Mr. John Hennessy
North Carolina Department of Water Resources
Water Quality Permitting Section/NPDES
1617 Mail Service Center
Raleigh, NC 27699-1617
Tuesday, January 23, 2024
RE: EMC SOC WQ S20-001 November 2023 Quarterly Progress Report
Mr. Hennessy,
Union County Water receieved the fully excuted SOC for the Grassy Branch WRF on June 21, 2022. As a
requirement of this SOC the County is to submit quarterly progress reports. This letter is intended to serve
as the quarterly progress report. Below is a summary of items that took place during the August 2023
report period.
For Collections system permit WQCS00054
• Ongoing inflow and infiltration (I&I) rehabilitation in the Grassy Branch basin.
o All I&I concerns identified in the June 2022 Grassy Branch Collections System
Assessment Report have been addressed.
For NPDES Permit NCO085812
• Submit Contract documents for regulatory approval for Grassy Branch WWTP upgrade project.
o Contract documents and Authorization to Construct was submitted on December 19,
2023
• Upon receiept of the required Division of Water Resources Authorization to Construct, begin
construction of Grassy Branch WWTP upgrades.
he_required approval from DMM
If you have any further questions please feel free to contact me.
Sincerely,
Christopher Clark, PE
Water & Wastewater Division Director
CC: Hyong Yi, Public Works Administrator
Josh Brooks, Water & Wastewater Assistant Division Director
John Shutak, Engineering Division Director
Greg Morgan, Utility Field Services Superintendent
Jonathan Jordan, WU Superintendent
Union County Water
4600 Goldmine Rd
Monroe, NC 28112
7 704.289.1434
unioncountync.gov/water