioretention pond exceeds the minimum infiltration requirements set forth in Session Law 2012-200. 3.1.1 Proposed Impervious Areas The separately attached construction plans and concept plan provided in Appendix A show the proposed pond, new and existing impervious areas, location of flow splitters and overall site layout. The following table summarizes the proposed impervious areas associated with the HAECO Facility Improvements project: Table 10: Minimum Area of Impervious Cover Required for Treatment Location Impervious Cover (acres) Proposed Hangar 5.06 Proposed Apron 5.11 Proposed Fire Access Roads 0.32 Proposed Sidewalk 0.09 Existing HAECO Site to the East 14.03 TOTAL = 24.61 acres Because the existing fire suppression pond is being abandoned as part of this project, the proposed SCM will need to be designed to accept runoff from the system currently going to the existing fire suppression pond. The stormwater runoff generated in sub - basins 60, 70 and 80 will be redirected into the proposed SCM. Appendix C highlights the areas that will drain to the pond along with a breakdown for the impervious area contributed from each sub -basin. As a result, an additional 20.49 acres of impervious area will be infiltrated in the proposed SCM as shown in the following table: Table 11: Proposed Impervious Cover to SCM Location Impervious Cover (acres) Proposed Hangar 3.35 Proposed Apron 5.11 Proposed Fire Access Roads 0.32 Proposed Side Walk 0.09 Existing HAECO Site to the East 11.92 Sub -Basin 60 0.42 Sub -Basin 70 9.22 Sub -Basin 80 14.09 TOTAL = 44.52 acres HAECO Facility Improvements Project Page 3-1 Stormwater Report Section 3: Water Quality Compliance In total, the proposed SCM will have a contributing drainage area of 54.0 acres with 44.52 acres of impervious cover. 3.1.2 High Flow Rate Bioretention Pond Design Criteria The State BMP Manual does not specifically have a set of design guidelines for a high flow bioretention pond so the following guidelines were used in the design of the proposed high flow bioretention pond: ♦ Infiltrate 100% of the runoff generated from the 1St inch of rainfall; ♦ Side slopes shall be no steeper than 3(H):1(V); ♦ SCM shall be located in a recorded drainage easement; ♦ A bypass or internal overflow is required for bypassing storm flows in excess of the design flow; ♦ Media permeability shall be between 6 and 10 inches per hour with a targeted detention time of 10 to 15 hours for infiltrating the water quality volume; ♦ Ponding depth for the water quality event shall be limited to 4.0 feet; ♦ Media depth will be 2 feet for each of the two soil media zones of the bioretention pond; ♦ An underdrain shall be located under the soil media to keep the pond dry and prevent groundwater from entering the pond; and ♦ A rip -rap energy dissipater shall be located at the outfall of each pipe entering the pond. 3.1.3 Water Quality Volume (WQV) The volume of runoff generated from the 1St inch of rainfall was calculated using an in- house spreadsheet based on the Schuler Simple Method. This spreadsheet shows the calculated water quality volume along with proposed SCMs stage -storage sizing (see Appendix G). The following table summarizes the minimum required volume along with the provided volume: Table 12: Calculated Storage Volumes Description Impervious Area Surface Runoff (acres) (ft3) Required Area for Treatment 25.01 72,582 Compensatory Treatment of Sub -basins 60, 70, 80 23.72 82,679 Total Provided Area for Treatment 44.52 155,260 Net Credit for WQ Treatment 19.51 82,678 As shown in Table 12, the proposed high flow rate bioretention pond will infiltrate an additional 82,678 cubic feet of runoff and 19.51 acres of impervious cover more than required. HAECO Facility Improvements Project Page 3-2 Stormwater Report Section 3: Water Quality Compliance 3.1.4 Pond Design Summary A concrete riser structure is proposed to control flows leaving the high flow rate bioretention pond. The primary spillway will include the following elements: a poured, reinforced concrete box riser and reinforced concrete outfall pipe with gaskets at joints. Because the weir length on these structures is 12' and the flows entering the ponds are generally very small, there were no emergency spillways proposed for the pond. The following is a summary of the design for the proposed high flow rate bioretention pond (See the separately attached plan set for additional details): ♦ Surface Area: The proposed high flow rate bioretention pond is larger than the minimum size needed to achieve the water quality goals of the project. The surface area of the pond was achieved by targeting a pond depth of less than 4.0 feet and a detention time between 10 and 40 hours. The more well -draining the soils the smaller the footprint of the pond needed to drain the pond in approximately 10 hours. As shown in this report, the surface area that drains the pond in approximately 11 hours is 28,005 square feet (0.64 acres). ♦ Primary Outfall: A concrete box riser with an outside dimension of 7'x7' is proposed with a primary weir elevation set at 583.75 feet NAVD 1988. The total weir length of the primary outfall is 18 feet (four 4.5' long weirs). ♦ Emergency Overflow: The primary spillway was designed to pass flow larger than the 100 -year flood without overtopping the top of dam. A 15' wide rip -rap lined