HomeMy WebLinkAboutSW3221202_Email_20230926
Peck, Kaitlin
From:svc_post_construction_stormwater
Sent:Tuesday, September 26, 2023 4:21 PM
To:Steven Prophet; mkirchner@eagleonline.net; kayle.schmidt@eagleonline.net; 'Lauren
Thomas'; 'Jeremy Roberts'; 'Phillip Hines'; 'Haley Daniel'; 'Mitch Eudy'
Cc:Mike McGee; 'Ryan McGee'; Peck, Kaitlin
Subject:RE: SW3221202 Piper Meadows
All,
I was looking over the addi?onal informa?on you provided on June 29, 2023 & July 28, 2023. Everything looks good
except for a few small issues:
Please correct the following:
- Supplement-EZ Form, Wet Pond Page:
o Line 2 – The provided value for Wet Pond #1 (12,336 cf) does not correspond to the value provided in
the calcula?ons (12,236 cf). The provided value for Wet Pond #2 (24,478 cf) does not correspond to the
value provided in the calcula?ons (26,578 cf). Please revise as needed.
o Line 25 – The provided value for Wet Pond #1 (622.0 ?) does not correspond to the value shown on the
plans (624.75 ?). The provided value for Wet Pond #2 (621.75 ?) does not correspond to the value
shown on the plans (6,22.0 ?). Please revise as needed. NOTE: The temporary pool eleva?on is
determined by the invert of the lowest bypass device.
o Line 32 – The provided value for Wet Pond #1 (3,663 cf) does not correspond to the value provided in
the calcula?ons (3,633 cf). The provided value for Wet Pond #2 (3,306 cf) does not correspond to the
value provided in the calcula?ons (7,688 cf). Please revise as needed.
Please provide the following:
- 1x hard copy & 1x electronic copy of the revised page of the Supplement-EZ Form.
- 1x hard copy (2x hard copies for plan sheets) & 1x electronic copy of any other items needed to address these
comments.
Hard copies should be mailed to me at the following address:
For FedEx/UPS:
Jim Farkas
512 N. Salisbury Street, Office 640M
Raleigh, NC 27604
For USPS:
Jim Farkas
1612 Mail Service Center
Raleigh, NC 27699-1612
Hand Delivery:
Please reach out to me prior to hand delivering a submission to make sure that I (or someone else in my group)
will be able to receive the submission. Do not leave the package in the foyer with the security guard.
NOTE: Hard copies should not be sent to a Regional Office. Doing so will delay the review process and the
submission package may be lost while being sent from the Regional Office to me in the Central Office.
1
Electronic copies should be uploaded at the following loca?on:
h?ps://edocs.deq.nc.gov/Forms/SW-Supplemental-Upload
Since these are really minor things, once I get the hard copies, anything else that may have changed from addressing
these issues, and the documents are uploaded to Laserfiche (Provided everything is s?ll in order), we can issue the
permit without doing another formal review. The quickness of the next review for this project is dependent on reviewer
availability.
Let me know if you have any ques?ons.
Thanks,
Jim Farkas
Post-Construc?on Stormwater Permi?ng Group
North Carolina Department of Environmental Quality
postconstruc?on@deq.nc.gov
From: Farkas, Jim J
Sent: Thursday, June 15, 2023 4:08 PM
To: Mike McGee <mike@mcgeebrick.com>; mkirchner@eagleonline.net; kayle.schmidt@eagleonline.net; 'Lauren
Thomas' <lauren.thomas@eagleonline.net>; 'Jeremy Roberts' <jroberts@eagleonline.net>; 'Phillip Hines'
<phillip.hines@eagleonline.net>; 'Haley Daniel' <haley.hardin@eagleonline.net>; 'Ryan McGee'
<Ryan@mcgeebrick.com>; 'Mitch Eudy' <mitcheudy@icloud.com>
Cc: Eplin, Jerry W <jerry.eplin@deq.nc.gov>
Subject: RE: SW3221202 Piper Meadows
Good Afternoon,
The Division of Energy, Mineral and Land Resources (DEMLR), received additional information for a Stormwater
Management Permit Application for the subject project on March 17, 2023. A review of that information has determined
that the application is not complete. Attached is a letter describing the items that need to be submitted. If you have any
questions, please feel free to contact me. My contact information is listed below.
Thank you,
Jim Farkas
State Stormwater Engineer
North Carolina Department of Environmental Quality
Office: (919) 707-3646
Jim.farkas@deq.nc.gov
2
From: Farkas, Jim J
Sent: Thursday, March 2, 2023 4:36 PM
To: Mike McGee <mike@mcgeebrick.com>; mkirchner@eagleonline.net; kayle.schmidt@eagleonline.net; 'Lauren
Thomas' <lauren.thomas@eagleonline.net>; 'Jeremy Roberts' <jroberts@eagleonline.net>; 'Phillip Hines'
<phillip.hines@eagleonline.net>; 'Haley Daniel' <haley.hardin@eagleonline.net>; 'Ryan McGee'
<Ryan@mcgeebrick.com>; 'Mitch Eudy' <mitcheudy@icloud.com>
Cc: Eplin, Jerry W <jerry.eplin@ncdenr.gov>
Subject: RE: SW3221202 Piper Meadows
Good Afternoon,
The Division of Energy, Mineral and Land Resources (DEMLR), received additional information for a Stormwater
th
Management Permit Application for the subject project on December 6, 2022. A review of that information has
determined that the application is not complete. Attached is a letter describing the items that need to be submitted. If
you have any questions, please feel free to contact me. My contact information is listed below.
Thank you,
Jim Farkas
State Stormwater Engineer
North Carolina Department of Environmental Quality
Office: (919) 707-3646
Jim.farkas@ncdenr.gov
From: DeBerry, Margie <Margie.DeBerry@ncdenr.gov>
Sent: Tuesday, December 6, 2022 12:40 PM
To: Mike McGee <mike@mcgeebrick.com>; mkirchner@eagleonline.net; kayle.schmidt@eagleonline.net; 'Lauren
Thomas' <lauren.thomas@eagleonline.net>; 'Jeremy Roberts' <jroberts@eagleonline.net>; 'Phillip Hines'
<phillip.hines@eagleonline.net>; 'Haley Daniel' <haley.hardin@eagleonline.net>; 'Ryan McGee'
<Ryan@mcgeebrick.com>; 'Mitch Eudy' <mitcheudy@icloud.com>
3
Cc: Khan, Zahid <zahid.khan@ncdenr.gov>; Farkas, Jim J <Jim.Farkas@ncdenr.gov>
Subject: SW3221202 Piper Meadows
Good afternoon,
We received your post-construction stormwater permit application for the above mentioned project on 12/6/2022.
Reviews under the standard permitting process generally take 75 calendar days, but can take up to 90 calendar days per
statute (our other reviewer, Corey Anen, no longer works for the State, so this review may exceed 75 days). Please
upload all documents that you mailed into our office through the link provided below. Be sure to choose the Central
Office as the Primary Contact office.
https://edocs.deq.nc.gov/Forms/SW-Supplemental-Upload
IMPORTANT NOTE: Please ensure that each file is uploaded under its appropriate file type. Additional file types can be
entered into the electronic form by clicking on the “Add Another Post-Construction File Upload” link directly below the
“State Stormwater Information Uploads” section of the form. Please do not upload entire plan sets through this form,
but rather upload the relevant individual sheets under the appropriate file type. Selecting the correct file type ensures
that the files are properly named in the electronic repository and it helps expedite the review process.
Please type in permit #: SW3221202
If you have any questions, please contact Jim Farkas Jim.Farkas@ncdenr.gov 919-707-3646.
Thank you,
Margie DeBerry
Environmental Specialist, Division of Energy, Mineral, and Land Resources
North Carolina Department of Environmental Quality
Office: (919) 707-9209
margie.deberry@ncdenr.gov
4