From: Bailey, David E CIV USARMY CESAW (USA) <David.E.Bailey2@usace.army.mil>
Sent: Wednesday, January 24, 2024 2:30 PM
To: Hartshorn, Jason; anh.nguyen@vinfastauto.com; Teague, Jeff L
Cc: Homewood, Sue; Mellor, Colin; Jason Steele; Chris Rivenbark; Capito, Rachel A CIV
USARMY CESAW (USA)
Subject: [External] RE: Standard (Individual) Permit: Vinfast EV manufacturing complex (Project
Blue) and associated infrastructure (NCDOT STIP No. HE-0006 and utility
improvements), Chatham and Lee Counties; SAW-2014-00610
Follow Up Flag: Follow up
Flag Status: Flagged
CAUTION: External email. Do not click links or open attachments unless verified. Report suspicious emails with the Report Message
button located on your Outlook menu bar on the Home tab.
Hi Jason. Thanks you for consolidating all of the forms. I have received all of the required countersigned MRTFs for the
following components of the Vinfast project:
• Project Blue component Phase 1B, and
• Utilities component.
Note, however, that the Corps of Engineers permit requires that the compensatory mitigation requirement for Phases
113 and 1C of the NCDOT HE-0006 component be satisfied (i.e. countersigned MRTFs must be received by the Corps)
"prior to initiating any impacts as authorized by this permit." As such, once the two MRTFs for Phases 113 and 1C of the
NCDOT HE-0006 component are submitted, then the compensatory mitigation requirements for the Vinfast Project Blue
component Phase 1B, Utilities component, and Phases 113 and 1C of the NCDOT HE-0006 component per Permit Special
Condition 28 will be satisfied.
Note also the phased compensatory mitigation requirements prior to initiating any authorized impacts in Project Blue
Phase 3 and Phases 1D, 1E, 2A, and 2B of the NCDOT HE-0006 component. Please let me know if you have any
questions.
-Dave Bailey
David E. Bailey, PWS
Chief, Raleigh Regulatory Field Office
US Army Corps of Engineers
CE-SAW-RG-R
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
Mobile: (919) 817-2436
Email: David. E.Bailey2@usace.army.miI
We would appreciate your feedback on how we are performing our duties. Our automated Customer Service Survey is
located at: https://regulatory.ops.usace.army.mil/customer-service-survey/
Thank you for taking the time to visit this site and complete the survey.
From: Hartshorn, Jason <jason.hartshorn@kimley-horn.com>
Sent: Tuesday, January 23, 2024 5:09 PM
To: Bailey, David E CIV USARMY CESAW (USA) <David.E.Bailey2@usace.army.mil>; anh.nguyen@vinfastauto.com;
Teague, Jeff L <jlteague@ncdot.gov>
Cc: Bowers, Todd <bowers.todd@epa.gov>; Homewood, Sue <sue.homewood@deq.nc.gov>; Fennel, Tommy E CIV
USARMY CESAW (USA)<Tommy.E.Fennel @usace.army.mil>; cmellor@ncdot.gov; Jason Steele
<Jason.Steele@freese.com>; Pete Benjamin <pete_benjamin@fws.gov>; Amy Staley <astaley@res.us>; Williams, Kelly
<kelly.williams@deq.nc.gov>; Harmon, Beth <beth.harmon@ncdenr.gov>; Camden Brunick
<cbrunick@wildlandseng.com>; Gledhill-earley, Renee <renee.gledhill-earley@dncr.nc.gov>; Davis, Erin B CIV USARMY
CESAW (USA) <Erin.B.Davis@usace.army.mil>; Tugwell, Todd J CIV USARMY CESAW (USA)
<Todd.J.Tugwell@usace.army.mil>; Chris Rivenbark <crivenbark@rkk.com>
Subject: [Non-DoD Source] RE: Standard (Individual) Permit: Vinfast EV manufacturing complex (Project Blue) and
associated infrastructure (NCDOT STIP No. HE-0006 and utility improvements), Chatham and Lee Counties; SAW-2014-
00610
Dave-
VinFast has completed payment of the required mitigation for the VinFast manufacturing complex (Sites 1 and 2) and
the Sanford utility improvements (all phases). NCDOT is currently finalizing the mitigation on their end following NCDOT
procedures and we anticipate that will be wrapped up shortly.
