HomeMy WebLinkAbout20121081 Ver 3_USACE Permit_20240205DEPARTMENT OF THE ARMY
U.S. ARMY CORPS OF ENGINEERS, WILMINGTON DISTRICT
ASHEVILLE REGULATORY FIELD OFFICE
151 PATTON AVENUE ROOM 208
ASHEVILLE NC 28801
February 5, 2024
Regulatory Program/Division
Wendy Patoprsty
Blue Ridge Conservancy
416 Aho Road
Blowing Rock, NC 28607
Via Email: wendy@blueridgeconservancy.org
Dear Ms. Patoprsty:
This letter is in response to the Pre -Construction Notification (PCN) you submitted to
the Wilmington District, Asheville Regulatory Field Office on December 13, 2023, for a
Department of the Army Nationwide permit (NWP) verification. This project has been
assigned the file number 2023-02438 and is known as Middle Fork Greenway Section 5
— Boone Gorge Park. This file number should be referenced in all correspondence
concerning this project.
A review of the information provided indicates that the proposed work would include
the construction of greenway trail to include two bridge crossings, and bank stabilization
activities associated with a fishing pier and stream improvements. The project/review
area is at/near 276 Old Blowing Rock Road, at Latitude 36.190126 and Longitude -
81.657340; in Boone, Watauga County, North Carolina.
We have determined that the proposed work is authorized by Nationwide Permit #13
and #33 pursuant to authorities under Section 404 of the Clean Water Act (33 U.S.C. §
1344). Impacts authorized are summarized in the table below:
Impact #
Reason/Type
Stream Name
Impact
Length
Impact
Acreage
S1
Bridge / Temp
Middle Fork New River
(MFNR)
40
0.046
S2
Bank Stabilization /
Perm
MFNR
20
0.009
S3
Crossing/TempCrossing/Temp
UT to MFNR
20
0.008
S4
Pier Stabilization
/Perm
MFNR
25
0.011
S5
Bank Stabilization
MFNR
250
0.293
Total
355
0.367
Based on recommendations from the North Carolina Wildlife Resource Commission,
in -stream work is prohibited between October 15 and April 15 in order to minimize
impacts to trout reproduction and is hereby incorporated as a special condition of this
permit authorization. Attached is their letter for reference which provides additional
recommendations for your consideration.
The proposed work must be accomplished in strict accordance with the general
permit conditions, any regional conditions, the application materials, and the enclosed
plans. If the extent of the project area and/or nature of the authorized impacts to waters
are modified, a revised PCN must be submitted to this office for written approval before
work is initiated. Any violation of permit conditions or deviation from your submitted
plans may subject the permittee to enforcement action.
This verification is valid until March 14, 2026, unless prior to this date the subject
NWP(s) is suspended, revoked, or is modified such that the activity no longer complies
with the terms and conditions of this NWP. If you commence or are under contract to
commence this activity before the date that the relevant NWP is modified or revoked,
you will have 12 months from the date of the modification or revocation of the NWP to
complete the activity under the present terms and conditions of this NWP.
This NWP verification does not preclude the necessity to obtain any other Federal,
State, or local permits, licenses, and/or certifications, which may be required.
If you have any questions related to this verification or have issues accessing
documents referenced in this letter, please contact Amanda Fuemmeler, Project
Manager of the Asheville Regulatory Field Office at 828-271-7980 ext. 4225, by mail at
the above address, or by email at amanda.jones@usace.army.mil. Please take a
moment to complete our customer satisfaction survey located at
https:Hregulatory.ops.usace.army.miI/customer-service-survey/.
Sincerely,
Amanda Fuemmeler
Project Manager
Enclosures
Cc (w/enclosures)
Carrie Caviness, Interface Environmental Consulting (via email)
Compliance Certification Form
Action ID Number: 2023-02438 County: Watauga
Permittee: Blue Ridge Conservancy, Wendy Patoprsty
Project Name: Middle Fork Greenway Section 5 — Boone Gorge Park
Date Verification Issued: 2/5/2024
Project Manager: Amanda Fuemmeler
Upon completion of the activity authorized by this permit and any mitigation required by
the permit, sign this certification and return it to the following email address:
ashevillencreg(a usace.army.mil
Please note that your permitted activity is subject to a compliance inspection by a U. S.
Army Corps of Engineers representative. Failure to comply with any terms or conditions
of this authorization may result in the Corps suspending, modifying or revoking the
authorization and/or issuing a Class I administrative penalty, or initiating other
appropriate legal action.
hereby certify that the work, and mitigation (if applicable), authorized by the above
referenced permit has been completed in accordance with the terms and conditions of
the said permit including any general or specific conditions.
