HomeMy WebLinkAboutNC0024406_Bromide Reduction Evaluation_20231116 (' DUKE Belews Creek Steam Station
ENERGY Duke Energy Carolinas
3194 Pine Hall Road
Walnut Creek, NC 27609
Certified mail#7020 0640 0001 7228 5798
November 10, 2023 RECEIVED
Sergei Chernikov, PhD NOV 16 2023
NC Department of Environmental Quality
Division of Water Resources NCDEQ/DWR/NPDES
Complex NPDES Permitting Unit
1617 Mail Service Center
Raleigh, North Carolina 27699-1617
Subject: Duke Energy Carolinas, LLC
Belews Creek Steam Station -#NC0024406
Bromide Reduction Evaluation Semi —Annual Report
Dear Dr. Chernikov:
As required by Condition A. (14) of the subject NPDES permit attached are three copies of the
Semi-annual status report summarizing Duke Energy's efforts to reduce bromide discharge and
potential subsequent Total Trihalomethane (TTHM) formation in downstream municipal water
treatment systems.
Should you have questions regarding this report, please contact Lori Tollie at 336-408-2591 or
Lori.Tollie@duke-energy.com.
Yours truly,
Michael F. Lanning,
General Manager Ill, Regulated Stations
RRE CDG Belews Creek Steam Station
Attachment
cc: Lon Snider, WSRO, 450 West Hanes Mill Road, Winston-Salem, NC 27105
Lori Tollie
Brenda Johnson, Env Field Support
Belews Creek Steam Station
Bromide Reduction Evaluation NPDES Permit-NC0024406
Semi-Annual Progress Report
November 2023
Pursuant to Condition A. (20) Bromide Reduction Evaluation of the NPDES Permit— NC0024406.
Duke Energy submits this semi-annual progress report. This report is required to summarize on-
going investigations focused on minimizing bromide discharge at Outfall 003, 006, and 111 as
well as efforts aimed at reducing the formation of total trihalomethanes (TTHM) at downstream
water treatment plants. Outfall 003 and Outfall 111 are no longer in operation. Outfall 003 was
replaced by Outfall 006 to the Dan River. Outfall 111 was a toe drain that was rerouted to
comingle with other low volume wastewater, ultimately discharging via Outfall 006 to the Dan
River.
• Duke Energy has worked cooperatively with the North Carolina Division of Water
Resources (DWR), the Town of Madison and City of Eden to address the bromide/TTHM
issues since being advised of the municipality's issues with TTHM formation.
• Bromide itself is not a health concern in surface waters. There is no water quality
standard for bromide and no NPDES permit limit.
• Duke Energy has provided direct technical expertise and financial assistance to Madison
and Eden to help address their respective TTHM issues.
Town of Madison
• No updated information new to report.
City of Eden
• No updated information new to report.
Belews Creek Steam Station
• Duke Energy has partnered with UNC-C and Electric Power Research Institute (EPRI) to
perform a lysimeter pilot at Mayo Power Plant that is reviewing halide sequestration and
encapsulation strategy from a long-term perspective.
• Belews Creek's conversion to natural gas for Unit 1 was completed in 4th quarter of 2019.
Conversion of Unit 2 was complete in the 4th quarter of 2020. This modification to the
operation of the station is a result of other factors but is expected to have an added
benefit of decreasing the mass of bromide discharges.
Belews Creek Steam Station
Bromide Reduction Evaluation NPDES Permit-NC0024406
Semi-Annual Progress Report
November 2023
Pursuant to Condition A. (20) Bromide Reduction Evaluation of the NPDES Permit— NC0024406.
Duke Energy submits this semi-annual progress report. This report is required to summarize on-
going investigations focused on minimizing bromide discharge at Outfall 003, 006, and 111 as
well as efforts aimed at reducing the formation of total trihalomethanes (TTHM) at downstream
water treatment plants. Outfall 003 and Outfall 111 are no longer in operation. Outfall 003 was
replaced by Outfall 006 to the Dan River. Outfall 111 was a toe drain that was rerouted to
comingle with other low volume wastewater, ultimately discharging via Outfall 006 to the Dan
River.
• Duke Energy has worked cooperatively with the North Carolina Division of Water
Resources (DWR), the Town of Madison and City of Eden to address the bromide/TTHM
issues since being advised of the municipality's issues with TTHM formation.
• Bromide itself is not a health concern in surface waters. There is no water quality
standard for bromide and no NPDES permit limit.
• Duke Energy has provided direct technical expertise and financial assistance to Madison
and Eden to help address their respective TTHM issues.
Town of Madison
• No updated information new to report.
City of Eden
• No updated information new to report.
Belews Creek Steam Station
• Duke Energy has partnered with UNC-C and Electric Power Research Institute (EPRI) to
perform a lysimeter pilot at Mayo Power Plant that is reviewing halide sequestration and
encapsulation strategy from a long-term perspective.
• Belews Creek's conversion to natural gas for Unit 1 was completed in 4th quarter of 2019.
Conversion of Unit 2 was complete in the 4th quarter of 2020. This modification to the
operation of the station is a result of other factors but is expected to have an added
benefit of decreasing the mass of bromide discharges.
Belews Creek Steam Station
Bromide Reduction Evaluation NPDES Permit-NC0024406
Semi-Annual Progress Report
November 2023
Pursuant to Condition A. (20) Bromide Reduction Evaluation of the NPDES Permit — NC0024406.
Duke Energy submits this semi-annual progress report. This report is required to summarize on-
going investigations focused on minimizing bromide discharge at Outfall 003, 006, and 111 as
well as efforts aimed at reducing the formation of total trihalomethanes (TTHM) at downstream
water treatment plants. Outfall 003 and Outfall 111 are no longer in operation. Outfall 003 was
replaced by Outfall 006 to the Dan River. Outfall 111 was a toe drain that was rerouted to
comingle with other low volume wastewater, ultimately discharging via Outfall 006 to the Dan
River.
• Duke Energy has worked cooperatively with the North Carolina Division of Water
Resources (DWR), the Town of Madison and City of Eden to address the bromide/TTHM
issues since being advised of the municipality's issues with TTHM formation.
• Bromide itself is not a health concern in surface waters. There is no water quality
standard for bromide and no NPDES permit limit.
• Duke Energy has provided direct technical expertise and financial assistance to Madison
and Eden to help address their respective TTHM issues.
Town of Madison
• No updated information new to report.
City of Eden
• No updated information new to report.
Belews Creek Steam Station
• Duke Energy has partnered with UNC-C and Electric Power Research Institute (EPRI) to
perform a lysimeter pilot at Mayo Power Plant that is reviewing halide sequestration and
encapsulation strategy from a long-term perspective.
• Belews Creek's conversion to natural gas for Unit 1 was completed in 4th quarter of 2019.
Conversion of Unit 2 was complete in the 4th quarter of 2020. This modification to the
operation of the station is a result of other factors but is expected to have an added
benefit of decreasing the mass of bromide discharges.