emergency overflow will convey flows over the top of dam should the riser be clogged for some unforeseen reason. This emergency spillway ties into a grass lined swale until it reaches an 18" RCP with a flared section opening. ♦ Top of Dam: The top of dam is set at elevation 855.25 feet which is approximately 1.7 feet above the 100 -year flood elevation. The total dam height measured from the toe of the embankment on the downstream side is approximately 3.0 feet. The following table summarizes the water surface elevations at the proposed pond for the water quality event, 1-, 10- and 100 -year floods: Table 13: Water Surface Elevations at Proposed Pond Water Quality 1 -Year Storm Event (NAVD'88) 853.28 853.48 10 -Year Storm 100 -Year Storm (NAVD'88) (NAVD'88) 853.50 853.52 Riser The riser detail provided in the separately attached plan set shows the 6'x6' concrete box to control water surface elevations inside the proposed SCM. The primary spillway was set at elevation 853.30 feet which is the dynamic elevation calculated inside EPA SWMM for the water quality storm event (an NRCS Type I1 distribution with 1.0 inches of HAECO Facility Improvements Project Page 3-3 Stormwater Report Section 3: Water Quality Compliance rainfall). The riser has a 42" diameter RCP barrel that conveys flow from the pond to a new 48" diameter closed drainage system. This 48"diameter closed system conveys the by-pass flows for larger storm events from the eastern side of the existing HAECO development. An anti -floatation calculation (See Appendix H) was performed for the pond riser resulting in a factor of safety of 1.22. This calculation ignores the friction forces of the underlying soil and therefore a factor of safety larger than 1.22 would be achieved in real conditions. Because this is a dry pond and water levels will rarely reach 6" above the crest of the weir therefore a factor of safety of 1.22 is acceptable. Flow Splitters Three flow splitters are proposed to divert stormwater runoff from the proposed closed drainage system into the high flow rate bioretention pond. For water quality rainfall event (1.0 inch of rain), 100% of the runoff generated will flow directly into the high flow rate bioretention pond. Inside each flow splitter is a weir wall that will direct flows generated from larger storm events into a closed by-pass pipe. The elevation of this weir wall was calculated in EPA SWMM by iteratively adjusting the elevation of the wall until no flow was being diverted in the water quality rainfall event. The splitter box located just north and west of the pond (Structure 5) will require a special design. Flows that go over the weir wall will drop into a concrete manhole structure and eventually into the sites main 72 inch diameter RCP. The following table summarizes the key elevations for the three proposed concrete flow splitters: Table 14: Summary of Flow Splitter Design Pipe to Pond Pipe to Pond Diameter (in) Splitter # Invert Elevation Weir Wall Height 15" (feet NAVD 1988) (ft) 1 (structure 20) 872.21 0.85 2 (structure 25) 855.10 2.75 3 (structure 5) 851.68 1.45 Pipe Sizes Pipe to Pond Entering Splitter Diameter (in) Box (in) 10 -Year Storm Event 30" 15" 48" 24" 54" and 42" 30" The separately attached design plans provide additional details on the size and construction of the flow splitters being used for this project. Table 15: Flow Splitter Performance Splitter # Water Quality Event 10 -Year Storm Event Flow To Pond Flow Around Pond Flow To Pond Flow Around Pond (cfs) (cfs) (cfs) (cfs) 1 (structure 20) 4 0 6 17 2 (structure 25) 10 0 20 50 3 (structure 5) 27 0 40 121 As shown in Table 15, approximately 67% of the peak flows from the larger storm events will be diverted around the pond. HAECO Facility Improvements Project Page 3-4 Stormwater Report Section 3: Water Quality Compliance Detention Time and Soil Media for High Flow Rate Bioretention Pond Per discussions with DEQ, it was agreed that the proposed high flow rate bioretention pond would detain the water quality event for between 10 and 40 hours. To achieve this goal, a well -draining sand media is needed that promotes infiltration at a rate that is not too quick (3 or 4 hours) and not too long (over 40 hours). With an assumed infiltration rate of 10 inches per hour for this well -draining sand, a footprint was iteratively determined until the time to drain the pond was 10 hours. This area was calculated to be 14,563 square feet. For those areas outside the well -draining sands an infiltration rate of 2 inches/hour was assumed. As shown in Appendix I, the combined flow rate passing through the soil media and leaving the pond is 3.9 cfs. For the area of well -draining sand, the construction of the high flow rate bioretention pond will mimic the design of a PGA golf green. It is assumed that the best draining soils that can be stockpiled from the onsite borrow area will be used for those areas outside the well -draining sands. At a minimum this media in Zone 1 will have a permeability of 2 inches/hour. The following is a summary of the construction for the area of the pond that mimics the PGA golf green: Option #1 for Zone 2 (No. 57 Stone at base) • 12" thick base of No. 57 stone (approximately 3/4' in size) • 4" of washed sand • 2' of well -draining sand -soil mix (with a permeability of 10 inches/hour) Option #2 for Zone 2 (Pea