Date Authorized Work Started:
Completed:
Describe any deviations from permit (attach drawing(s) depicting the deviations):
*Note: The description of any deviations on this form does not constitute approval by the Corps.
Signature of Permittee
Date
Surveyed
BRC Parcel
r-'/N:281958778000F
_A11=
LEGEND
SURVEYED BOUNDARY
SURVEYED ADJOIN
COUNTY GIS BNDY
MFNR TOP OF BANK
PERM EASEMENT REQUEST
MFG ALIGNMENT
MFG BOARDWALK/BRIDGE
0 200 400
Feet
BANK STABILIZATION
PERM IMPACTS
ADA FISHING PER
PERM IMPACTS
BR DGE 2
PERM IMPACTS
GIS Bndy
ASU Parcel
PIN: 2819678860000
PERM EASEMEN
c
\ REQUEST (,n
—3.635 ACRE'
w
N
MFG Alignment S�R� U, _ �, eyEO Toe
UT MFNR "�"'yam Gore
TEMP IMPACTS °°"(to be
determined
Surveyed EPHEMERAL '%, by survey)
BRC Parcel —1.7 acres
PIN: 2819587780000 TEMP IMPACTS No Adjoin
BRIDGE 1
TEMP IMPACTS J�
_ rRM EASEMENT,/
EQUEST
0.503 ACRES
\ \ GIS Bndy
I \ Wat Co Parcel
J \\ Surveyed PIN: 2819761780000
Adjoin Line \ r
\\ PIN:2819664689000
\ GIS Bndy
ASU Parcel
\\ PIN: 2819760912000
GIS Bndy
ASU Parcel
\ SIN: 2819762 9000
BASIS OF DATA
SURVEYED BRC BOUNDARY DATA PROVIDED BY SURVEY PROS, INC.
SURVEYED EASEMENT LINES PROVIDED BY MATTERN & CRAIG ENGINEERS AND SURVEYORS, INC.
GIS BOUNDARY LINES AND AERIAL PHOTOGRAPHY ARE PUBLICLY AVAILABLE DATA .
EASEMENT REQUEST AREAS AND MFG ALIGNMENTS GENERATED BY IEC, LLC. (11 /2023)
0
IEC
PROPOSED INVASIVE
REMOVAL REG FLOODWAY
600 ems° LINE FROM FRIS
\ SURVEYED TOP
OF BANK
\ X00 \ `
xoo PROPOSED TOEWOOD
SLOPING FOR PROPOSED LOGVANE
PEDESTRIAN ACCESS
+
PROPOSED STREAMBANK
` \ SLOPING
PROPOSED INVASIVE
REMOVAL
PROPOSED ADA
FISHING PIER
0 60 120
�
Fee\ � �00
UPPER
LEFT
BRIDGE
(BRIDGE
tream
1)
3248
3240
'
y
\\'----
♦
f
3232
Boreho
--
-----
3224
1+ 5 1+50 1+25
1+00
Station
3216
0+75 0+50 0+25
0+00 -0 10
BRIDGE 1 TEMP IMPACTS
DUE TO CONSTRUCTION; SETTING
TEMP CROSSING AND ACCESSING
\ ABUTMENT LOCATIONS FOR
CONCRETE POURS
Ok00
N
W
Z�Z
f�
7
Q
U
o
LEGEND
BRIDGE ABUTMENT 322 .
Q a nu 2 / REG FLOODWAY
—� _ / (SURVEYED)
LOWER BRIDGE
(BR DGE 2)
3176
13168
------
2 6-----
----------------
----------- -
3160
, 6 „
'
3152
RIVE
RIGHT
ore hRIVER
LEFT
3144
1+ 5 1+50 1+25
1+ DO
Station
0+75 0+50 0+25 3136
0+00 -0 10
/ RIVER G
8 F LEFT RIVER
o RIGHT
BRIDGE ABUTMENTS + �� BRIDGE 2 PERM IMPACTS
STREAMBANK SLOPING AND
r J ( STABILIZATION. RIPRAP
PROP GREENWAY CURRENTLY PROPOSED; TBD
ALIGNMENT REVISE TO MATTING PER
58 STRUCTURAL ENGINEERS REC
o
LEGEND
n ' / REG FLOODWAY
LOW SPOT/
FLOW -WAY TOB/OHWM
(SURVEYED)
ADA FISHING PER
STA 2+ 02
3172
316
168
316
71
316
160
CD
315
C
315
152
r�
314
�°
314
144
314
313
136
1+00
0+00
—0+10
Station
3
3
3
3
3
,-SMOOTH TRANSITION FROM
4
ELEV 3158.
