HomeMy WebLinkAbout[External] RE: SAW-2021-01566 Troutman Widewaters - Iredell County - Request for Additional InformationBaker, Caroline D
From: Tinklenberg, Chris <Chris.Tinklenberg@kimley-horn.com>
Sent: Friday, December 29, 2023 9:43 AM
To: Stock, N Carmela CIV USARMY CESAS (USA)
Cc: Wooten, Samantha; Kiker, Taylor
Subject: [External] RE: SAW-2021-01566 Troutman Widewaters - Iredell County - Request for
Additional Information
Follow Up Flag: Flag for follow up
Flag Status: Flagged
CAUTION: External email. Do not click links or open attachments unless verified. Report suspicious emails with the Report Message
button located on your Outlook menu bar on the Home tab.
Good morning, Carmela,
I hope you had a very Merry Christmas. I think there may be some confusion here. This is a request for a permit
modification, not a brand-new permit. The modification is requesting a reduction in currently authorized permanent
impacts. We can provide the requested information, but it was all submitted with the original application, i.e. agency
consultations and permit plans, so you should have it in the file. My biggest concern is your comment #7. We have
already demonstrated avoidance and minimization which was acceptable to the Corps as demonstrated by the current
authorization. This modification request is to further reduce stream impacts, not create additional rationale for a project
that has already been authorized.
We have submitted a similar 401 modification request to NCDWR.
I hope this clears things up but let me know if you have any other questions. If you don't already have the information
you requested on file, we can provide it, but I'd like to be clear that we'd like to focus solely on the reduced stream
impact and not reevaluate the project as a whole.
Thank you,
Chris
Chris Tinklenberg, PWS
Kimley-Horn 1 580 Kingsley Park Dr. Suite 125, Fort Mill, SC 29715
Direct: 803 881 3919 1 Mobile: 910 538 9836
From: Stock, N Carmela CIV USARMY CESAS (USA) <Nichelle.C.Stock@usace.army.mil>
Sent: Wednesday, December 27, 2023 1:00 PM
To: Tinklenberg, Chris <Chris.Tinklenberg@kimley-horn.com>
Cc: samantha.wooten@deq.nc.gov
Subject: SAW-2021-01566 Troutman Widewaters - Iredell County - Request for Additional Information
You don't often get email from nichelle.c.stock@usace.army.mil. Learn why this is important
Good afternoon, Chris,
This email is in reference to the Pre -construction notification (PCN) for the proposed Troutman Widewaters
Project (SAW-2021-01566), received on November 16, 2023.
The following information is required to complete our evaluation, confirm compliance with one or more General
or Regional Conditions, and/or complete consultation with another federal/state agency to verify the use of the
Nationwide Permit (NWP), please:
1. Provide SHPO concurrence letter referenced in the PCN.
2. Provide USFWS concurrence referenced in the PCN.
3. Verify the width of the stream and culvert size where the stream impacts are proposed.
4. Provide a cross -sectional drawing of proposed stream impacts.
5. Provide detailed construction plans calling out all proposed impacts, type of impact, and amount of
impact at each impact location.
6. The provided plans indicate a 26LF 15in RCP crossing north of, and parallel with, proposed stream
impacts 1 and 2. Please provide details on the purpose of the RCP. Would the RCP serve as an
additional culvert? Would there be any additional impacts to Waters of The US (WOTUS) as a result of
the proposed RCP?
7. Provide rationale for minimization and/or avoidance of W2 impacts. Applicants in similar situations have
implemented retaining walls to minimize impacts to WOTUS as a result of grading. Have further
minimization measures been considered?
8. Provide a bank credit approval letter for proposed mitigation.
Additionally, have you been in contact with NCDWR regarding an updated Individual Water Quality
Certification reflecting the proposed impact changes?
Please provide the requested information within 30 days, or your application will be administratively withdrawn.
To clarify, if the requested information is submitted after the 30-day timeframe, you will not be required to re-
submit an entirely new PCN (unless otherwise specified). We will continue to review and/or process your
permit application upon receipt of the requested information.
Please contact me with any questions or concerns.
Best Regards,
N. Carmela Stock
Biologist
Regulatory Project Manager
U.S. Army Corps of Engineers
SAD Technical Regional Execution Center
100 W. Oglethorpe Ave.
Savannah, GA 31401
Email: Nichelle.C.Stock(aï¿œusace.army.mil
Telephone: (912) 724-8979
To assist us in improving our service to you, please complete the survey found at
https://regulatory.ops.usace.army.mil/customer-service-survey/