From: Steffens, Thomas A CIV USARMY CESAW (USA) <Thomas.A.Steffens@usace.army.mil>
Sent: Monday, February 12, 2024 12:46 PM
To: Wilson, Travis W.; Chris Rivenbark; Ward, Garcy
Subject: RE: [External] Moratorium Variance Request -Bridge No. 38, US 13 over Tar River,
Greenville, Pitt County
CAUTION: External email. Do not click links or open attachments unless verified. Report suspicious emails with the Report Message
button located on your Outlook menu bar on the Home tab.
Thank you Travis,
The Corps concurs with the WRC that an extension of the moratorium from 15 February 2024
to 29 February 2024 to perform in -water work is allowable. This transmission may be
considered as official approval of the action and will be added to the administrative record for
the project.
Thomas A Steffens
Regulatory Project Manager
US Army Corps of Engineers
2407 West 5th Street
Washington, NC 27889
(910)-251-4615
From: Wilson, Travis W. <travis.wilson@ncwildlife.org>
Sent: Monday, February 12, 2024 10:52 AM
To: Chris Rivenbark <crivenbark@rkk.com>; Ward, Garcy <garcy.ward@deq.nc.gov>; Steffens, Thomas A CIV USARMY
CESAW (USA) <Thomas.A.Steffens@usace.army.mil>
Subject: [Non-DoD Source] RE: [External] Moratorium Variance Request -Bridge No. 38, US 13 over Tar River, Greenville,
Pitt County
I have coordinated with our fisheries biologist. We are already beginning to see a few shad in the river. However, we
can agree to allow the proposed in water work activities to proceed through February 29, 2024.
Travis W. Wilson
Eastern DOT Habitat Conservation Coordinator
Habitat Conservation Division
NC Wildlife Resources Commission
1718 Hwy 56 West
Creedmoor, NC 27522
New Phone: 919-707-4057
Fax: 919-528-2524
Travis.Wilsona-ncwildlife. org
1
From: Chris Rivenbark <crivenbark@rkk.com>
Sent: Monday, February 5, 2024 5:55 PM
To: Wilson, Travis W. <travis.wilson@ncwildlife.org>; Ward, Garcy <garcy.ward@deg.nc.gov>; Steffens, Thomas A CIV
USARMY CESAW (USA) <Thomas.A.Steffens@usace.army.mil>
Subject: RE: [External] Moratorium Variance Request -Bridge No. 38, US 13 over Tar River, Greenville, Pitt County
CAUTION: External email. Do not click links or open attachments unless verified. Report suspicious emails with the Report Message
button located on your Outlook menu bar on the Home tab.
Travis,
The contractor estimates that they will install 6 templets, one for each bent 1-6, and 18 casings, 3 per bent 1-6 between
Feb 16-29.
CHRIS RIVENBARK, PWS, CPM
919.215.6408 CellKor
From: Chris Rivenbark
Sent: February 5, 2024 4:29 PM
To: Wilson, Travis W. <travis.wilson@ncwildlife.org>; Ward, Garcy <garcy.ward@deg.nc.gov>; Steffens, Thomas A CIV
USARMY CESAW (USA) <Thomas.A.Steffens@usace.army.mil>
Subject: RE: [External] Moratorium Variance Request -Bridge No. 38, US 13 over Tar River, Greenville, Pitt County
Good afternoon,
We're still waiting on a response for Travis' question but below are answers to Garcy's.
1. How many structures in total will need to be installed? 18 permanent casing and 6 templets to install. Before
this work can start we have to finish installation of the work bridge and remove the existing piles from the river,
which we anticipate finishing prior to the moratorium starting.
2. What is the method of installation — pile driving or vibratory? Vibratory
3. What is the anticipated amount of time for installing each structure? Anticipate 3 templets every 2 days (1.5 per
day), one Bent of permanent casings (3 casings) per day.
4. How many structures will be installed in a day and what is the time interval between each? Three casings, one
every 2.5 to 3 hours. Driving time should not exceed 30 mins each, remaining time will be set up and material
staging.
CHRIS RIVENBARK, PWS, CPM
919.215.6408 Cell
Ric
From: Chris Rivenbark
Sent: February 2, 2024 11:27 AM
To: Wilson, Travis W. <travis.wilson@ncwildlife.org>; Ward, Garcy <garcy.ward@deg.nc.gov>; Steffens, Thomas A CIV
USARMY CESAW (USA) <Thomas.A.Steffens@usace.army.mil>
Subject: RE: [External] Moratorium Variance Request -Bridge No. 38, US 13 over Tar River, Greenville, Pitt County
Good morning guys,
Thank you for looking at this so quickly.
I've forwarded your questions to Jason and Jordan.
CHRIS RIVENBARK, PWS, CPM
919.215.6408 Cell
RK
From: Wilson, Travis W. <travis.wilson@ncwildlife.o
Sent: February 2, 2024 9:26 AM
To: Ward, Garcy <garcy.ward@deg.nc.gov>; Chris Rivenbark <crivenbark@rkk.com>; Steffens, Thomas A CIV USARMY
CESAW (USA) <Thomas.A.Steffens@usace.army.mil>
Subject: RE: [External] Moratorium Variance Request -Bridge No. 38, US 13 over Tar River, Greenville, Pitt County
EXTERNAL EMAIL: Do not click links or open attachments unless you trust the 'Sender' and know the content is
safe.
Chris, I have some of the same questions. Primarily of the 8 piles and 6 casing listed below can we get a better idea of
what will be remaining after February 15?
Travis
From: Ward, Garcy <garcy.ward@deg.nc.gov>
Sent: Thursday, February 1, 2024 3:01 PM
To: Chris Rivenbark <crivenbark@rkk.com>; Steffens, Thomas A CIV USARMY CESAW (USA)
<Thomas.A.Steffens@usace.army.mil>; Wilson, Travis W. <travis.wilson@ncwildlife.org>
Subject: RE: [External] Moratorium Variance Request -Bridge No. 38, US 13 over Tar River, Greenville, Pitt County
Chris,
Please provide a little more detail on the installation of the permanent casings and templates that is expected to be
remaining after February 15.
• How many structures in total will need to be installed?
• What is the method of installation — pile driving or vibratory?
• What is the anticipated amount of time for installing each structure?
• How many structures will be installed in a day and what is the time interval between each?
I know from experience that this section of river is heavily utilized by shad during this time frame. Thanks for any
additional information you can provide.
Garcy Ward
Environmental Specialist, Transportation Permitting Branch
North Carolina Department of Environmental Quality
Office: (252) 948-3917
garcy.ward@deg.nc.gov
0-0
NOkI'H CAHOLIN D E Q6i
�
OeAaAmeet of Envirennlental Uuali
Email correspondence to and from this address is subject to the North
Carolina Public Records Law and may be disclosed to third parties.
From: Chris Rivenbark <crivenbark@rkk.com>
Sent: Thursday, February 1, 2024 12:10 PM
To: Ward, Garcy <garcy.ward@deg.nc.gov>; Steffens, Thomas A CIV USARMY CESAW (USA)
<Thomas.A.Steffens@usace.army.mil>; Wilson, Travis W. <travis.wilson@ncwildlife.org>
Subject: [External] Moratorium Variance Request -Bridge No. 38, US 13 over Tar River, Greenville, Pitt County
CAUTION: External email. Do not click links or open attachments unless verified. Report suspicious emails with the Report Message
button located on your Outlook menu bar on the Home tab.
USACE Action ID: SAW-2018-01119
DWR Project No.: 20210955
Good afternoon,
I thought it would save time to include Travis on the initial request for his thoughts/decision. Please let me know if this
request needs to be submitted through Laserfiche, I'll be happy to do so.
The contractor is not going to make the February 15 date for having in -water work completed. Though it is possible they
may finish with a two week variance, we are requesting a three week variance, allowing in -water to continue until
March 7.
In the last few weeks, multiple weather events caused river level rise and has slowed progress on the job within water
work. They currently have the main line of the temp trestle installed and are working on the fingers. At the current rate,
they should have all the fingers in, much of the existing bridge demo done, with setting the permanent casings to remain
at February 15 mark. If we cannot get all the permanent cans installed for the drilled shafts, the project basically will be
at a standstill until they are able to resume bridge construction once moratorium ends.
The following is the remaining in -water work that needs to be completed.
• Complete Finger 1—two
piles and one section of bridge remains to be installed
• Complete Finger 2—two
piles and one section of bridge remains to be installed
• Complete Finger 3—two
piles and one section of bridge remains to be installed
• Complete Finger 4—four
piles and three section of bridge remains (working on one section today)
• Removal of existing bridge caps and piles
• Install permanent casings for Piers 1— 6
• Install templet for permanent casings 1— 6
Please let me know if you have any questions or need any additional information.
Thank you,
CHRIS RIVENBARK, PWS, CPM
Project Delivery Leader
8601 Six Forks Road
Forum 1 - Suite 700
Raleigh, NC 27615
919.215.6408 Cell 1919.878.9560 Main
www.rkk.com
Responsive People I Creative Solutions
"RK&K" and "RK&K Engineers" are registered trade names of Rummel, Klepper & Kahl, LLP, a Maryland limited liability partnership. This message contains
confidential information intended only for the person or persons named above. If you have received this message in error, please immediately notify the
sender by return email and delete the message. Thank you.
Rummel, Klepper and Kahl, LLP ensures nondiscrimination in all programs and activities in accordance with Title VI of the Civil Rights Act of 1964. RK&K does
not discriminate on the grounds of race, color, or national origin in the selection and retention of subcontractors. We also note that RK&K will ensure
minorities will be afforded full opportunity to submit proposals and not be discriminated against on the grounds of race, color, or national origin in
consideration for an award.
Rummel, Klepper and Kahl, LLP is an equal opportunity employer that values diversity at all levels. If you need more information or special assistance for
persons with disabilities or limited English proficiency, contact our Human Resources office at (410) 728-2900 for further assistance.
Email correspondence to and from this address may be subject to the North Carolina Public Records Law and may be disclosed to third parties by an authorized
state official.
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third parties.