HomeMy WebLinkAbout20130777_RE Draft Inspection report for R-3101 (UNCLASSIFIED)_20151012
Carpenter,Kristi
From:Wanucha, Dave
Sent:Monday, October 12, 2015 9:32 AM
To:Slaughter, Johnathan H
Cc:andrew.e.williams2@usace.army.mil
Subject:RE: Draft Inspection report for R-3101 (UNCLASSIFIED)
Attachments:USACE Draft Compliance Notes.pdf
Hi Heath,
I concur with Andy's draft notes. Except that in addition to Sites 8, 9, 50 and 51 of which required "Remedial Action", I
would add the entries for Sites 25, 40 and 48 (highlighted in yellow in the attached) to the "Remedial Action" List as well.
As I recall, we all agreed that additional work was to take place on those sites as well.
Andy, FYI. Heath, Greg and I met at Site 50 with Marla last week to review the low flow sill and high flow side. As I
recall, Marla agreed with a plan to remove the low flow sill, then revisit at a later date to review and proceed from there
based on the level of functioning. Also, a sill at the outlet, and flood plain benches were to be constructed at the
inlet/outlet of the high flow side and backfilled.
Heath, Is that how we left it with Marla?
Dave W.
Dave Wanucha
NC DENR Winston Salem Region Office
NC Division of Water Resources
Transportation Permitting Unit
450 W. Hanes Mill Rd, Suite 300
Winston-Salem, NC 27105
Cell (336) 403-5655
Office (336) 776-9703
Dave.Wanucha@ncdenr.gov
-----
E-mail correspondence to and from this address may be subject to the North Carolina Public Records Law and may be
disclosed to third parties.
-----Original Message-----
From: Slaughter, Johnathan H
Sent: Friday, October 09, 2015 8:38 AM
To: Wanucha, Dave <dave.wanucha@ncdenr.gov>
Subject: FW: Draft Inspection report for R-3101 (UNCLASSIFIED)
-----Original Message-----
From: Williams, Andrew E SAW \[mailto:Andrew.E.Williams2@usace.army.mil\]
Sent: Thursday, September 24, 2015 8:31 AM
To: Slaughter, Johnathan H <hslaughter@ncdot.gov>
Cc: Williams, Andrew E SAW <Andrew.E.Williams2@usace.army.mil>
1
Subject: Draft Inspection report for R-3101 (UNCLASSIFIED)
Classification: UNCLASSIFIED
Caveats: NONE
Heath,
Please take a look at this draft compliance inspection report. Let me know if I missed anything. If not, I will finalize it. I
will also send you a copy of the final report. Thanks.
Andrew Williams
Regulatory Project Manager
U.S. Army Corps of Engineers
Raleigh Regulatory Field Office
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
919-554-4884 extension 26
The Wilmington District is committed to providing the highest level of support to the public. To help us ensure we
continue to do so, please complete the Customer Satisfaction Survey located at http://regulatory.usacesurvey.com/.
Classification: UNCLASSIFIED
Caveats: NONE
________________________________
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third
parties.
2
CESAW-RG-R
MEMORANDUM FOR RECORD
SUBJECT: Compliance Report
DA-SAW Number: SAW-2012-01963 Project Name: R-3101
City: Sparta County: Alleghany
Applicant: NCDOT
POC: Mr. Heath Slau�hter Telephone: 336-903-9202
I. FILE REVIEW FINDINGS: Date: September 14, 2015
Action: � NWP � IP � JD � Pre-App � Compliance
Yes No Remarks
Easement Recorded / Provided ❑ 0 Was not a requirement of this permit authorization
Mitigation Responsibility � ❑ Received signed mitigation form. Signature date is 28
Transfer Form/Receipt January 2014.
Submission of Plat/ As-Builts(s) ❑ 0 Was not a requirement of this permit authorization
Monitoring Report(s) ❑ 0 Was not a requirement of this permit authorization
II. FIELD VISIT FINDINGS:
Has work begun?
Is work complete?
Is work in compliance?
Mitigation Complete?
