December4, 2023
John Hennessy, Supervisor
NC]EQ / Division of Water Resources
NPDES Permitting — Compliance & Expedited Permitting Branch
1617 Mail Service Center
Raleigh, NC 27699-1617
Re: EMC SOC WQ S22-003
SOC Milestone Updates
Per the Special Order by Consent the milestone titled "Appy for permits for APRA Sewer Rehabilitation
Project" due date is November 30, 2023. As a sewer rehabilitation project this project requires limited
permitting. The majority of the project will be `Permitted by Regulation' as rehabilitation or replacement of
sewers within the same ROW or easement. The portion to be completed by dig and replace is proposed to be
less than 2,000 LF and therefore erosion control permit is not anticipated. A few segments of the sewer are
below minimum grade and are proposed to be rehabilitated with CIPP or pipe burst with HDPE and therefore
require a Variance. Note that a rehabilitation project some conditions are unknown and additional
documentation may be required during construction. The Variance request was submitted on November 30,
2023, and therefore meets the SOC required due date.
The due date for `Award Construction Contracts for Main Interceptor Replacement Project' is December 30,
2023. This project is planned to proceed with the Wastewater Treatment Plant Expansion Project has been
delayed due to funding delays. The funds provided by the State Budget are expected to be available soon and
the Town is currently coordinating with NCDEQ DWI to complete the steps required proceed to bid this work.
There are also outstanding easements required for relocation of the Iine outside the 100-year floodway and
floodplain where feasible. In order to allow time for final DWI review and approval and easement acquisition
we request a 90-day extension to March 29, 2024.
The due date to acquire and maintain temporary sludge handling equipment at the WTP and at the WWTP are
December 1, 2023. The Town has updated contracts with Synagro to provide sludge handling at both facilities
during the winter months of December 2023 to March 2024.
If any further information is required for this report, please don't hesitate to contact me.
Sincerely,
Chris McCorquodale
Town of Siler
22 ty
Chris McCorquodale
Director of Public Utilities
PO Box 769 • 311 N. Second Avenue
Siler City, NC 27344-0769
cmccorquodale@silercity.org
Phone: 919-742-4732 • Fax: 919-663-3874
www.silerc".org
To advorrce a framr7ework for oeir success through halaoced governooce, dynamic partnerships, acid an en tg qed comnu pity.