Gravel at base) • 12" thick base of peak gravel (100% passage of 3/8" sieve) • 2' of well -draining sand -soil mix (with a permeability of 10 inches/hour) Specifications for the two soil zones will be prepared at final design. Channel Liner As shown on the separately attached design plans, two shallow rip -rap lined swales are proposed to convey runoff from small storm events to the side of the SCM with the riser. The swales were designed to be relatively shallow (1 foot in depth) and flat in order to promote infiltration. It was assumed that the entire pond bottom would be inundated fairly quickly and the need to size a large swale to minimize erosion would not be necessary. A calculation for the channel liner design is provided in Appendix J. Maintenance and Operation Procedures A maintenance and operation plan for the bioretention facilities has been included with this report as Appendix K. HAECO Facility Improvements Project Page 3-5 Stormwater Report Section 3: Water Quality Compliance 3.2 Conclusion As shown in this report, the proposed high flow rate bioretention pond is designed to bring the HAECO Facility Improvements project at the Piedmont -Triad International Airport in compliance with the State's requirements for water quality as outlined in Session Law 2012-200. By diverting runoff for the water quality rainfall event from basins 60, 70 and 80 into the proposed SCM, the airport is providing treatment for 44.52 acres of impervious cover. As shown in this report, the proposed SCM is providing approximately 19.51 acres more than the minimum required amount. The airport would like to request a water quality credit to offset the need to provide or minimize treatment with a future onsite development. HAECO Facility Improvements Project Page 3-6 Stormwater Report WDICKSON communily Inlfaslructure consultants Proposed Concept Plan - Appendix A High Flow Rate Bioretention Pond Piedmont -Triad International Airport HAECO Site Development 200 100 1 inch = 200 feet 200 Feet Project: HAECO Facility Improvement @ PTIA, Greensboro, NC Prepared by: DJK Date: November 9, 2015 SWMM Input Data Appendix B EXISTING CONDITIONS SUBBASINS Flow Basin Percent SWMM Sub- Pervious Area Width Elevation (sq. ft.) Length Slope Impervious Basin ID RCN(acres)Area (ft.) Change (ft.) (ft ) M M 10 74 77.1 3356329 3294 1019 21 0.64% 31% 20 74 28.8 1253061 1259 995 11 0.83% 34% 30 74 19.3 842697 1856 454 19 1.03% 40% 40 74 4.1 180429 1027 176 12 1.12% 44% 50 74 3.6 156421 520 301 10 1.92% 21% 60 74 5.2 225908 841 269 14 1.66% 8% 70 74 9.2 401743 1215 331 16 1.34% 100% 80 71 14.4 627272 1095 573 21 1.91% 100% 85 71 3.0 131013 338 388 36 10.65% 24% 90 74 8.9 388935 1359 286 27 1.98% 82% 100 74 19.3 840092 1465 573 9 0.58% 43% 110 74 6.1 263574 496 531 7 1.31% 29% 120 74 15.3 665778 958 695 25 2.56% 92% 130 74 4.5 195877 944 207 35 3.65% 44% 142 74 9.4 407511 707 576 35 4.95% 26% 145 74 12.2 529689 1513 350 49 3.25% 2% 240.27 PROPOSED CONDITIONS SUBBASINS Flow Basin Percent SWMM Sub- Pervious Area Width Elevation Area (sq. ft.) Length Slope Impervious Basin ID RCN (acres) (ft.) Change (ft.) (ft.) (%) (%) 10 74 77.05 3356329 3294 1019 21 0.6% 31% 20 74 28.77 1253061 1259 995 11 0.8% 34% 30 74 19.35 842697 1856 454 19 1.0% 40% 40 74 4.14 180429 1027 176 12 1.1% 44% 50 74 3.59 156421 520 301 10 1.9% 21% 60 74 5.19 225908 841 269 14 1.7% 8% 70 74 9.22 401743 1215 331 16 1.3% 100% 80 71 14.09 613567 1095 560 21 1.9% 100% 90 74 8.93 388935 1359 286 27 2.0% 82% 100 74 19.29 840092 1465 573 9 0.6% 43% 110 74 6.05 263574 496 531 7 1.3% 29% 120A 74 13.95 607823 1487 409 25 1.6% 85% 1208 74 2.43 105911 640 165 21 3.3% 50% 130 74 4.50 195877 944 207 35 3.7% 47% 142 74 9.36 407511 707 576 35 5.0% 32% 144-A 74 0.84 38104 143 266 0.715 0.5% 100% 144-B 74 0.86 38293 127 302 0.635 0.5% 100% 144-C 74 0.75 32703 137 239 0.685 0.5% 100% 144-D 74 0.88 38306 152 252 0.76 0.5% 100% 144-E 74 0.51 22097 175 126 0.875 0.5% 100% 144-F 74 0.47 20479 102 201 0.51 0.5% 100% 144-G 74 0.54 23709 108 220 0.54 0.5% 100% 144-H 74 1.74 75931 237 320 1.185 0.5% 42% 146-A 74 0.81 35111 406 86 2.03 0.5% 100% 146-B 74 1.71 74691 406 184 2.03 0.5% 100% 146-C 74 1.53 66657 406 164 2.03 0.5% 100% 146-D 74 1.99 86824 450 193 2.25 0.5% 100% 146-E 74 0.67 29025 106 274 0.53 0.5% 28% 148 74 1.08 47109 275 171 44 16.2% 10% 240.27 �wl< iDICKSON community infrastructure consultants Existing Conditions Drainage Area Map - Appendix C Piedmont -Triad International Airport HAECO Site Development 500 250 0 500 Feet 1 inch = 500 feet I 1 1 �wl< iDICKSON community infrastructure consultants Contributing Drainage Areas and Impervious Cover to SCM - Appendix C 4-1 Piedmont -Triad International Airport r. HAECO Site Development 300 150 0 300 Feet 1 inch = 300 feet I �wl< W DICKSON community infrastructure consultants Existing Landuse Map - Appendix D 4 500 250 0 500 Feet Piedmont -Triad International Airport s HAECO Site Development 1 inch = 500 feet �wl< Proposed Landuse Map - Appendix D 4-500 250 0 500 Feet W DICKSON Piedmont -Triad International Airport s� community infrastructure consultants HAECO Site Development 1 inch = 500 feet 25 z 20 LENGTH MINIMUM U OF THICKNESS STONE STONE �� 15 � r\ 2 STONE LIGHT 6" 6 X O 12" � ` 1 10 O 8 X D 30' 5 STONE HEA VY 23" 10 X D 30" 6 STONE HEAVY 23" 5 m 5 10 �15 DIAMETER OF PIPE IN FEET APPENDIX F ZONE APRON CLASS SIZE