HomeMy WebLinkAboutSAW-2021-01091 NCDOT HB-0001 Alligator River Bridge NWP (003)U.S. ARMY CORPS OF ENGINEERS WILMINGTON DISTRICT Action Id. SAW-2021-01091 County: Tyrrell County U.S.G.S. Quad: Fort Landing GENERAL PERMIT (REGIONAL AND NATIONWIDE) VERIFICATION Permittee: Jason Dilday NC DOT Address: 1598 Mail Service Center Raleigh NC, 27699-1598 Telephone Number: (919) 707-5785 Size (acres) 20 Nearest Town Columbia Nearest Waterway Alligator River River Basin Albemarle-Chowan USGS HUC 03010205 Coordinates Latitude: 35.907294; Longitude:-76.028807 Location description: The project area is located on either side of the Alligator River along the alignment of US 64 approximately 13.5 miles east of the town of Columbia in Tyrrell County, North Carolina. Description of projects area and activity: NCDOT proposes to drive 20 test piles at 15 different locations within the alianment of the Droaosed Alliaator River Bridae location. These Diles will be 36" or 48" in diameter and will be cut off below the mudline when the project is completed. Additionally, 19 piles 30" in diameter will be installed along a 1,080 foot alignment at 60 feet aaart for the moorina of eauiament for this Droiect. These Diles will be removed at the completion of the project. Applicable Law: ❑ Section 404 (Clean Water Act, 33 USC 1344); ® Section 10 (Rivers and Harbors Act, 33 USC 403) Authorization: Regional General Permit Number and/or Nationwide Permit Number: 6&33 SEE ATTACHED RGP or NWP GENERAL, REGIONAL AND/OR SPECIAL CONDITIONS Your work is authorized by the above referenced permit provided it is accomplished in strict accordance with the attached conditions and your submitted application and attached information dated January 8, 2024. Any violation of the attached conditions or deviation from your submitted plans may subject the permittee to a stop work order, a restoration order, a Class I administrative penalty, and/or appropriate legal action. This verification will remain valid until the expiration date identified below unless the nationwide and/or regional general permit authorization is modified, suspended or revoked. If, prior to the expiration date identified below, the nationwide and/or regional general permit authorization is reissued and/or modified, this verification will remain valid until the expiration date identified below, provided it complies with all requirements of the modified nationwide permit. If the nationwide and/or regional general permit authorization expires or is suspended, revoked, or is modified, such that the activity would no longer comply with the terms and conditions of the nationwide permit, activities which have commenced (i.e., are under construction) or are under contract to commence in reliance upon the nationwide and/or regional general permit, will remain authorized provided the activity is completed within twelve months of the date of the nationwide and/or regional general permit's expiration, modification or revocation, unless discretionary authority has been exercised on a case - by -case basis to modify, suspend or revoke the authorization. Activities subject to Section 404 (as indicated above) may also require an individual Section 401 Water Quality Certification. You should contact the NC Division of Water Resources (telephone 919- 807-6300) to determine Section 401 requirements. For activities occurring within the twenty coastal counties subject to regulation under the Coastal Area Management Act (CAMA), prior to beginning work you must contact the N.C. Division of Coastal Management in Morehead City, NC, at (252) 808-2808. This Department of the Army verification does not relieve the permittee of the responsibility to obtain any other required Federal, State or local approvals/permits. If there are any questions regarding this verification, any of the conditions of the Permit, or the Corps of Engineers regulatory program, please contact Kyle Barnes at (910) 251-4584 or Kyle.W.Barnes(a)usace.army.mil. o� 2024.01.26 13:18:44 Corps Regulatory Official: "'� 0s'00' Date: January 26, 2024 Expiration Date of Verification: March 14, 2026 The Wilmington District is committed to providing the highest level of support to the public. To help us ensure we continue to do so, please complete our Customer Satisfaction Survey, located online at https:Hregulatoly.ops.usace.army.mil/customer-service-survey/ SAW-2021-01091 SPECIAL CONDITIONS 1. The NCDOT shall implement the "Guidelines for Avoiding Impacts to the West Indian Manatee: Precautionary Measures for Construction Activities in North Carolina Waters" as identified by the USFW Service. Action ID Number: SAW-2021-01091 County: Tyrrell County Permittee: Jason Dilday NC DOT Project Name: NCDOT HB-0001 Alligator River Bridge Date Verification Issued: January 26, 2024 Project Manager: Kyle Barnes Upon completion of the activity authorized by this permit and any mitigation required by the permit, sign this certification and return it to the following address: US ARMY CORPS OF ENGINEERS WILMINGTON DISTRICT Attn: Kyle Barnes Please note that your permitted activity is subject to a compliance inspection by a U. S. Army Corps of Engineers representative. Failure to comply with any terms or conditions of this authorization may result in the Corps suspending, modifying or revoking the authorization and/or issuing a Class I administrative penalty, or initiating other appropriate legal action. I hereby certify that the work authorized by the above referenced permit has been completed in accordance with the terms and condition of the said permit, and required mitigation was completed in accordance with the permit conditions. Signature of Permittee Date NOTIFICATION OF ADMINISTRATIVE APPEAL OPTIONS AND PROCESS AND REQUEST FOR APPEAL Applicant: File Number: SAW-2021-01091 Date: January 26, NCDOT/Jason Dilday 2024 Attached is: See Section below INITIAL PROFFERED PERMIT (Standard Permit or Letter of permission) A PROFFERED PERMIT (Standard Permit or Letter of permission) B PERMIT DENIAL WITHOUT PREJUDICE C PERMIT DENIAL WITH PREJUDICE D APPROVED JURISDICTIONAL DETERMINATION E PRELIMINARY JURISDICTIONAL DETERMINATION F SECTION I The following identifies your rights and options regarding an administrative appeal of the above decision. Additional information may be found at httl)s://www.usace.army.miI/Missions/Civil-Works/Requlatory-Program- and-Permits/a eals/ or Corps regulations at 33 CFR Part 331. A: INITIAL PROFFERED PERMIT: You may accept or object to the permit • ACCEPT: If you received a Standard Permit, you may sign the permit document and return it to