ASPHALT TO DECKING
TYPICAL
—
FLOW
DEPTH
a��NDriu
UTSLOPE O 5%
2
SLOPE (4:1)
a
4
�iN 12' own+
0+75 0+50 0+25
PERMANENT IMPACT
DUE TO SLOPING AND
V/—X//j/�RIPRAP STABILIZATION
PROP ADA FISHING PIER
AND ADJACENT STREAMBANK
SLOPING CONTOURS
RIVER
RIGHT
I C(`CN In
/ REG FLOODWAY
TOB/OH WM
(SURVEYED)
9 North Carolina Wildlife Resources Commission 9
Cameron Ingram, Executive Director
January 11, 2024
Ms. Amanda Fuemmeler
U.S. Army Corps of Engineers, Regulatory Branch
151 Patton Avenue, Room 208
Asheville, North Carolina 28801-5006
SUBJECT: Middle Fork Greenway Section 5 — Boone Gorge Park
Middle Fork South Fork New River and Unnamed Tributary (UT), Watauga
County
Dear Ms. Fuemmeler:
Biologists with the North Carolina Wildlife Resources Commission (NCWRC) reviewed an
application to temporarily impact 60 ft and permanently impact 295 ft of the Middle Fork South
Fork New River and an unnamed tributary (UT) in Watauga County. Our comments on this
application are offered for your consideration under provisions of the Clean Water Act of 1977
(33 U.S.C. 466 et. seq.) and Fish and Wildlife Coordination Act (48 Stat. 401, as amended; 16
U.S.C. 661-667d).
There are Brown Trout in the vicinity of the project, and in -stream activities should be avoided
between October 15 and April 15 in order to minimize impacts to trout reproduction. The site is
within the South Fork New and New River Aquatic Habitat, a natural area designated by the NC
Natural Heritage Program and rated Exceptional due to the rich aquatic community it supports,
which includes the following rare species in the vicinity of the project: Kanawha Minnow
[Phenacobius teretulus, NC Special Concern (SC)]. Tonguetied Minnow [Exoglossum laurae,
NC Significantly Rare (SR)], Kanawha Darter (Etheostoma kanawhae, NC SR), and Appalachia
Darter (Percina gymnocephala, NC SR). It is likely that Eastern Hellbender (Cryptobranchus
alleganiensis, US Federal Species of Concern, NC SC) is within the project area, as well.
The application proposes to install two bridges and stabilize a reach of the Middle Fork South
Fork New River. Bridge construction will involve 60 ft of temporary impacts; for a bridge,
equipment will be set on a low floodplain bench, and a temporary culvert will be installed in the
UT. Permanent impacts will involve riprap stabilization near bridge footers and under a fishing
pier. In addition, 250 ft of the Middle Fork South Fork River will be stabilized with bank
grading, toewood, removal of a mid -channel bar, and one log vane.
Mailing Address: Habitat Conservation • 1721 Mail Service Center • Raleigh, NC 27699-1721
Telephone: (919) 707-0220 • Fax: (919) 707-0028
Middle Fork Greenway Page 2 January 11, 2024
Middle Fork S Fork New & UT, Watauga Co
We offer the following recommendations to minimize impacts to the aquatic community:
1. In -channel work should be accomplished as quickly as possible and vigilance used in
sediment and erosion control during site preparation, construction, and clean up. Disturbed
areas should be seeded, mulched and/or matted as soon as possible, preferably at the end of
each work day.
2. Any erosion control matting used should be free of nylon or plastic mesh, as this type of
mesh netting frequently entangles wildlife and is slow to degrade, resulting in a hazard that
may last for years.
3. In -stream activities should be done outside the October 15 to April 15 trout moratorium to
minimize impacts to Brown Trout reproduction.
4. Work should be performed during low flows. For instream work, we recommend diverting
flows around the work area especially at bank tie-in locations to reduce the risk of fine
sediment liberation and loss.
5. A preliminary planting plan includes River Birch, which we recommend removing unless
already naturally occurring on -site. Sweet Birch is a good substitute.
Thank you for the opportunity to review and comment on this project. Please contact me at
(828) 400-4223 if you have any questions about these comments.
Sincerely,
Andrea Leslie
Mountain Region Coordinator, Habitat Conservation Program
ec: Carrie Caviness, Interface Environmental Consulting
Seren Homer, NC Division of Water Resources