LENGTH MINIMUM MATERIAL OF OF OF THICKNESS STONE STONE APRON k OF STONE I STONE FINE J. 4 X 0 9" 2 STONE LIGHT 6" 6 X O 12" 3 STONE MEDIUM l3" 8 X D 18" 4 STONE HEAVY 23" 8 X D 30' 5 STONE HEA VY 23" 10 X D 30" 6 STONE HEAVY 23" 12 X D 30" REQUIRES LARGER STONE OR ANOTHER TYPE OF 7 DEVICE. DESIGN IS BEYOND THE SCOPE OF THIS PROCEDURE. WWDTH V WDTH = DIAMETER f D.4 (LENGTH) : 6� MINIMUM LENGTH TO PREVENT SCOUR HOLE, MIN LENGTH 1D' i i i NAME I 910CHT SIZE SPECIFICATIONS i ' RIP -RAP iI 30% SHALL WEIGH AT LEAST 100 CLASS 1 5 — 200 LBS EACH. NO MORE THAN 102' SHALL NEIGH LESS THAN 15 LBS EACH. 60% SHALL WEIGH AT LEAST 100 20 25 CLASS 2 25 — 250 LBS &L EACH. SS THANA 50 LBS. EACH. EROSION CONTROL STONE CLASS A 2" _ B" 108 TOP & 8OTTOM SIZES NO GRADATION SPECIFIED. CLASS B 15 — 300 NO GRADATION SPEC0ED. STRUCTURE LOCA17ON Q—FLDW DIAMETER OF OUTLET DEPTH N1DOT APRON APRON APRON APRON RIP—RAP REMARKS OR (CFS) PIPE VELOCITY OF FLOW ZONE LENGTH WIDTH 3Do WWDTH V THICKNESS CLASS LINE (IN.) (FTS.) (FT.) (FT) (FL) (FT) (IN.) PADA PIORETENTION POND 3D 36 4.J 1.3 2 18 9 10 24" TYPE I RIP—RAP PAD,f2 l EVORETENTION POND 26 24 5.4 1.4 2 - 15 6 8 24" TYPE I RIP—RAP 4 SOURCE; BANK & CHANNEL LINING PROCEDURES, NEW YORK DEPARTMENT OF TRANSPDRTAlION, DIVISION OF DESIGN AND CONSTRUCRON, 1971. 7za 04, Me r�N1ER DRIVE W,K1 720 0N, NC Z7Ba7 DICKSON (918) 7B2—a19B orcr<. �uans North t. o ha communityGaargia infrastructure consu€tants samh Cwdma no tla Appendix G Water Quality Volume and Stage Storage at Proposed Central High Flow Bioretention Pond Project: HAECO Facility Improvement @ PTIA, Greensboro, NC Prepared by: DJK Checked by: Date: November 3, 2015 Summary of Inovervious Areas Stage -Storage from Contours - Proposed Detention Facility - High Flow Bioretention Pond Impervious Area Total Drainage Description ac) Area ac) Basin 60 .42 5.1 Basin 70 9.22 9.22 Basin 80 14.09 14.09 Basin 120 11.92 13.95 ProposedApron 5.11 6.59 Proposed Hangar 5.06 5.95 Proposed Access Rd 0.32 0.66 Hangar Area Not Draining to Pond -1.71 -1.71 Proposed Sidewalk 0.09 0.09 Tota( 44.52 54.03 EI,yiA - . Planners . S. -y - L -d -Pt Atthile 15 R„ Runoff coefficient The R. is a measure of the site response to rainfall events, and in theory is calculated as: R,. = r y, where r and p are the volume of storm runoff and storm rainfall, respectively, expressed as inches. The R, for the site depends on the nature of the soils, topography, and cover. However, the primary influence on the R,, in urban areas is the amount of imperviousness of the site. Impervious area is defined as those sufaces in the landscape that cannot infiltrate rainfall consisting of building rooftops, pavement, sidewalks, driveways, etc. In the equation R„ _ 0.05 + 0.009(1), "P' represents the percentage of impervious cover expressed as a whole number. A site that is 75% impervious would use I = 75 for the puposes of calculating R.. Calculate the runoff coefficient: Rv=0.05+0.009(la) Calculate the required volume to be detained for the first 1" of runoff: Rv = runoff coefficient = storm runoff (inches) / storm rainfall (inches) Volume = (Design rainfall)(Rv)(Drainage Area) la = percent impervious = impervious portion of the drainage area (ac.)/drainage area (ac.) Volume = 1" rainfall * Rv * 1/12 (feet/inches) * Drainage Area la 82.40 Volume = 3.6 acre-feet Rv= 0.79 (in./in.) Volume = 155,260 W Stage Storage Relationship V.2 = %(A, +AZ+ A, • AZ Incremental volume determined using "conic" method as described in USACE HEC -1 manual Pond bottom Elevation that exceeds the water quality volume (assuming static elevation with no infiltration) Stage -Storage from Contours - Proposed Detention Facility - High Flow Bioretention Pond S S SW MM CONTOUR INCREMENTAL ACCUMULATIVE TOTAL NODE INVERT CONTOUR DEPTH AREA VOLUME VOLUME VOLUME (FT) (FT) (FT) (AC) (SF) (GAL) (CF) (AC -FT) (GAL) (CF) (AC*FT) (%) 848.50 848.50 0.00 0.00 1 849.00 0.50 0.00 2 6 1 0.000 6 1 0.000 0% 850.00 1.50 0.00 319 2 0.000 24 3 0.000 0% Pond Bottom 851.00 2.50 0.33 14,563 36842 4925 0.113 36,866 4,928 0.113 2% 1 852.00 3.50 0.56 24,328 143909 19238 0.442 180,775 24,166 0.555 8% 853.00 4.50 0.60 26,138 188715 25228 0.579 369,490 49,394 1.134 17% 854.00 5.50 0.64 28,005 202469 27066 0.621 571,959 76,460 1.755 26% 855.00 6.50 0.69 29,929 216648 28962 0.665788,607 105,421 2.420 36% 856.00 7.50 0.73 31,910 231254 30914 0.710 1,019,862 136,336 3.130 47% 856.60 8.35 0.76 33,133 145958 19512 0.4481, 165,819 155,847 3.578 54% 857.00 8.50 0.78 33,948 246287 32924 0.756 1,266,148 169,259 3.886 58% 858.00 9.50 0.83 36,043 362123 48409 1.111 1,628,271 217,668 4.997 75% 859.00 10.50 0.88 38,196 539362 72102 1.655 2,167,634 289,770 6.652 100% Incremental volume determined using "conic" method as described in USACE HEC -1 manual Pond bottom Elevation that exceeds the water quality volume (assuming static elevation with no infiltration) Riser Structure Flotation Calculation Project: HAECO Site Development Prepared by: DJK Dated: 11-3-15 Appendix H _alc QC Check on Calcs Inside Lgth (ft) (perpendicular to flow) Inside Width (ft) Outside Loth (ft) (perpendicular to flow)1 Bottom of pond with regards to soil (invert of underdrain system is 848.5 Invert Out Elev. 1 6.00 5.30 5.30 0.67 I 0.50 1.25 848.00 Primary Weir Elev. 853.30 0.00 0.00 42.00 9.62 Overflow Weir Elev. 853.30 Concrete weight (lbs/cu ft) Water weight (lbs/cu ft) (Secondary Weir Hght (ft) 1.50 99.20 Weir capacity Secondary Weir Width (ft) 4.67 calc Primary Weir Hght (ft) 1.50 calc Primary Weir Width (ft) 4.67 calc Top of Box Elev. 855.30 calc Appendix H _alc QC Check on Calcs Inside Lgth (ft) (perpendicular to flow) Inside Width (ft) Outside Loth (ft) (perpendicular to flow)1 4.67 I 4.67 6.00 Outside Width (ft) Primary weir hgth (ft) (CALCULATED) 1 Overflow weir hgth (ft) (CALCULATED) Wall thickness (ft) Top thickness (ft) Base thickness (ft) 1 6.00 5.30 5.30 0.67 I 0.50 1.25 Inside width of box 5.67 Orifice diameter (in) ,Orifice area (sq -ft) Outlet pipe dia (in) Outlet pipe area (sq ft) 0.00 0.00 42.00 9.62 7.00 Concrete weight (lbs/cu ft) Water weight (lbs/cu ft) 146.00 62.40 Probable �Str volume (cu -yd) 4.89 Height of box (below top) 4.8 Str weight (lbs) 19,267 81.066667 cu ft Buoyant force (lbs) 15,837 _alc Thickness of top Resultant weight (lbs) 3,430 Volume of top 24.5 cu ft Factor of Safety 1.22 61.25 cu ft Bearing Weight (lbs/sq ft) 535.19 Weight of Concrete Appendix H _alc QC Check on Calcs _alc Check on Volume _alc Inside width of box 5.67 _alc Outside width of box 7.00 Area of inside box 32 Area of outside box 49 Design Input (Target factor of safety of 1.2) Height of box (below top) 4.8 Net Volume of Walls 81.066667 cu ft Top Area of structure 49 _alc Thickness of top 0.50 Volume of top 24.5 cu ft :alc Volume of base 61.25 cu ft Total Volume of Concrete 166.81667 Weight of Concrete 24,355 Conservative Assumptions: Bouyant force measured at top of structure lid 100 -year flood depth is 8.6 feet in depth (calculation went to elevation 9.5 feet) Weight of soil on outfall pipe not accounted for in calculation Anti-Floatation.xls Volume of displaced water 320.95 cu ft Unit weight of water 62.4 Force of displaced water 20,027 Factor of Safety 1.22 Detention Time and Design of High Flow Rate Media Project: HAECO Facility Improvement @ PTIA, Greensboro, NC Prepared by: DJK Checked by: Date: October 23, 2015 Description Basin 60 Basin 70 Basin 80 Basin 120 Proposed Apron Proposed Hangar Proposed Access Rd Total Impervious Area (ac) 0.4 9.2 14.1 11.9 5.1 5.1 0.3 44.5 Total Drainage Area (ac) 5.2 9.2 14.1 14.0 6.6 6.0 0.7 54.0 Calculate the runoff coefficient: Rv=0.05+0.009(la) Rv = runoff coefficient = storm runoff (inches) / storm rainfall (inches) la = percent impervious = impervious portion of the drainage area (ac.)/drainage area (ac.) Ia 82.40 Rv= 0.79 (in./in.) Calculate the runoff volume for the water quality event (first 1" of runoff): Volume = (Design rainfall)(Rv)(Drainage Area) Volume = 1" rainfall * Rv * 1/12 (feet/inches) * Drainage Area Volume = 3.6 acre-feet Volume = 155,260 ft3 DWK [31 CHCS(3N I.an4yap, AmFOWts Appendix I Infiltration Zone and Assumed Infiltration Rates for Pond Assumed Infiltration Rate Assumed Infiltration Rate Assumed Infiltration Zone Area (sq ft) (inch/hr) Whr) Rate (ft/sec) 1 (moderately draining soils) 12,403 2 0.2 0.000046 2 (well draining sand) 14,563 10 0.8 0.000231 Calculate Peak Flows and Drawdown Time for WQ Event Time to Drain Pond Time to Drain Zone 1 Peak Flow (cfs) Zone 2 Peak Flow (cfs) Total Flow (cfs) Time to Drain Pond (sec) (min) Pond (hours) 0.6 3.4 3.9 39,354 656 10.9 Shear Stress Analysis of Rip -Rap Ditches Inside SCM Pond Project: HAECO Site Development Project, PTIA Airporl Engineer: DJK Date: 11-3-15 Appendix J Mannings Equation, Q =(A) 1.49 Rh.66S0.5 n 36 Inch RCP on Western Side of Pond Storm Design Chan Bot Side Side Slope Design Chan Wetted Hydraulic Mann. Channel Q Calc. Calc. Shear Temp. Perm. Event Flow (cfs) Width Slope Length Depth Area Perim., Pw Radius "n" Slope Allow. Depth Velocity Stress Liner Liner 10 -Year 30 3 3 6.3 2 18 16 1.2 0.040 0.002 32 1.9 1.8 0.2 Straw w/ net Class A 1 -Year 9 3 5 5.1 1 8 13 0.6 0.040 0.002 9 1.0 1.2 0.1 Straw w/ net Class A 24 Inch RCP on Eastern Side of Pond Storm Design Chan Bot Side Side Slope Design Chan Wetted Hydraulic Mann. Channel Q Calc. Calc. Shear Temp. Perm. Event Flow (cfs) Width Slope Length Depth Area Perim., Pw Radius "n" Slope Allow. Depth Velocity Stress Liner Liner 10 -Year 26 3 3 6.3 2 18 16 1.2 0.040 0.002 33 1.9 1.8 0.2 Straw w/ net Class A 1 -Year 9 3 5 5.1 1 8 13 0.6 0.040 0.002 9 1.0 1.2 0.1 Straw w/ net Class A IShear Stress, T= yds T = shear stress in Ib/sq. ft. y = unit weight of water, 62.4 Ib/cu. ft. d = flow depth in ft. s = channel slope in ft./ft. Notes: Side slope = horiz./vert. TemporaryLiners AllowSheafitress Material (lb/sglt) Tacked Mulch 0.35 Jute Net 0.45 Straw w/Net 1.45 SytheticMat 2.00 C1assA 1.25 ClassB 2.00 Classl 3.40 Classll 4.50 Max Permi ss ibb Vel ocitiesfor Unpro eeted Sot l sin Ex. Channels Material Max. Permissibb Velocity(ff/s) FineSand(noncollidl) 2.5 Sand Loam(nonco I I idl) 2.5 Si ltLoam(noncollidl) 3.0 OrdinaryFirm Loam 3.5 Fine Gravel 5.0 Stiff Clay (very collidal) 5.0 Graded,Silt toCobbles 5.0 IDepth and Velocity calculated using AutoCAD's Hydroflow Express Max. Allow. Design V for Vegetative Channels ChannelSlope Soil GrassLining Permissibb V (11/s) 0-5% Sands/Silk Bermuda 5.0 Tall Fescue 4.5 KYBluegrass 4.5 Grass-legumemix 3.5 Clay Mixes Bermuda 6.0 Tall Fescue 5.5 KY Bluegrass 5.5 Grass-leguinemix 4.5 5-10% Sands/Silt Bermuda 4.5 Tall Fescue 4.0 KYBluegrass 4.0 Grass- legume mix 3.0 Clay Mixes Bermuda 5.5 TallFescue 5.0 KYBluegrass 5.0 Grass-legumemix 