HomeMy WebLinkAboutNCC200124_NOT Closeout Documents_20240103 Sedimentation/Construction Stormwater Inspection Report
North Carolina Department of Environmental Quality
Land Resources: 610 East Center Avenue, Suite 301,Mooresville,NC 28115 (704) 663-1699
County: Catawba Project: Mountain Creek Park River basin: Catawba
Person financially responsible:Catawba County-John T Cameron,Construction Project#: CATAW-2020-007
Manager
Address: 25 Government Dr,Newton,NC 28658
1, Project Location: Little Mountain Road,Sherrills Ford
Pictures: No
2. Weather and soil conditions: Sunny,workable soil • Initial inspection: No
3, Is site currently under notice of violation? No
4. Is the site in compliance with S.P.C.A.and rules? Yes If no,check violations below:
5. Violations:
6, Is the site in compliance with NPDES Permit NCG010000 Construction Stormwater requirements? Yes
Describe:
7, Has sedimentation damage occurred since last inspection? No If Yes,where? (check all that apply)
Degree of damage:
8. Contact made with(name): No one on site Title:
Inspection report: Sent Report Date given/sent: June 24,2022
9. Corrective action needed:
10. Comments: This project only consists of the mountain bike trails throughout this project.
Overall the site has sufficient permanent ground cover to restrain erosion,however there are
some bare areas and rills that need to be repaired and stabilized,No additional self-monitoring
or self-inspections are required.Project is in compliance and released under the SPCA.
Termination of coverage under the NPDES General Stormwater Permit for Construction
Activities(NCGOI)must be requested by the permittee via a Notice of Termination(NOT).
The NOT is available at:https://edocs.deq.nc.gov/Forms/NCGOI-Termination.Please note
that this correspondence must be uploaded as part of completing the NOT process.
All project that have been approved prior to April 01,2019,under the old permit system,are
not required to take any additional actions.The stormwater permit is terminated at the same
time as the termination of this erosion control permit.
Reported by: Jesse McDonnell Others present:
Date of Inspection: June 22,2022 Time arriving on site: 9:30 AM Time leaving site: 9:50 AM
ec: