HomeMy WebLinkAboutSW6231202_Supplement-EZ Form_20240321 SUPPLEMENT-EZ COVER PAGE
LOAD SUPPLEMENT FORMS
PROJECT INFORMATION
1 Project Name Dunn,NC-Petco
2 Project Area(ac) 1.68
3 Coastal Wetland Area(ac) 0
4 Surface Water Area(ac) 0
5 Is this project High or Low Density? High
6 Does this project use an off-site SCM? No
COMPLIANCE WITH 02H.1003(4)
7 Width of vegetated setbacks provided(feet) 30
8 Will the vegetated setback remain vegetated? Yes
9 If BUA is proposed in the setback,does it meet NCAC 02H.1003(4)(c-d)? N/A
10 Is streambank stabilization proposed on this project? No
NUMBER AND TYPE OF SCMs:
11 Infiltration System
12 Bioretention Cell 1
13 Wet Pond
14 Stormwater Wetland
15 Permeable Pavement
16 Sand Filter
17 Rainwater Harvesting(RWH)
18 Green Roof
19 Level Spreader-Filter Strip(LS-FS)
20 Disconnected Impervious Surface(DIS)
21 Treatment Swale
22 Dry Pond
23 StormFilter
24 Silva Cell
25 Bayfilter
26 Filterra
LOAD SUPPLEMENT FORMS
DESIGNER CERTIFICATION
27 Name and Title: Andrew Maysent
28 Organization: McClure Engineering Company
29 Street address: 335 SE Oralabor Rd
30 City,State,Zip: Ankeny,IA 50021
31 Phone number(s): 515-512-1361
32 Email: amaysent@mcclurevision.com
Certification Statement:
I certify,under penalty of law that this Supplement-EZ form and all supporting information were prepared under my direction or supervision;that the
information provided in the form is,to the best of my knowledge and belief,true,accurate,and complete;and that the engineering plans,
specifications,operation and maintenance agreements and other supporting information are consistent with the information provided here.
Designer
SS/•
SEAL — Signature of Designer
045881 ti
c
03.20.24
Seal Date
DRAINAGE AREAS
1
Is this a high density project?
Yes
2
If so, number of drainage areas/SCMs
1
3
Does this Droiect have low densit areas?
No
4
If so, number of low density drainage areas
0
5
Is all/part of this project subject to previous rule
versions?
No
CLICK TO LOAD FORM
DRAINAGE AREA INFORMATION
Entire Site
1
2
4
Type of SCM
Bioretention
Bioretention
5
Total drainage area (sq ft
73050
63957
6
Onsite drainage area (sq ft
73050
63957
7
Offsite drainage area (sq ft
0
0
8
Total BUA in project (sq ft
46265 sf
46265 sf
9permitting)
New BUA on subdivided lots (subject to
s ft
sf
sf
10permitting)
New BUA not on subdivided lots (subject to
sf
46265 sf
46265 sf
11
Offsite BUA (sq ft
sf
sf
12
Breakdown of new BUA not on subdivided lots:
0
0
- Parking (sq ft
29813 sf
29813 sf
- Sidewalk (sq ft
5709 sf
5709 sf
- Roof (sq ft
10743 sf
10743 sf
- Roadway s ft
\
- Future (sq ft
sf
- Other, please specify in the comment box
below (sq ft
sf
sf
13
New infiltrating permeable pavement on
subdivided lots (sq ft
sf
sf
14
New infiltrating permeable pavement not on
subdivided lots (sq ft
sf
sf
15permitting)
Existing BUA that will remain (not subject to
s ft
sf
sf
16
Existing BUA that is already permitted (sq ft
sf
sf
17
Existing BUA that will be removed (sq ft
sf
sf
18
Percent BUA
63%
72%
19
Design storm inches
1.0 in
1.0 in
20
Design volume of SCM cu ft
3046 sf
3046 cf
21
Calculation method for design volume
NRCS
NRCS
ADDITIONAL INFORMATION
22
Please use this space to provide any additional information about the
drainage area(s):
BIORETENTION CELL
area n
Minimum required treatment volume
GENERAL MDC FROM 02H .1050
3
Is the SCM sized to treat the SW from all surfaces at build -out?
Yes
4
Is the SCM located away from contaminated soils?
Yes
5
What are the side slopes of the SCM (H:V)?
3:1
6
Does the SCM have retaining walls, gabion walls or other
engineered side slopes?
No
7
Are the inlets, outlets, and receiving stream protected from erosion
(10-year storm)?
Yes
8
Is there an overflow or bypass for inflow volume in excess of the
design volume?
Yes
g
lWhat is the method for dewatering the SCM for maintenance?
Pump (preferred)
10
If applicable, will the SCM be cleaned out after construction?
Yes
11
Does the maintenance access comply with General MDC (8)?
Yes
12
Does the drainage easement comply with General MDC (9)?
Yes
13
If the SCM is on a single family lot, does (will?) the plat comply with
General MDC (10)?
N/A
14
Is there an O&M Agreement that complies with General MDC (11)?
Yes
15
Is there an O&M Plan that complies with General MDC (12)?
Yes
16
Does the SCM follow the device specific MDC?
Yes
17
Was the SCM designed by an NC licensed professional?
Yes
BIORETENTION
CELL MDC FROM 02H .1052
18
SHWT elevation (fmsl)
164.00
19
Bottom of the bioretention cell (fmsl)
166.25
20
Ponding depth of the design storm (inches)
12 in
21
Surface area of the bioretention cell (square feet)
3303 sf
22
Design volume of SCM cu ft
3046 cf
23
Is the bioretention cell used for peak attenuation?
Yes
24
Depth of peak attenuation over planting surface (in)
18 in
25
j Height of peak attenuation outlet above the planting surface (in)
18 in
26
Infiltration rate of the in situ soil (inch/hour)
in/hr
27
Diameter of the underdrain pipes (if applicable)
4 in
28
Does the design include Internal Water Storage (IWS)?
yes
29
if so, elevation of the top of the IWS (fmsl)
168
30
Elevation of the planting surface (fmsl)
170.5
31
What type of vegetation will be planted? (grass, trees/shrubs,
other)?
Grass
32
IMedia depth (inches)
30 in
33
Percentage of medium to coarse washed sand by volume
75-85%
34
Percentage of fines (silt and clay) by volume
8-10%
35
Percentage of organic matter by volume
5-10%
36
Type of organic material
pine bark fines
37
Phosphorus Index (P-Index) of media (unitless)
<50
38
Will compaction be avoided during construction?
Yes
39
Will cell be maintained to a one inch/hour standard?
Yes
40
Depth of mulch, if applicable (inches)
41
Type of mulch, if applicable
42
How many clean out pipes are being installed?
2
43
Type of pretreatment that will be used:
Swales
ADDITIONAL INFORMATION
44 Please use this space to provide any additional information about
the bioretention cell(s):
Bioretention 2 2:38 PM 6/20/2024