HomeMy WebLinkAbout20081473 Ver 4 _Phase II Remediation Plan _20151120res
Memo 10055 Red Run Blvd.
Suite 130
Owings Mills, MD
To: Katie Merritt, DWR 21117
From: Brian Hockett , RES
412 N. 4th St. Suite 300
Baton Rouge, LA
cc: File
70802
Date: November 20, 2015
1307 Broad Street
Camden, SC
29020
Re: Arrington Bridge Phase II — Year 3 Monitoring
1514 South Church Street
Suite 103
Charlotte, NC
Per the November 3, 2015 email response from Katie Merritt (DWR) referencing the Year 3
28203
monitoring report for the Arrington Bridge Phase II Bank Parcels, RES is providing a written
course of action for remediation as requested.
5020 Montrose Blvd.
Suite 650
Houston, TX
1. A supplemental planting plan which shall include 1) a proposed deadline to
77006
complete the replanting, 2) a commitment to flag all stems that will be planted, 3)
a commitment to provide post - planting pictures of the replanted areas, 4) stem
1200 Camellia Blvd.
count data for Plots 1 & 4 post planting.
Suite 220
RES staff has taken immediate action to remediate the easement encroachment of
Lafayette, LA
0.81 acres at the Arrington Bridge Phase II Bank Parcel. A supplemental planting is
70508
planned in the month of January 2016 for all encroachment areas and buffer areas
137 1/2 East Main Street
below success criteria stem densities (Plots 1 and 4). As requested by DWR, all
Suite 210
supplemental tree stems planted in the encroachment areas and Vegetation Plots 1 and
Oak Hill, WV
25901
4 will be flagged with marking tape. After supplemental planting activities are
completed, vegetation plots 1 and 4 stem count data will be reported to DWR. Photo
380 Southpointe Blvd.
documentation of these services will be provided. A supplemental planting of 3 100
P PP P g �
Plaza 11, Suite 405
Canonsburg, PA
stems by Environmental Banc and Exchange did occur in December 2014 at the site;
15317
however, it is documented that additional stems were not planted within the
vegetation plots 1 and 4. During the planned January 2016 supplemental planting
Capability Drive
activities, RES will assure that additional stems will be planted within vegetation
Suite
Suite 3100
Raleigh, NC
plots 1 and 4 and surrounding areas. As part of RES's active preventative action, in
27606
mid - October 2015 RES planted 3- gallon container trees along the easement edge and
posted additional easement marking signs. Our intentions is that planting larger trees
along the boundary will help to provide a visual boundary between the agriculture
fields and the conservation easement. RES has also discussed with the landowner and
persons responsible for the easement encroachment to assure it doesn't happen again.
Photos of the tree plantings and additional easement signage are provided below.
2. A written course of action for remediating the encroachment problems on the
site with a proposed deadline for completion.
As stated above, RES plans to perform a supplemental planting at the Arrington
Bridge Phase II Site in January 2016. All documentation of the required remediation
work will be provided to DWR following the completion of the work. Additional
easement markers have been posted along the boundary of the easement as well as 3-
gallon container trees planted along the encroachment area borders. It should be noted that RES took
action to perform this work prior to DWR's email requesting remedial work onsite. RES discussed
the easement encroachment problems with the landowner /persons responsible in hopes to prevent
future encroachment occurrences.
Please let me know if you have additional concerns or questions about our remedial action plan.
Brian Hockett, PLS
NC Operations Manager
RES
Planted 3- gallon container trees on Easement Boundary.
Installed additional easement boundary markers along encroachment areas.
Planted 3- gallon container trees on Easement Boundary.
Planted 3- gallon container trees on Easement Boundary.
Installed additional easement boundary markers along all borders.