the district engineer for final authorization. If you received a Letter of Permission (LOP), you may accept the LOP and your work is authorized. Your signature on the Standard Permit or acceptance of the LOP means that you accept the permit in its entirety, and waive all rights to appeal the permit, including its terms and conditions, and approved jurisdictional determinations associated with the permit. • OBJECT: If you object to the permit (Standard or LOP) because of certain terms and conditions therein, you may request that the permit be modified accordingly. You must complete Section II of this form and return the form to the district engineer. Upon receipt of your letter, the district engineer will evaluate your objections and may: (a) modify the permit to address all of your concerns, (b) modify the permit to address some of your objections, or (c) not modify the permit having determined that the permit should be issued as previously written. After evaluating your objections, the district engineer will send you a proffered permit for your reconsideration, as indicated in Section B below. B: PROFFERED PERMIT: You may accept or appeal the permit • ACCEPT: If you received a Standard Permit, you may sign the permit document and return it to the district engineer for final authorization. If you received a Letter of Permission (LOP), you may accept the LOP and your work is authorized. Your signature on the Standard Permit or acceptance of the LOP means that you accept the permit in its entirety, and waive all rights to appeal the permit, including its terms and conditions, and approved jurisdictional determinations associated with the permit. • APPEAL: If you choose to decline the proffered permit (Standard or LOP) because of certain terms and conditions therein, you may appeal the declined permit under the Corps of Engineers Administrative Appeal Process by completing Section II of this form and sending the form to the division engineer. This form must be received by the division engineer within 60 days of the date of this notice. C. PERMIT DENIAL WITHOUT PREJUDICE: Not appealable You received a permit denial without prejudice because a required Federal, state, and/or local authorization and/or certification has been denied for activities which also require a Department of the Army permit before final action has been taken on the Army permit application. The permit denial without prejudice is not appealable. There is no prejudice to the right of the applicant to reinstate processing of the Army permit application if subsequent approval is received from the appropriate Federal, state, and/or local agency on a previously denied authorization and/or certification. D: PERMIT DENIAL WITH PREJUDICE: You may appeal the permit denial You may appeal the denial of a permit under the Corps of Engineers Administrative Appeal Process by completing Section II of this form and sending the form to the division engineer. This form must be received by the division engineer within 60 days of the date of this notice. E: APPROVED JURISDICTIONAL DETERMINATION: You may accept or appeal the approved JD or provide new information for reconsideration • ACCEPT: You do not need to notify the Corps to accept an approved JD. Failure to notify the Corps within 60 days of the date of this notice means that you accept the approved JD in its entirety and waive all rights to appeal the approved JD. • APPEAL: If you disagree with the approved JD, you may appeal the approved JD under the Corps of Engineers Administrative Appeal Process by completing Section II of this form and sending the form to the division engineer. This form must be received by the division engineer within 60 days of the date of this notice. • RECONSIDERATION: You may request that the district engineer reconsider the approved JD by submitting new information or data to the district engineer within 60 days of the date of this notice. The district will determine whether the information submitted qualifies as new information or data that justifies reconsideration of the approved JD. A reconsideration request does not initiate the appeal process. You may submit a request for appeal to the division engineer to preserve your appeal rights while the district is determining whether the submitted information qualifies for a reconsideration. F: PRELIMINARY JURISDICTIONAL DETERMINATION: Not appealable You do not need to respond to the Corps regarding the preliminary JD. The Preliminary JD is not appealable. If you wish, you may request an approved JD (which may be appealed), by contacting the Corps district for further instruction. Also, you may provide new information for further consideration by the Corps to reevaluate the JD. POINT OF CONTACT FOR QUESTIONS OR INFORMATION: If you have questions regarding this decision you If you have questions regarding the appeal process, or may contact: to submit your request for appeal, you may contact: District Engineer, Philip Shannin Wilmington Regulatory Division, Regulatory Appeals Review Officer Attn: Kyle Barnes South Atlantic Division 2407 West 5' Street 60 Forsyth St SW, Floor M9 Washington, North Carolina 27889 Atlanta, Georgia 30303-8803 Philip.A.Shan nin2(a)usace.army.mil 404-562-5136 SECTION II — REQUEST FOR APPEAL or OBJECTIONS TO AN INITIAL PROFFERED PERMIT REASONS FOR APPEAL OR OBJECTIONS: (Describe your reasons for appealing the decision or your objections to an initial proffered permit in clear concise statements. Use additional pages as necessary. You may attach additional information to this form to clarify where your reasons or objections are addressed in the administrative record.) ADDITIONAL INFORMATION: The appeal is limited to a review of the administrative record, the Corps memorandum for the record of the appeal conference or meeting, and any supplemental information that the review officer has determined is needed to clarify the administrative record. Neither the appellant nor the Corps may add new information or analyses to the record. However, you may provide additional information to clarify the location of information that is already in the administrative record. RIGHT OF ENTRY: Your signature below grants the right of entry to Corps of Engineers personnel, and any government consultants, to conduct investigations of the project site during the course of the appeal process. You will be provided a 15-day notice of any site investigation and will have the opportunity to participate in all site investigations. Date: Signature of appellant or agent. Email address of appellant and/or agent: Telephone number: