From: Burdette, Jennifer a
Sent: Monday, November 16, 2015 11:33 AM
To: 'Craig R. Wyant'; Hair, Sarah E SAW; Johnson Jr, Tony; Chris Scott
Cc: Tom Foley
Subject: RE: VMC Rockingham Quarry
Attachments: SKM_C224e15111611480.pdf
Craig,
Attached is a copy of the Division's request for additional information on the subject project. A paper copy follows via US
Mail.
Thanks,
Jennifer
Jennifer Burdette
401 /Buffer Coordinator
Division of Water Resources - 401 & Buffer Permitting Unit Department of Environmental Quality
919 807 6364 office
jennifer.burdette @ncdenr.gov
1617 Mail Service Center
Raleigh, NC 27699 -1617
(Physical Address: 512 N. Salisbury St, Raleigh, NC 27604 - 9th Flr Archdale Bldg — Room 942F)
Email correspondence to and from this address is subject to the North Carolina Public Records Law and may be disclosed
to third parties.
- - - -- Original Message---- -
From: Craig R. Wyant [ mailto:craig.wyant @charter.net]
Sent: Thursday, November 12, 2015 10:45 AM
To: Hair, Sarah E SAW <Sarah.E.Hair @usace.army.mil >; Burdette, Jennifer a < Jennifer.Burdette@ncdenr.gov>; Johnson Jr,
Tony <johnsonto @vmcmail.com >; Chris Scott <ScottC @vmcmail.com>
Cc: Tom Foley <FoleyT @vmcmail.com>
Subject: Re: VMC Rockingham Quarry
Elizabeth
Thank you very much for your prompt response. I will forward this information to the Applicant.
Have a good day.
Craig
1
Craig R. Wyant RLA
A Fine Line Design
Post Office Box 163
High Shoals, NC 28077
704 - 240 -0793
craig.wyant @charter.net
On 11/12/15 10:14 AM, "Hair, Sarah E SAW" <Sarah.E.Hair @usace.army.mil>
wrote:
> Craig,
• The Public Notice concluded for this project on November 6, 2015. 1
• received 2 comment letters in response to that notice: 1) A No
• Staffing Letter from NMFS regarding EFH, stating that the project
• would not occur in the vicinity of EFH, and that their present
• staffing levels preclude further analysis of the project; and 2) From
• USFWS concurrence on not likely to adversely affect endangered species or their critical habitat.
• At this point, I have to draft my decision document for review along
• with any special conditions that may be required as a part of the
• decision. The permitting review process is 120 days from receipt of a
• complete application to render a decision.
> I'll be in touch in the coming weeks if I have any questions.
> Thank you,
• Liz Hair
• Regulatory Project Manager
• U.S. Army Corps of Engineers - Wilmington District Wilmington Regulatory
• Field Office
• 69 Darlington Avenue
• Wilmington, NC 28403
• phone: 910- 251 -4049
• email: sarah.e.hair @usace.army.mil
• For more information on our program, please visit our website at:
• www.saw.usace.army.mil
• Your feedback on our service is greatly appreciated. Please take some
• time to complete the customer feedback survey at:
• http:// corpsmapu .usace.army.mil /cm_apex /f ?p= 136:4:0
> Please see the following link for guidance on use of Preliminary
> Jurisdictional Determinations:
• http: / /www.saw.usace.army.mil/ Missions/ RegulatoryPermitProgram /PublicN
• otices.a
> spx
> - - - -- Original Message - - - --
* From: Craig R. Wyant [ mailto:craig.wyant @charter.net]
> Sent: Thursday, November 12, 2015 7:57 AM
> To: Hair, Sarah E SAW <Sarah.E.Hair @usace.army.mil >,
• jennifer.burdette @ncdenr.gov, Johnson Jr, Tony <johnsonto @vmcmail.com>
• Subject: [EXTERNAL] VMC Rockingham Quarry
> Elizabeth and Jennifer
• I have been asked to check on the processing of the 404 and 401 permit
• application for the VMC Rockingham Quarry in Richmond County. Does
• everything seem to be in order so far?
• Please let me know if you have any questions or if there is any way I
• can be of assistance to you.
• Respectfully,
• Craig