HomeMy WebLinkAbout20231153 Ver 2_Meeting Minutes_20231011WILDLANDS
ENGINEERING
Regulatory Stakeholder Meeting #1— Meeting Summary
Stakeholder Meeting
Meeting: Shulls Mill Dam Removal Project
Wildlands Project No. 005-50002
Date: Friday September 11, 2023 at 10am —12pm
Minutes distributed 11/3/23
Location: Shulls Mill Dam Project Site, Boone, NC
Attendees
Jake McLean, Wildlands Engineering-jmclean@wildlandseng.com
Andy Hill, MountainTrue
Hannah Woodburn, MountainTrue
Gray Jernigan, MountainTrue
Erin McCombs, American Rivers
Andrea Leslie, NC Wildlife Resources Commission
Sue Homewood, NCDEQ (401 permitting)
Seren Homer, NCDEQ (401 permitting)
Amanda Fuemmeler, US Army Corps of Engineers -Asheville (404 permitting)
Meeting Summary
Discussed Assessment Activities to Date
• Topographic survey
• Completed JD work
• Installed stream gage to look at flows and rainfall -runoff response
• Geomorphic evaluation to look at bankfull channel geometry
• Geologic evaluation of hillslope processes and impact on channel form
• Invasives management
Discussed the Proposed Approach
Remove sediment in formerly impounded area upstream of dam down to the leave of predicted
pre -dam bed level that is to be approximated based on confluence of evidence from assessment
activities and summarized in a technical memo as part of permitting application
Dispose of sediment onsite to rebuild eroding left bank with secondary disposal area to likely
target the right bank rock bar at and downstream of the dam where loose material would be
properly protected and revegetated and where hydraulic modeling would support an acceptably
low level of risk of material washing out.
Restore and protect the left bank which may require some tree removal and excavation beyond
the existing top of bank. Material on the left bank close to the channel is largely part of
deposition from the former impoundment and easily erodible. The restoration will protect the
channel toe with large boulders and wood and stabilize the bank material with matting and
reestablish native woody vegetation for long-term stability.
Project may use dam concrete material to form the base of restored bank. Break up enough to
allow for normal tree growth, bury in bank to prevent future exposure — use natural boulders as
face protection rock. Wildlands indicated that natural boulders from area to right of dam may
be used extensively and the area renaturalized, as this would be a lesser impact than offsite
boulder import although offsite import may be used as necessary.
Jake verified for Amanda that both percussive activities and tree clearing were going to be part
of the project.
Discussed Recent Geotechnical Exploration Activity and Findings
• Conducted test digging with excavator to evaluate depth of sediment, refusal depths, ability to
execute preliminary channel diversion approach (ability to move or break up large rocks on site)
• Findings were basically as follows:
o The upper end of the former impoundment has shallow bedrock leading to the
conclusion that the project channel manipulation activities should start below the point
bar and bedrock area since the upstream morphology is bedrock driven.
o The remainder of the former impoundment does not have bedrock. Test pits were able
to be dug to a depth of —6-8' and had consistent gravelly and sandy material. A thin (6-
12") layer of organic (leafy) material was present with additional gravel and sandy
material below.
■ The thin layer of material is not judged to pose an undue risk to the project. This
material will be maintained onsite and managed to prevent its downstream
transport.
It is anticipated that removing 3-6' of material from the bed between the
bedrock controlled area and the dam would return the channel to its original
configuration.
Project Timing
Mountaintrue & American Rivers have verbal agreement to receive grant funding to construct
project. They will know more details in November.
Jake indicated target project window was early spring to early summer, but that could
potentially be ready to start sooner.
Other Questions and Discussion
Wildlands is going to check on scoping letters.
Amanda offered that Wildlands could submit permits a little earlier in process to start
consultation process.
Jake told Andrea that design team would submit preliminary memo in advance of permitting
submittal that could be used by WRC to evaluate proposed approach to flow diversion, material
relocation, and other considerations. Jake will plan to meet with WRC in November -December
of 2023 or during dormant season to review plan and refine approach as needed to meet
resource concerns.
Shulls Mill Dam — Regulatory Stakeholder Meeting 10.11.23 (Summary 10.26.23)
• Jake and Andy have both talked to County and no real concerns about county permitting
process (floodplain permit).
Next Steps
• Provide tree clearing information to Corps / USFWS to start consultation, or submit permit
application with this and other information.
o Whatever happens, Jake needs to make sure that if tree clearing has to occur in winter
that this is 1-known and 2-acted upon prior to the beginning of the bat nesting period.
• Work on getting plans to 60% and doing a field review with WRC. Submit technical memo brief
to describe rationale for design as part of this. Refine plans and package after and submit 75%
plans and full memo with PCN to get permitting started.
• Finish no -rise modeling and submit to County in early 2024.
• Finish ESC plans and submit ESC package in early 2024.
Shulls Mill Dam — Regulatory Stakeholder Meeting 10.11.23 (Summary 10.26.23)