Loading...
HomeMy WebLinkAbout4.1.2Context Effects to a resource are based on a relevant context for that resource, which may be based on geographic areas, relevant population of the resource, or, in the case of many socioeconomic effects, the perceptions of affected individuals or groups. Duration Effects are short-term, long-term, or permanent. Defining short-term and long-term effects of the alternatives is complicated in that the construction alternatives require a range of years to complete. For the purpose of analysis, construction periods were assumed to be 2 years for the Laurel Branch Picnic Area, 5 years for the Partial-Build Alternative to Bushnell, and 15 years for the Northern Shore Corridar. The definition of permanent is incorporated, in particular, with natural resource impacts, since long-term effects may occur well before the tim�period of construction is complete. Intensity As noted, the intensity of the impacts varies for each resource, but is categorized by NPS guidance as no/negligible, minor, moderate, or major. The intensity of direct and indirect impacts to the same resource may vary. Direct impacts are not necessarily more intense than indirect impacts. 4.1.2 Cumulative Impacts The CEQ regulations to implement the NEPA require assessment of cumulative impacts in the decision- making process. Cumulative impacts are defined as "impacts on the environment which result from the incremental impact of the action when added to other past, present, and reasonably foreseeable future actions regardless of what agency (federal or nonfederal) or person undertakes such other actions" (40 CFR 1508.7). Cumulative effects were determined for each resource by combining the direct and indirect impacts of the alternatives being considered with other applicable past, present, and reasonably foreseeable future actions in the study area. The study area for cumulative impacts was expanded to include the entire GSMNP in order to adequately address cumulative impacts to Park resources. Cumulative impacts of some resource topics (e.g., economics) have the potential to extend outside this defined study area boundary and are discussed from a regional perspective. In addition, some past, current, or future actions outside this study area are discussed due to their relevance to the project or their regional impact. Cumulative effects can be distant from the project in time, as well as space; therefore, a time horizon far the analysis was also considered. The temporal boundary for the analysis was set generally beginning in the late nineteenth century in order to consider those past actions that played a major role in shaping the study area. A future temporal boundary of 20 years (2025) was set to encompass planned projects in the study area, as Clarification of the term "baseline" for this project: The Partial-Build Alternative to Bushnell and the Northern Shore Corridor include a baseline route, as well as options to that route. Baseline routes and options are detailed in Section 2.5 and shown on Figure 2-8. Baseline routes have been compared to existing conditions. Impact analyses for the options are shown as a difference from the associated baseline route. Environmental Consequences — 4-3 North Shore Road Final Environmental Impact Statement well as to include the construction period of the Northern Shore Corridor alternative. This temporal boundary also corresponds with the future year traffic projections. Cumulative impacts are documented for each resource topic following the corresponding analysis of direct and indirect impacts. These cumulative impacts were considered in the determination of overall impact thresholds for each impacted resource. An evaluation of collective impacts to Park resources resulting from the proposed alternatives is presented in Collective Impacts, Sustainability, and Long-Term Management, Section 4.8. 4.1.2.1 Actions in the Area A number of projects and trends in the study area vicinity were evaluated to determine their potential, when combined with the North Shore Road Project, to have cumulative impact on the study area resources. This information also describes, in part, the baseline conditions of the study area under the No-Action Alternative. Several past public and private actions dramatically shaped the study area and changed the economic and social conditions of the region. The relatively self-sufficient farming/herding/hunting lifestyles of the nineteenth century began to change with the arrival of the railroad and the beginning of logging and mining operations in the 1880s and 1890s. Lifestyles were modified greatly with the commencement of large-scale logging operations by about 1910. By the time the lumber companies left, starting in the late 1920s, Alcoa had developed plans for Fontana Dam and Reservoir along the Little Tennessee and had begun buying bottomland in the area. Past federal actions considered include the 1838 "Trail of Tears; ' the purchase of forestland in the region, beginning in 191 l, for what is now the Nantahala National Forest; the establishment of the TVA in 1933; the establishment of GSMN P in 1934; and the construction of Fontana Dam beginning in 1942. These actions resulted in a decline in Swain Counry's population. Tbe flooding of the Little Tennessee River Valley due to the construction of Fontana Dam eliminated lower reaches of many streams and the associated floodplain wetlands. The dam flooded more than 10,000 ac (4,050 ha) of the Little Tennessee, Tuckasegee, and Nantahala valleys, including areas that had been inhabited in some cases by generations by the people of the Tennessee Valley. The project caused the loss of many farms and communities, as well as railroad lines and NC 288, the area's main east-west roadway. More than 44,000 ac (17,800 ha) along the north shore of Fontana Lake became inaccessible due to the flooding. The land was acquired by the TVA and added to GSMNP. However, the construction of Fontana Dam also brought jobs for thousands of people in the area. The effects of these public and private actions on the local economy and the people of the area are discussed further in the Environmental Justice Section of the ECR, Section 3.2.2. Other past actions, as well as some of the present and reasonably foreseeable projects and trends in the study area vicinity are summarized below. Several projects were analyzed and determined to have no cumulative effect on the study area when combined with potential impacts due to proposed North Shore Road Clarification of the term "baseline" for this project: The Partial-Build Alternative to Bushnell and the Northern Shore Corridor include a baseline route, as well as options to that route. Baseline routes and options are detailed in Section 2.5 and shown on Figure 2-8. Baseline routes have been compared to existing conditions. Impact analyses for the options are shown as a difference from the associated baseline route. Environmental Consequences — 4-4 North Shore Road Final Environmental Impact Statement alternatives. These projects include the potential removal of the Dillsboro Dam and the rehabilitation of Newfound Gap Road. Public projects that could impact the study area include NCDOT STIP projects, projects included in local thoroughfare plans, and GSMNP projects. (These projects are described in more detail in the Public Projects in the Viciniry of the Study Area Section of the ECR, Section 3.15.) In addition, recent trends, including gaming operations in Cherokee and increased second-home construction, are expected to continue to shape the region. The planned relocation of the GSMR headquarters to downtown Bryson City will likely result in dramatic changes to Bryson Ciry in the foreseeable future. 4.1.2.1.1 Cherohala Skyway Construction of the Cherohala Skyway began in l 965. The completed roadway is approximately 40 mi (64.4 km) long and located in the Cherokee and Nantahala national forests between Tellico Plains, Tennessee and Robbinsville, North Carolina, soutbwest of the study area. The road ascends to elevations above 5,000 ft (1,524 m) and generally follows the crest line of that portion of the Blue Ridge Mountains. 4.1.2.1.2 NCDOT State Transportation Improvement Program (STIP) Projects STIP Project No. A-9 consists of widening approximately 27 mi (43.5 krn) of US 74 from Andrews to NC 28 east of Almond to a four-lane divided facility, primarily on new location. While portions of the project are complete, the entire project is scheduled for completion after 2012. Project No. B-3701 involves the replacement of a bridge over Alarka Creek on Lower Alarka Road. Construction is scheduled for fiscal year 2006. Project No. E-4588 involved streetscape improvements to Everett Street in Bryson City. Project No. E-4972, which involves streetscape improvement to Depot Street in Bryson City, is scheduled for construction in fiscal year 2007. 4.1.2.1.3 Appalachian Development Highway System The Appalachian Regional Commission (ARC) was established in the 1960s to address poverty in the Appalachian Region of the United States. With the priority on developing a modern highway system as the key to economic development, Congress authorized the construction of the Appalachian Development Highway System (ADHS) in l 965. The ADHS is currently authorized at 3,090 mi (4,973 km). By the end of FY 2004, 2,627 mi (4,228 km) were complete or under construction (ARC 2005). NCDOT STIP Project No. A- 9 is funded through the ADHS program. 4.12.1.4 Thoroughfare Plans Thoroughfare plans are completed by the NCDOT Statewide Planning Branch in conjunction with local jurisdictions. Tbe plans document existing and future deficiencies in the local and regional transportation Clarification of the term "baseline" for this project: The Partial-Build Alternative to Bushnell and the Northern Shore Corridor include a baseline route, as well as options to that route. Baseline routes and options are detailed in Section 2.5 and shown on Figure 2-8. Baseline routes have been compared to existing conditions. Impact analyses for the options are shown as a difference from the associated baseline route. Environmental Consequences — 4-5 North Shore Road Final Environmental Impact Statement system and long-range plans for new or improved facilities. The recommended projects must be funded locally or placed on the NCDOT STIP list to be constructed. Widening projects proposed in the Bryson City Thoroughfare Plan (1993) include Spring Street, US 19, Main Street, Everett Street, Slope Street, Gibson Street, and Locust Street. Other improvements include a new frontage road and interchange along US 74. The Spring Street widening is complete. No other improvements have been completed, nor are any listed on the NCDOT STIP. Updated in 1998, the Thoroughfare Plan Technical Report for Graham County and Robbinsville addresses two projects that are in the NCDOT STIP: Project A-9 and Project No. R-2407. R-2407 ties into A-9 and also involves ihe widening and realigning of NC 28. However, this project is currently not funded. 