HomeMy WebLinkAboutNCC233539_ESC Approval Submitted_20231130 (--.
MBE cOG7'>.14 Planning & Development Department
.._ 0 ,
William Jason Guess
i REOVLE TO MATCH I Erosion Control Officer
OUR MOUNTAINS
NORTH cArt004P.
LETTER OF APPROVAL WITH MODIFICATIONS
July 14, 2023 NOTICE — This is not a permit
Anderson Bear Creek, LLC &Nowell Beaar Creek, LLC
Mr. Dave Hudson
9101 Glenwood Avenue
Raleigh,NC 27617
RE: Project Name: PRESTIGE SUBARU
Acres Approved: 28.0 AC
Project#: ER02023-000013
County: BUNCOMBE
City: ASHEVILLE
Address: 107 S. BEAR CREEK ROAD
River Basin: FRENCH BROAD
Stream Classification: C
Submitted By: DAVE HUDSON
Plan Type: COMMERCIAL
Dear Sir/Madam,
This office has reviewed the subject erosion and sedimentation control plan. We find the
plan to be acceptable and hereby issue this Letter of Approval with Modifications. This
approval shall become null and void if you have not made progress on the site within six
months after the date of approval. A one-time six-month extension can be granted for
good cause shown upon receiving a written request from you before the expiration of the
approved plan. This letter of approval is being issued prior to the issuance of the
stormwater permit due to concurrent reviews, but any land disturbing activity
associated with this project shall not begin prior to issuance off all required permits
including the stormwater permit and the land disturbing permit.
As of April 1, 2019, all new construction activities are required to complete and submit an
electronic Notice of Intent(eNOl) form requesting a Certificate of Coverage (COC)under
the NCG010000 Construction General Permit. After the form is reviewed and found to be
complete, you will receive a link with payment instructions for the $100 annual permit
fee. After the fee is processed, you will receive the COC via email. As the Financially
46 Valley Street—Asheville, NC 28801
p. (828) 250.4830 f. (828) 250.6086 buncombecounty.org
Responsible Party shown on the FRO form submitted for this project, you MUST obtain
the COC prior to commencement of any land disturbing activity. The eNOI form may be
accessed at deq.nc.gov/NCG01. Please direct questions about the eNOI form to the
Stormwater Program staff in the Raleigh central office. If the owner/operator of this
project changes in the future, the new responsible party must obtain a new COC.
Title 15A NCAC 4B .0118(a) and the NCGO1 permit require that the following
documentation be kept on file at the job site:
1. The approved E&SC plan as well as any approved deviation.
2. The NCG01 permit and the COC, once it is received.
3. Records of inspections made during the previous 12 months.
Also, this letter gives the notice required by G.S. 113A-61.1(a) of our right of periodic
inspection to ensure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Act is performance-oriented, requiring
protection of existing natural resources and adjoining properties. If, following the
commencement of this project, it is determined that the erosion and sedimentation control
plan is inadequate to meet the requirements of the Sedimentation Pollution Control Act of
1973 (North Carolina General Statute 113A-51 through 66), this office may require
revisions to the plan and implementation of the revisions to ensure compliance with the
Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal
and State water quality laws, regulations, and rules. In addition, local city or county
ordinances or rules may also apply to this land-disturbing activity. This approval does not
supersede any other permit or approval.
Please note that this approval is based in part on the accuracy of the information provided
in the Financial Responsibility Form, which you provided. You are requested to file an
amended form if there is any change in the information included on the form. In addition,
it would be helpful if you notify this office of the proposed starting date for this project.
Please notify us if you plan to have a preconstruction conference.
Your cooperation is appreciated.
Sincerely,
• J a imiv. 0.0.46
W. Jason Guess
Erosion Control Officer
Enclosures: NPDES NCG01 Fact Sheet
Cc: BGE, Inc.
J�GoMBE cOG7'>.
Planning & Development Department
0.4
.._ 0 ,
William Jason Guess
PEOR MOUPLETONMTATCHAINSI Erosion Control Officer
OU
NORTH CARO0"P
MODIFICATIONS FOR APPROVAL
Project name: PRESTIGE SUBARU
Project No. ER02023-00013
Location: 107 S.BEAR CREEK ROAD
Date Approved: JULY 14, 2023
Person financially responsible: MR. DAVE HUDSON
1. Prior to issuance of land disturbing permit,encroachments agreements with NCDOT must
be provided to this office.
2. Per the Erosion Control Ordinance, please maintain a 10'undisturbed vegetative buffer
between stormwater discharge and the property line at the proposed discharge point for
construction runoff.
3. Contractor to ensure that any import or export material be from a permitted site.
4. Erosion control measures must be installed in accordance with the approved engineering
plans and maintained at all times. Alternate measures must first be approved with the
engineer of record and regulatory site inspector prior to installation.
5. Clearing limits for grading must be clearly delineated in the field as shown on the
approved engineering plans. Any additional clearing or land disturbing activity that
disturbs the ground surface outside of those limits will constitute a violation of the
County's Ordinance and will be subject to penalties.
6. Any deviations in the original approved construction plans or design changes to land
clearing to the overall site must first be submitted for review to this regulatory office and
approved prior to continuation of construction. Failure to resubmit could result in
possible issuance of stop work orders,holding of any building inspections, or issuance of
certificates of occupancy.
7. Erosion control measures must be in good working condition and in place at the
completion of construction each day and on holidays to prevent possible off-site
sedimentation associated with changing weather events.
8. Additional measure may be required if site dictates change due to construction activities.
9. NCG010000 Construction General Permit, Buncombe County Floodplain Development
Permits and Buncombe County Stormwater Management Permits must be obtained prior
to beginning construction and issuance of Buncombe County Land Disturbance Permit.
10. An on-site pre-construction meeting must be scheduled with this office prior to any land
disturbing activities including tree removal.
. R
46 Valley Street—Asheville, NC 28801
p. (828) 250.4830 f. (828) 250.6086 buncombecounty.org