3.5 Permit Number: (to be provided by DEMLR) Drainage Area Number: High Flow Rate Bioretention Pond Operation and Maintenance Agreement I will keep a maintenance record on this BMP. This maintenance record will be kept in a log in a known set location. Any deficient BMP elements noted in the inspection will be corrected, repaired or replaced immediately. These deficiencies can affect the integrity of structures, safety of the public, and the removal efficiency of the BMP. Important maintenance procedures: — The drainage area of the high flow rate bioretention pond will be carefully managed to reduce the sediment load to the sand filter. — Once a year, sand media will be skimmed. — The sand filter media will be replaced whenever it fails to function properly after maintenance. The high flow rate bioretention pond will be inspected once a quarter and within 24 hours after every storm event greater than 1.0 inches. Records of operation and maintenance will be kept in a known set location and will be available upon request. Inspection activities shall be performed as follows. Any problems that are found shall be repaired immediately. BMP element: The entire BMP The grass filter strip or other pretreatment area The flow diversion structure (if applicable) Potential problem: Trash/debris is present. Areas of bare soil and/or erosive gullies have formed Sediment has accumulated to a depth of greater than six inches. The structure is clogged The structure is damaged How I will remediate the problem: Remove the trash/debris. Regrade the soil if necessary to remove the gully, and then plant a ground cover and water until it is established. Provide lime and a one-time fertilizer application. Search for the source of the sediment and remedy the problem if possible. Remove the sediment and dispose of it in a location where it will not cause impacts to streams or the BMP. Unclog the conveyance and dispose of any sediment off-site. Make any necessary repairs or replace if damage is too large for repair. High Flow Rate Bioretention Pond O&M Page 1 of 3 BMP element: The bioretention cell: soils and mulch Permit Number: Potential problem: Mulch is breaking down or has floated away. Soils and/or mulch are clogged with sediment. Water is ponding on the surface for more than 24 hours after a storm. (to be provided by DEMLR) How I will remediate the problem: Spot mulch if there are only random void areas. Replace whole mulch layer if necessary. Remove the remaining mulch and replace with triple shredded hard wood mulch at a maximum depth of three inches. Check to see if the collection system is clogged and flush if necessary. If water still ponds, remove the top few inches of the filter bed material and replace. If water still ponds, then consult an expert. Outlet device Clogging has occurred. Clean out the outlet device and dispose sediment in a location that will not impact a stream or the BMP. The outlet device is damaged. Repair the outlet device. The observation well(s) The water table is within one Contact DEMLR Stormwater foot of the bottom of the Permitting staff immediately at system for a period of three 919-707-9220. consecutive months. The emergency overflow berm The receiving water The outflow pipe is clogged The outflow pipe is damaged. Erosion or other signs of damage have occurred at the outlet. Erosion or other signs of damage have occurred at the outlet. Provide additional erosion protection such as reinforced turf matting or riprap if needed to prevent future erosion problems. Repair or replace the pipe. The emergency overflow berm will be repaired or replaced if beyond repair. Contact the N.C. Division of Water Resources 401 Certification Program staff at 919-707-8789. High Flow Rate Bioretention Pond O&M Page 2 of 3 Permit Number: (to be provided by DEMLR) I acknowledge and agree by my signature below that I am responsible for the performance of the maintenance procedures listed above. I agree to notify DEMLR of any problems with the system or prior to any changes to the system or responsible party. Project name: HAECO Site Development Project BMP drainage area number: Print name: Title: Address: Phone: Signature: Date: Note: The legally responsible party should not be a homeowners association unless more than 50% of the lots have been sold and a resident of the subdivision has been named the president. a Notary Public for the State of County of , do hereby certify that personally appeared before me this _ day of , and acknowledge the due execution of the forgoing high flow rate bioretention pond maintenance requirements. Witness my hand and official seal, SEAL My commission expires High Flow Rate Bioretention Pond O&M Page 3 of 3 DIVISION OF MITIGATION SERVICES (DM'S) IN -LIEU FEE REQUEST FORM Revised 4/23/2015 Complete requested information, sign and date, email to kellv.williamsftncdenr.aov. . Attachments are acceptable for clarification purposes (location map, address or lat long is required). Information submitted is subject to NC Public Records Law and may be requested by third parties, Review meetings are held on Tuesday afternoons. - CONTACT INFORMATION APPLICANT'S AGENT APPLICANT 1. Business/Company Name Michael Baker Engineering, Inc. Piedmont Triad Airport Authority 2. Contact Person Richard Darling Alex Rosser, PE 3. Street Address or P O Box 5000 Regency Pkwy., Suite 600 1000-A Ted Johnson Pkwy. 4. City, State, Zip Cary, NC 27518 Greensboro, NC 27409 5. 