4.12.1.5 GSMNP Projects The ECR discussed several projects proposed or underway in GSMNP. Projects determined to have the potential to cumulatively, with the North Shore Road Project, impact GSMNP and/or the study area are outlined below. Elkmont Historic District Planning The Elkmont Historic District is located on the Tennessee side of GSMNP. It consists of contributing and non-contributing buildings, cultural landscape elements, and features associated with two private vacation resort communities that date back to the early part of the twentieth century. When land for GSMNP was being set aside in the 1920s and 1930s, owners within the club towns were offered one-half payment for their property in exchange for a lifetime lease of the structures. All leases expired in 1992, with the exception of one that expired in 1996 and two that expired in 2001. The GSMNP GMP states that all buildings are to be removed upon termination of the leases and the building sites are to be returned to a natural state. The GMP has not been implemented on this issue due to the fact that Elk�nont was listed in the NRHP as an historic district in 1994. A GMP Amendment/EIS is being prepared to enable the Park to make a decision on future management of this district. The environmental compliance process, which formally began in spring 2002, effectively combines guidelines laid out by the NHPA and NEPA. Alternatives developed include various mixes of cultural and natural preservation strategies, which range from complete removal of structures to varying degrees of preservation and uses of structures. The Elkmont DEIS/GMP Amendment was published February 10, 2006, and the official public comment period ended May 11, 2006. The environmentally preferred and agency preferred alternative identified in the DEIS (Alternative C) proposes to retain the Appalachian Clubhouse and 16 historic buildings in the Daisy Town area, as well as a cabin in the Society Hill area, provide day use opportunities and parking to accommodate visitars, and restore native plant communities and natural systems in areas where buildings are removed (NPS 2006a). The planning team is currently in Clarification of the term "baseline" for this project: The Partial-Build Alternative to Bushnell and the Northern Shore Corridor include a baseline route, as well as options to that route. Baseline routes and options are detailed in Section 2.5 and shown on Figure 2-8. Baseline routes have been compared to existing conditions. Impact analyses for the options are shown as a difference from the associated baseline route. Environmental Consequences — 4-6 North Shore Road Final Environmental Impact Statement the process of reviewing public commenis and will respond to substantive comments in the Elkmont Final EIS. Foothills Parkway The Foothills Parkway was authorized by Congress as a scenic parkway on February 22, 1944. The purpose of the Foothills Parlcway is to provide beautiful vistas of the Great Smoky Mountains from the north flank and to disperse visitor traffic. The Parkway parallels GSMNP's northern boundary as it extends east from Chilhowee Lake on US 129 to I-40 near Cosby, Tennessee. To date, only two discontinuous segments, totaling 22.5 mi (36.2 lan) of the 72-mi (115.9-km) parkway, have been completed and opened to vehicular traffic. In ] 984 and 1985, two contracts were awarded to construct 16.1 mi (25.9 km) of the Parkway between Walland and US 321 in Wears Valley. Both projects experienced such severe slides and erosion problems that work was suspended, leaving a 1.6-mi (2.6-km) "missing link." A new design, which uses ] 0 bridges to minimize surface disturbance and resulting environmental impacts, was developed for this 1.6-mi (2.6-km) segment. To date, two bridges have been completed. Construction on another bridge began in summer 2005. Completion of the "missing linl�' is a prioriry, but it depends on available funding. Completion of the remainder of the Parkway also depends on available funding, as well as adequate mitigation of environmental impacts and allocation of sufficient base funding far operation of the highway. Lake View Road In 1959, the state of North Carolina completed a road from Bryson Ciry to the GSMNP boundary. Approximately 7.2 mi (1 ].6 km) of the originally proposed North Shore Road, including a tunnel, have been constructed within GSMNP. The last segment was completed in the 1970s. Known as Lake View Road, the road and the existing tunnel will require rehabilitation in the fareseeable future. If a partial-build ar build alternative were selected, this rehabilitation would have to be finished prior to completion of construction. There are also rehabilitation needs for the road crossing and extending north of Fontana Dam. Constructing the Northern Shore Corridor using the Southem Option Crossing Fontana Dam would require that this rehabilitation occur prior to completion of construction. More detailed study of these rehabilitation needs and associated costs would be required if any of the partial-build or build alternatives were selected for implementation. Ravensford Land Exchange A land excbange between the EBCI and NPS was authorized by congressional action in 2003. Through the exchange, the EBCI acquired a site for new schools. The Ravensford site is located just east of Newfound Gap Road north of Cherokee. NPS received a tract of land at Waterrock Knob, which is near the Jackson and Haywood county line more than 15 mi (24 km) east of Bryson Ciry. Clarification of the term "baseline" for this project: The Partial-Build Alternative to Bushnell and the Northern Shore Corridor include a baseline route, as well as options to that route. Baseline routes and options are detailed in Section 2.5 and shown on Figure 2-8. Baseline routes have been compared to existing conditions. Impact analyses for the options are shown as a difference from the associated baseline route. Environmental Consequences — 4-7 North Shore Road Final Environmental Impact Statement Cades Cove Opportunities Plan The Cades Cove area of GSMNP receives up to 2 million visitors each year, making it one of the most visited areas in the national park system. As a result, one major issue faced in Cades Cove is congestion. The 11-mi (17.7-km) loop road that encircles the valley floor is at a LOS of E ar F 50 percent of the time during peak visitation (June, July, August, and October). Five alternatives (one No-Action and four action alternatives) are being studied for Cades Cove. The action alternatives are comprised of varying combinations of tbe following options: completing roadway and parking i��nprovements, requiring reservations for private vehicular use of the road, utilizing a transit system, utilizing intelligent transportation systems, and constructing visitor centers. GSMNP is preparing an EIS to identify a preferred alternative for Cades Cove. Aggregate Surfacing of Cemetery Access Roads This action involves resurfacing sections of five cemetery access roads on the north side of Fontana Lake in GSMNP. The affected roads are Bone Valley Road (1.8 mi [2.9 km]), Woody Cemetery Road (0.8 mi [13 km]), Pilkey Creek Road (0.9 mi [1.4 km]), Cable Branch Road (0.6 mi [1.O lcm]), and Chambers Creek Road (0.7 mi [1.1 km]). The work also includes roadway stabilization and replacement of deteriorated log retaining walls. The work is funded and the project's construction is underway. 4.12.1.6 Wilderness Designation As discussed in the Parklands and Recreational Facilities Section of the ECR, Section 3.4, the Wilderness Act (September 1964) directed the Secretary of the Interior to study all roadless National Park areas of 5,000 or more contiguous ac (2,000 ha) for wilderness designation. Since 1966, the NPS has been pursuing wilderness designation for GSMNP in an effort to protect and perpetuate its scenic and biotic resources. Throughout the 1980s and 1990s, Congress debated the issue and drafted numerous bills either for or against designation of wilderness within GSMNP. Additional detail related to the history of wilderness designation recommendations related to GSMNP is included Section 3.2.5.1.1 of this document. 4.12.1.7 Urbanization in the Eastern United States Urbanization and suburbanization along the eastern seaboard of the United States has resulted in a reduction in the amount of undeveloped areas including open space, forested land and other natural areas. Growth and development has accelerated in the past few decades in the southeastern United States. Public lands without public vehicular access comprise only 3 percent of the land in the Southern Appalachian region of Alabama, Georgia, Kentucky, North Carolina, South Carolina, Tennessee, Virginia, and West Virginia. GSMNP has been identified as having the largest total area (more than 464,000 ac [187,800 ha]) without roads that have public vehicular access in the Southern Appalachian region, or more than one-third of such land in the region (USDA 2004). This land area is almost twice as large as the largest National Forest area without public Clarification of the term "baseline" for this project: The Partial-Build Alternative to Bushnell and the Northern Shore Corridor include a baseline route, as well as options to that route. Baseline routes and options are detailed in Section 2.5 and shown on Figure 2-8. Baseline routes have been compared to existing conditions. Impact analyses for the options are shown as a difference from the associated baseline route. Environmental Consequences — 4-8 North Shore Road Final Environmental Impact Statement vehicular access east of the Mississippi (USDA 2000). Potential changes to ]and use and management in GSMNP are discussed in Land Use, Section 4.2.4. 4.1.2.1.8 Cherokee Casino The 1997 opening and subsequent expansions of Cherokee Casino and Hotel/Conference Center by the EBCI is the single largest influence shaping recent economic trends in the region. The casino has become the area's largest employer. Through its local purchases of goods and services and expenditures by the more than 3.3 million annual visitors, the casino indirectly supports many more jobs in construction, lodging and food service establishments, trade, and the services sectar. The gaming-related revenues have allowed tribal operations to expand, funding infrastructure investments and added services and programs. 4.12.1.9 Relocation of Great Smoky Mountains Railroad Headquarters to Bryson City The GSMR, presently headquartered in Dillsboro, is widely credited with fostering a renewal of the community's downtown. It is expected that the relocation of the GSMR headquarters to downtown Bryson City will have a similar revitalizing effect in that location as well. Implementation of a strategic relocation plan has begun with the renovation of an existing building near the Bryson City depot to include a combination of ground-floor retail and second-floor offices for the company's administrative functions. Those functions expect to relocate within the year. Future plans include additional redevelopment of existing buildings, construction of a roundhouse and turntable for storage and maintenance of the company's locomotives and rolling stock, a hotel/motel, and expanded parking. Full implementation will be a long-term endeavor requiring ] 0 or more years. However, even prior to full implementation, Bryson City will become the primary terminal for most of the GSMR's scheduled excursions. That change will dramatically increase the number of people and traffic in downtown Bryson City, lengthen the duration of their visits, and provide an economic infusion that would ripple across the downtown landscape, stimulating new business stariups, reinvestment in existing structures, and new development. 4.1.2.1.10 Private Development (outside GSMNP) With its outstanding scenic and recreational resources, western North Carolina has long been host to many second-homes for use on a seasonal or occasional basis. The development in Swain and Graham counties, which has increased in recent years, includes a substantial amount of retirement and second-home construction intended primarily for seasonal or occasional occupancy. Meeting the needs and wishes of the owners and guest of these units, in addition to those of traditional tourists, is seen as becoming a driving force for economic develop�ment and redevelopment in Swain and Graham counties and elsewhere in the region. Clarification of the term "baseline" for this project: The Partial-Build Alternative to Bushnell and the Northern Shore Corridor include a baseline route, as well as options to that route. Baseline routes and options are detailed in Section 2.5 and shown on Figure 2-8. Baseline routes have been compared to existing conditions. Impact analyses for the options are shown as a difference from the associated baseline route. Environmental Consequences — 4-9 North Shore Road Final Environmental Impact Statement 4.1.2.1.11 Other Trends As demonstrated by the designation of westem North Carolina as the Blue Ridge National Heritage Area, heritage tourism plays an important role in the regional economy. As noted in Economic Impacts, Section 4.2.2, tourism and recreation visitation are major drivers of long-term economic growth across the region. While the number of visitors to the area is not expected to see large year-over-year increases, expenditures by those who do visit the area are expected to rise. The number of touring motorcyclists, which increased in the study area region over the last 10 to 15 years, can be expected to remain a part of the tolirism market for the foreseeable future. 4.1.3 Impairment (as defined by NPS policy) References to the purpose of GSMNP are provided in the NPS Organic Act of 1916 and in the legislation establishing the Park. The National Park Service Organic Act of 1916 states that the NPS, ". .. shall promote and regulate the use of the Federal areas known as national parks, monuments, and reservations hereinafter specified ... by such means and measures as conform to the fundamental purpose of the said parlcs, monuments, and reservations, which purpose is to conserve the scenery and the natural and historic objects and the wildlife where in and to provide for the enjoyment of the same in such manner and by such means as will leave them unimpaired for the enjoyment of future generations." The Park's enabling legislation states that GSMNP is "for the benefit and enjoyment of the people" and directed that the newly created park be administered, protected and developed under the direction of the Secretary of Interior. As further refined in the Park's 2005-2008 Strategic Plan, the purpose of GSMNP is "to preserve its exceptionally diverse natural and cultural resources, and to provide for public benefit from and enjoyment of those resources in ways that will leave them basically unaltered by modern human influences." (Additional information about GSMNP enabling legislation is included in Great Smoky Mountains National Park, Section 3.2.5.1. GSMNP enabling legislation is included in Appendix Q.) NPS managers must always seek ways to a�oid, or to minimize to the greatest degree practicable, adverse impacts on park resources and values. However, the laws establishing the national park system give the NPS management discretion to allow certain impacts to park resources and values when necessary and appropriate to fulfill the purpose of a park, so long as the impact does not constitute impairment of the affected resources and values. NPS Management Policies leave determinations of impairment to the responsible park manager and only direct that an action should be considered to constitute impairment if, in the manager's professional judgment, the action "would barm the integrity of the park resources or values, including the opportunities that otherwise would be present for the enjoyment of those resources or values" (NPS 2006b). NPS policies further state that whether an impact meets this definition depends on: ■ the particular resources and values that would be affected; ■ the severity, duration, and timing of the impact; Clarification of the term "baseline" for this project: The Partial-Build Alternative to Bushnell and the Northern Shore Corridor include a baseline route, as well as options to that route. Baseline routes and options are detailed in Section 2.5 and shown on Figure 2-8. Baseline routes have been compared to existing conditions. Impact analyses for the options are shown as a difference from the associated baseline route. Environmental Consequences — 4-10 North Shore Road Final Environmental Impact Statement