NWP/GP
Yes �� No ❑
Yes ❑ No �
Yes ❑
Yes �
No �
No ❑
Date: September 15, 2015
Individual Permit/SP
Yes � No p°�
Yes �❑ � No I❑
Yes ❑
Yes ❑
No ❑
No ❑
Remarks: During the site visit, the following�ermit sNo ites were inspected:
Sites 1 2 3 4 8 9 10 11 13 21 24 25 26 27 29 30 32 33 3� 40 42 45 46 47 48 50 51 54 55
and 56. Several of the existin�pipes had not been re�lace but rather, installed immediately
beside the existin�pipe via the jack and bore method. This was done primarily for safetX
reasons associated with keeping the road open to traffic during construction and was
coordinated with the USACE �rior to installation. The following observations were made
during the 15 September 2015 site inspection:
Site 1: A�proximately 15 linear feet of rip rap was installed on the downstream end of the
crossing for dissi�ation. The �ipe is still perched; however there is an im�oundment
immediatelv downstream. The �erched pipe should have limited im�act on aquatic life
movement.
Site 2: Durin� the site ins�ection, rip ra� was observed bein� placed within the �ermit area as
indicated in the project plans.
Site 3: Fill a�peared to have been placed within the permit area as indicated in the project
lp ans•
Site 4: Culvert was replaced with a bridge. Rip rap had been placed along the banks under the
Page 1 of 3
brid�e•
Site 8: The constructed culvert at this location was sli�htl�perched. NCDOT Division
Environmental Officer will provide recommendation for remedial action. Discussed the
installation of a lo� vane during the site visit.
Site 9: The �ermit plans indicate that 1721inear feet of stream was to be relocated at this site.
The work had been conducted a�roximately 3 weeks prior to the site inspection. The NCDOT
DEO will continue to monitor the relocation for stabilitv.
Site 10: The permit plans indicated rip rap would be installed at the outlet end. No ri� ra� had
been installed, but there did not a�ear to be any erosion issues.
Site 11: This culvert was replaced by borin_g and jackin� immediately beside the existing
culvert. A�proXimatel_y 30 linear feet of stream channel was relocated on the downstream,
outlet end of the culvert. This relocation was not indicated in the a�roved �lans. The channel
appeared stable and had a similar pattern, dimension and �rofile as the downstream receiving
stream se�ment. The be i�g of the stream is just u�slo�e of the u�stream end of the culvert.
No additional miti�ation would have been required for the 301f of relocation. Also, see Site 47
description re a� rdin� miti at� ion•
Site 13: The a�roved project plans indicated that 17 linear feet of stream would be
permanently filled at this site. The site inspection revealed that a�roximately 30 lf was filled.
This culvert was installed with the jack and bore method. The existing receivin� channel
downslo�e is relatively stee�. No additional miti�ation would have been rec�uired. Also, see
Site 47 description regardin� atg ion•
Site 21: This culvert was reali�ned, but no additional permanent loss of waters occurred.
Approximately 20 feet of rip rap was placed at the inlet end of the culvert. The rip ra� was not
shown on the project �lans.
Site 24: The crossing ap�eared to be constructed in accordance with the a�roved plans.
Site 25: This culvert was installed via jack and bore method. The existin� outlet will need to
have a small (�proximatel.�) channel installed to connect to the eXisting downstream
segment.
Site 26: This crossin�appeared to be constructed in accordance with the a�roved plans.
Site 27: This crossing a�eared to be constructed in accordance with the a�proved �lans. It
was designed with a"parallel end section", NCDOT personnel and contractors stated it was
not a good desi�n for the mountain areas, and should probably be avoided in most cases in the
future.
Sites 29 and 30: A�proximately 45 square feet of existin� wetlands had been excavated in
order to replace this project with the jack and bore method. It had been seeded and matted.
Site 32: No s�rin� box was installed at this site. The fill footprint a�eared to be �laced in
accordance with the ap�roved plans.
Site 33: This crossing a�peared to be constructed in accordance with the a�proved �lans.
Site 34: This culvert was installed adjacent to the existin�pipe, using the jack and bore
method. It resulted in a�proximately 15 linear feet of new channel at the outlet end to join it
with the downstream receivin� stream segment. The outlet end of the �ipe was scoured out
durin� a large storm event after the pipe extension was installed. Several cobble sized stones
had been tamped into the substrate to protect from additional erosion. Immediatel�pstream
of the culvert the stream was filled (Site 33) and no aquatic movement would occur throu�
the culvert at Site 34.
Site 40: The installed culvert is perched. The existin� stream is intermittent and the previous
pipe was also �erched, according to NCDOT officials and the site contractor. Pipe is resting on
existin� bedrock and could not have been buried. NCDOT will place a�roximatel_y 15 linear
feet of rip rap at the outlet end for a dissipation pad. These impacts were not shown on the
approved plan, but are needed to prevent additional scour. No additional compensatorX
Page 2 of 3
miti�ation would be required. Also, see Site 47 description regarding miti atg ion•
Site 42: This crossing a�eared to be constructed in accordance with the a�roved plans.
During the site visit, NCDOT personnel indicated that the pipe needed to be extended into the
existing�ard for safety reasons. Google earth site images revealed that the stream within that
area had been previousl�piped and that the section of pipe would just be replaced.
Site 45: This crossing a�peared to be constructed in accordance with the a�proved �lans.
Site 46: This crossin�appeared to be constructed in accardance with the a�proved �lans.
Site 47: The a�roved �lans indicated that 125 linear feet of stream channel was to be filled.
The site ins�ection revealed that this segment of stream channel was actually relocated to the
ed�e of the ROW. The iill at this site did not result in a loss of 125 lf of stream channel,
although NCDOT still provided compensatory mitigation for this feature.
Site 48: Old channel was filled in accordance with the a�roved plans. NCDOT relocated
channel upslope of the culvert extension. This channel is showing signs of active erosion and
will need to be lined with ri� ra� to �revent sedimentation in downstream stream segments•
NCDOT has �rovided compensator.�gation for all stream loss.
Site 49: This brid�e crossin�a�peared to be constructed in accordance with the a�proved
lp ans•
Site 50: NCDOT will place a sill at the outlet end of the left descendin� barrel of the newly
constructed box culvert. Additionally, a floodplain bench will be constructed within the stream
channel below the barrel as discussed with NCWRC. The construction of the flood�lain bench
will not result in a loss of stream len�th, but will �rovide far better passage of aquatic life.
Floodplain bench plans must be provided to USACE prior to construction.
Site 51: The site ins�ection revealed that the permitted rock vanes failed. NCDOT will re-
installlo v� anes•
Site 54: This crossing appeared to be constructed in accordance with the a�proved plans.
Site 55 and 56: NCDOT constructed a new pipe next to the existin� pipe. No additional
impacts to jurisdictional streams and wetlands were required.
III. CONCLUSIONS Date: September 24, 2015
In Compliance: � Yes � No If No, (i.e., out of compliance), describe concerns:
See remedial action required, listed below.
Remedial Actions Required: �Yes � No If YES, describe actions to be taken:
Site 8: The constructed culvert at this location was slightly perched. NCDOT Division Environmental
Officer will provide recommendation for remedial action. Discussed the installation of a lo� vane durin�
the site visit. Site 9: The permit plans indicate that 172 linear feet of stream was to be relocated at this
site. The work had been conducted a�roximatel_y 3 weeks prior to the site inspection. The NCDOT DEO
will continue to monitor the relocation for stability. Site 50: NCDOT will �lace a sill at the outlet end of
the left descendin� barrel of the newly constructed box culvert. Additionally, a floodplain bench will be
constructed within the stream channel below the barrel as discussed with NCWRC. The construction of
the flood�lain bench will not result in a loss of stream length, but will �rovide for better �assage of
aquatic life. Floodplain bench plans must be provided to USACE �rior to construction.
Site 5 L• The site ins�ection revealed that the �ermitted rock vanes failed. NCDOT will re-install lo�
vanes.
Corps Official:
Page 3 of 3
Date: September 24, 2015