You were already copied on these, but for sake of continuity I wanted to follow up and provide the signed MRTFs for the
non-NCDOT impacts in a single email. With the previously conducted pre -construction meeting, and with the mitigation
payments completed, can you review the attached documentation and confirm that the mitigation requirement is
complete for the VinFast and Sanford pieces of this project? The contractors are standing by to mobilize, however we
wanted to confirm with USACE before any impact areas are released.
NCDWR has also received these and is reviewing to confirm compliance with NCDWR mitigation requirements as well.
Thanks!
-Jason
Jason Hartshorn, PWS
Kimley-Horn 1 421 Fayetteville Street, Suite 600, Raleigh, NC 27601
Direct: 919 678 4155 1 Mobile: 919 417 1781
From: Bailey, David E CIV USARMY CESAW (USA)<David.E.Bailey2@usace.army.mil>
Sent: Monday, December 11, 2023 4:33 PM
To: anh.nguyen@vinfastauto.com; Teague, Jeff L <jlteague@ncdot.gov>
Cc: Hartshorn, Jason <jason.hartshorn@kimley-horn.com>; Bowers, Todd <bowers.todd@epa.gov>; Homewood, Sue
<sue.homewood@deg.nc.gov>; Fennel, Tommy E CIV USARMY CESAW (USA)<Tommy.E.Fennel@usace.army.mil>;
cmellor@ncdot.gov; Jason Steele <Jason.Steele@freese.com>; Pete Benjamin <pete beniamin@fws.gov>; Amy Staley
<astalev@res.us>; Williams, Kelly <kelly.williams@deq.nc.gov>; Harmon, Beth <beth.harmon@ncdenr.gov>; Camden
Brunick <cbrunick@wildlandseng.com>; Gledhill-earley, Renee <renee.gledhill-earlev@dncr.nc.gov>; Davis, Erin B CIV
USARMY CESAW (USA) <Erin.B.Davis@usace.army.mil>; Tugwell, Todd J CIV USARMY CESAW (USA)
<Todd.J.Tugwel I @ usace.a rmy. mi I>
Subject: Standard (Individual) Permit: Vinfast EV manufacturing complex (Project Blue) and associated infrastructure
(NCDOT STIP No. HE-0006 and utility improvements), Chatham and Lee Counties; SAW-2014-00610
Ms. Nguyen and Mr. Teague,
The proffered permit (i.e. Standard Permit — Second Time Out Package) for the above referenced project is attached to
this email. Importantly, this authorization includes multiple Compensatory Mitigation requirements (RES, Wildlands, and
NCDMS). Due to the file size of the permitted project plans I have provided a DoD SAFE link email under separate cover
containing the permitted plansheets for the Project Blue, HE-0006, and utilities project components as well as the HDD
contingency plan (referenced in Permit Special Conditions 1, 19, and 20); these documents are part of this permit. Note
that hard copies of these documents will not be distributed unless specifically requested.
Please let me know if you have any questions.
Sincerely,
Dave Bailey
David E. Bailey, PWS
Chief, Raleigh Regulatory Field Office
US Army Corps of Engineers
CE-SAW-RG-R
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
Mobile: (919) 817-2436
Email: David. E.Bailey2@usace.army.miI
We would appreciate your feedback on how we are performing our duties. Our automated Customer Service Survey is
located at: https://regulatory.ops.usace.army.mil/customer-service-survey/
Thank you for taking the time to visit this site and complete the survey.