919.4$1.57 Telephone Number -- - 40 336.665.5600 6. E -Mail Address rdariing@mbakerintl.com PROJECT INFORMATION 7. Project Name 8. Project Location (nearest town, city) 9. Lat-Long Coordinates or attach a map 10. County 11. River Basin & Cataloging Unit (8 -digit) (See Note 1) 12. Project Type "*indicate owner type and write in project type (e.g. school, church, retail, residential, apartments, road, utilities, military, etc.)** 13. Riparian Wetland Impact (ac.) (e.g., 0.13) 14. Non -Riparian Wetland Impact (ac.) HAECO Facility Improvements rossera@gsoair.org Radar Road, Greensboro, NC 27410 36 05 49 N, 79 55 53 W Guilford Owner Type: ) Government 0 Private Project Type: aviation development 0.81 C 15. Coastal Marsh Impact (ac.) 1 0 16. Stream Impact (ft.) (e.g. 1,234) 17. Riparian Buffer Impact (sq. ft.) Include subwatershed if Jordan or Falls Lake: 18. Regulatory Agency Staff Contacts USAGE. David Bailey s Warm. _ Cool Cold 1,601 i Zone 1: Zone 2: NCDWR: Other: Sue Homewood Check (�) below if this request is for a: By signing below, the applicant is confirming they ha) revision to a current acceptance ! read and understand the DMS refund policy posted at nceep.net and attached to this form. renewal of an expired acceptance Signature f Ap cant or Authorized Agent: extension of acceptance unexpired p Date: 11(131 wtS Note 1: For help in determining the Cataloging Unit, visit:www.nceeti.net or contact DMS Direct questions to Felly Williams at 919-707-8915 or kellv.williamsCa)ncdenr.Qov or to the front desk at 919707-8976 Print Form DMS ILF Mitigation Request Statement of Compliance with §143-214.11 & 143-214.20 (link to G.S. 143-214.11) Prior to accessing the Division of Mitigation Services (DMS), all applicants must demonstrate compliance with G.S. § 143-214.11 and 143-214.24. All requests MUST include this form signed and dated by the permit applicant or an authorized agent. Please refer to DENR's Implementation Poli\ for more details. Compliance Statement: have read and understand G.S. § 143-214.11 and 214.20 and have, to the best of my knowledge, complied with the requirements. I understand that participation in the DMS is voluntary and subject to approval by permitting agencies. Please check all that apply: Applicant is a Federal or State Government Entity or a unit of local government meeting the requirements set forth in G.S. 143-214.11 and is not required to purchase credits from a mitigation bank. ri There are no listed mitigation banks with the credit type I need located in the hydrologic unit where this impact will take place (link to DwR list) Mitigation bank(s) in the hydrologic unit where the impacts will occur have been contacted and credits are not currently available. ® The DWR or the Corps of Engineers did not approve of the use of a mitigation bank for the required compensatory mitigation for this project. F7 This is a renewal request and the permit application is under review. Bank credits were not available at the time the application was submitted. Enter date permit application was submitted for review: Note: It is the applicant's responsibility to document any inquiries made to private mitigation banks regarding credit availability. I have read and understand the DMS refund policies (attached) ini1 bete J. Alex Rosser, PE; Deputy Executive Director Signature of Applicant or Agent Printed Name Date HAECO Facility Improvements Piedmont Triad International Airport Project Name Location Refund Policv for Fees Paid to DMS In -Lieu Fee Proqrams (912112009) Purpose: The purpose of this policy is to make clear the circumstances and process under which a permittee can obtain a refund while simultaneously balancing customer service and responsible business practices. This policy applies to all refund requests made on or after the publication date of this policy. Policy Statement: The policy of DMS is to allow for refunds under certain conditions. 1. All refund requests must be made in writing to the DMS In -Lieu Fee Program Coordinator at kellv.wiIIiams(&ncden r.gov. 2. All refund requests are subject to fund availability. DMS does not guarantee fund availability for any request. 3. The request must either come from the entity that made the payment or from an authorized agent. Third parties requesting refunds must provide written authorization from the entity that made the payment specifying the name and address of the authorized refund recipient. 4. Refund requests related to unintended overpayments, typographical errors or incorrect invoices should be brought the attention of the In -Lieu Fee Program Coordinator as soon as possible. Such requests are typically approved without delay. S. Payments made under the incremental payment procedure are not eligible for refunds. b. Refund requests made within nine months of payment to DMS will only be considered for requests associated with projects that have been terminated or modified where the permittee's mitigation requirements have been reduced. Such requests must be accompanied by written verification from the permitting agency that the project has been cancelled, the permits have been rescinded or have been modified, or the mitigation requirements have been reduced. 7. Refund requests made more than nine months from the payment date will only be considered for permits that were terminated or modified to not require any mitigation. Such requests must be accompanied by written verification from the permitting agency that the project has been cancelled, the permits have been rescinded and/or mitigation is no longer required. 8. Refund requests not meeting the criteria specified above are not eligible for a refund. 9. Refund requests that meet the criteria above will be elevated to DMS Senior Management for review. The following considerations apply to all refund requests: a. availability of funds after consideration of all existing project and regulatory obligations b. the date the payment was made c. the likelihood DMS can use the mitigation procured using the payment to meet other mitigation requirements 10. Once a refund has been approved, the refund recipient must provide a completed W-9 form to the DMS In -Lieu fee Program Coordinator within two weeks in order to process the refund though the State Controller's Office, 11. All decisions shall be final. 11/252015 W Shipment Receipt Address Information FedEx Shp Manager -Print Yotr Labels) Ship to: Ship from: David Bailey Phyllis Best US Army Corps of Engineers Michael Baker Corp. 3331 Heritage Trade Dr. 8000 Regency Parkway Suite 105 Suite 600 WAKE FOREST, NC Cary, NC 27587 27518 US US 919-554-4884 919-463-5488 Shipment Information: Tracking no.: 775064672806 Ship date: 11/25/2015 Estimated shipping charges: 8.60 Package Information Pricing option: FedEx Standard Rate Service type: Priority Overnight Package type: FedEx Pak Number of packages: 1 Total weight: 1 LBS Declared Value: 0.00 USD Special Services: Pickup/Drop-off: Use an already scheduled pickup at my location Billing Information: Bill transportation to: MICHAEL BAKER JR INC -994 Project Number: 148092 Task Number: I Invoice no. : Department no: Thank you for shipping online with FedEx ShipManager at fedex.com. Please Note FedEx will host he responsible fa any clam in excess of $100 per package, whedw the result of loss, damage, delay, r delivery, misdelivery, or misinfamabon, unless ypu d8dwO a higher value, pay an addtianal charge, document your actA loss and file a timely claim. Urnitabors loL M in the current FecEx Service Gude apply. you right to recova horn FedEx for any loss, includirig intrinsic value of the package, loss of sales, income interest, profit attorney's fees, costs, and other forms of damage whether direct, incidental, consequential, a special is limited to the greats of $100 or the aulMrized declared value. Recovery cannot exceed achsl documented loss. Maximum for items M extraadnary value is $1000, e.g., jewelry, precias metals, negotiable imbUrnerlb and mhw items listed in err Service Gude. Written Gams must be filed within strict Uma limits; Casult the applicable FadEx Service Guide for details. The estimated shipping charge may be different than the actual charges for your shipment. Differences may occur based m ache) weight dmensions, and ofactors. Consult the applicable F_drx Service Guoe a the FedEx Rete Sheels for details on how stopping charges we calculated. https://www.fedex.com/shippinglhtml/eNPrintiFrame.htm1 212 11/25/2015 Wal,K _ Shipment Receipt Address Information Ship to: Karen Higgins NCDENR-DWQ 401 Permitting 512 Salisbury St. Archdale Blding, 9th Floor RALEIGH, NC 27604 US 919-807-6360 Fei Ship Manager -Print Your l.abel(s) Ship from: Phyllis Best Michael Baker Corp. 8000 Regency Parkway Suite 600 Cary, NC 27518 US 919-463-5488 Shipment Information: Tracking no.: 775064584645 Ship date: 11/25/2015 Estimated shipping charges: 22.66 Package Information Pricing option: FedEx Standard Rate Service type: Priority Overnight Package type: Your Packaging Number of packages: 2 Total weight: 10 LBS Declared Value: 0.00 USD Special Services: Pickup/Drop-off: Use an already scheduled pickup at my location Billing Information: Bill transportation to: MICHAEL BAKER JR INC -994 Project Number: 148092 Task Number: 1 Invoice no. : Department no: Thank you for shipping online with FedEx ShipManager at fedexxom. Please Note FedEx will not be respatsible for any claim in excess of $100 pr package, whether the result d loss, damage, delay, nondelivery, misdelivery, Or misinformation, unless you dedwe a Mgher value, pay an atlbtod charge, doc mem yon actual loss and file a timely clam. Umitadms found in Vie currera FedEx Service Gude apply. Vora nigh m recover horn FedEx for arty loss, including intrinsic valued the package. loss of sales, income interest, profit, adarnei fens, costs, and other forms of damage whether direct, incidental, consmtAritial, a special is limited to Via greeter of $100 or the authorized declared value. Recovery cannot exceed actual documented lass. Maximum far items of immaodinary value is $1000, e.g., lerelry, precious metals, negotiable instruments and ether items listed in our Service Gude. Written dams must be filed vaatn strict time limit,; Consult the applicable FedEx Service Guidsfor details. The estimated shipping charge may be QVerert brain the actual charges for your shipment. Differences may ecce based on aerial weigh, dimensions, and otter factors. Cost ma applicable FedEx Service Guide a ore FedEx Rate Sheets for debut is on how shipping charges we calculated. https:/hvww.fedex.com/shippingthtm I/erdPrintiFrame.htm1 313