Loading...
HomeMy WebLinkAboutNC0086550_Authorization to Construct_20000407.r State of North Carolina Department of Environment and Natural Resources Division of Water Quality James B. Hunt, Jr., Governor Bill Holman, Secretary Kerr T. Stevens, Director April 7, 2000 Mr. Jeffrey Lewis Town of Fairmont P.O. Box 248 Fairmont, North Carolina 28340 erfill NCDENR Subject: Authorization to Construct ATC No. 086550ACA NPDES Permit No. NCO086550 Fairmont Regional WWTP Robeson County Dear Mr. Lewis: The Division of Water Quality's NPDES Unit has reviewed the Town of Fairmont's request for an Authorization to Construct a new regional wastewater treatment facility near Boardman. the new Fairmont Regional WWTP. The Division finds the proposed design to be satisfactory and hereby grants authorization for construction of a 1.75 MGD activated sludge treatment facility including the following: • Headworks: • Two 1.0 MGD bar screens, one manually cleaned, one mechanically cleaned • Aerated grit chamber • Activated sludge system: • Two 724,000 gallon rectangular aeration basins, • Two 75 ft. diameter clarifiers (octagonal), • Coarse -bubble diffused aeration system with three 3200 scfm centrifugal blowers, • Blowerbuilding, • Disinfection system: • Gaseous chlorination and two 170,600 gallon chlorine contact chambers • Gaseous sulfur dioxide dechlorination and 35,900 gallon contact chamber Chlorine and sulfur dioxide feed building, • One cascade aerator, • Solids handling facilities: • One 30 ft. diameter gravity thickener • Two aerated digesters, 376,000 gallons total volume • One 444,400 gallon sludge holding tank • One sludge loading station • Laboratory and control building, and • All associated structures, pumps, motors, valves, piping, wiring, controls, and other appurtenances as described in the subject plans and specifications. 1617 Mail Service Center, Raleigh, North Carolina 27699-1617 Telephone (919) 733-5083 FAX (919) 733-0719 An Equal Opportunity Affirmative Action Employer Internet: http://h2o.enr.state,nc.us/ •.r Fairmont Regional WWTP ATC No. 086550ACA z Page 2 This Authorization to Construct is issued in accordance with NPDES Permit No. NC0086550, issued June 9, 1999. The Division issued Wastewater Collection Permit No. WQ0015382 in January 1999, authorizing construction of related facilities: • Pump Station No. 1 and force main to pump the Town's wastewaters from the current treatment plant site to the new treatment facilities and • Pump Station No. 2 and force main to discharge treated wastewater to the Lumber River. Upon submittal of Engineer's Certification(s) of completion for the entire project (see below), the Town shall be authorized to discharge up to 1.75 MGD of treated wastewater to the Lumber River in accordance with the conditions and limitations specified in its NPDES permit. The Division understands that, upon start-up of the regional facility, the Town's NPDES permit for the existing Fairmont WWTP (N00021059) will no longer be needed and can be rescinded. The key issue with the proposed design is that the 1.75 MGD average design flow is considerably higher than the sum of current flows, around 0.5 MGD, that will be pumped to the new plant. Because the plant is designed with only two treatment trains, operators could face a significant challenge in meeting permit limits across the full range of flows. The design addresses this issue to a certain degree: it provides for operating just one of the two treatment trains at the lower flows and using an operating mode better suited to those conditions. In addition, the prospects for connecting other wastewater sources to the plant seem to be improving, and the added connections could shorten the time that the plant has to operate under low flow conditions. Still, the approach is less than optimal. The Town should consider whether a design change, such as converting to a three- or four -train configuration, is appropriate at this time in order to enhance the plant's ability to reliably meet permit limits over the wide range of expected flows. Fairmont is understandably interested in attracting industry in order to boost the area's economy, and the regional plant design includes some capacity for industrial wastewater flows. The Town should be aware, however, that the new plant is specifically designed to treat domestic wastewater. Many industrial wastewaters are not suitable for treatment in this type of facility. Without special pretreatment, they can exert toxic effects in the plant, upsetting the biological treatment processes and causing violations of the NPDES permit limit for toxicity. Before committing to accept any significant industrial flows, the Town must be convinced and demonstrate to the Division that the new wastewater is compatible with its treatment plant. The Town must also develop and implement a local pretreatment program, approved by the Division, to control the industrial source(s) discharging to its treatment plant. Engineer's Certification Upon completing construction of all components of the regional project approved under this ATC and the Wastewater Collection Permit No. WQ0015382 and prior to operation of the new facilities, the Permittee shall provide the Division with a certification from a professional engineer certifying that the permitted facilities have been installed in accordance with the NPDES Permit, the Authorizations to Construct, and the approved plans and specifications. The Certification should be mailed to: NCDENR/ DWQ/ NPDES Unit 1617 Mail Service Center Raleigh, North Carolina 27699-1617 Additional Conditions In the event that the facilities fail to perform satisfactorily, including the creation of nuisance conditions, the Permittee shall take immediate corrective action, including those as may be required by this Division, such as the construction of additional or replacement wastewater treatment or disposal facilities. •_o Fairmont Regional WWTP ATC No. 086550ACA Page 3 The Permittee shall notify the Fayetteville Regional Office, telephone number (910) 486-1541, at least forty-eight (48) hours in advance of operation of the installed facilities, so that an in -place inspection can be made. Such notification to the regional supervisor shall be made during the normal office hours of 8:00 a.m. until 5:00 p.m. on Monday through Friday, excluding State Holidays. The Permittee shall employ a certified wastewater treatment plant operator to be in responsible charge (ORC) of the wastewater treatment facilities. The operator must hold a certificate of the type and grade at least equivalent to or greater than the classification assigned to the wastewater treatment facilities by the Certification Commission. The Permittee must also employ a certified back-up operator of the appropriate type and grade to comply with the conditions of Title 15A, Chapter 8G, .0200. The ORC of the facility must visit each Class I facility at least weekly and each Class II, III, and IV facility at least daily, excluding weekends and holidays; and must properly manage and document daily operation and maintenance of the facility and comply with all other conditions of Title 15A, Chapter 8G, .0200. The Operational Agreement between the Permittee and the Environmental Management Commission is incorporated herein by reference and is a condition of this Permit. Noncompliance with the terms of the Operational Agreement shall subject the Permittee to all sanctions provided by G. S. 143-215.6 for violation of or failure to act in accordance with the terms and conditions of this Permit. Failure to abide by the requirements contained in this Authorization to Construct may subject the Permittee to an enforcement action by the Division of Water Quality in accordance with North Carolina General Statute 143-215.6A to 143-215.6C. The issuance of this Authorization to Construct does not preclude the Permittee from complying with any and all statutes, rules, regulations, or ordinances which may be imposed by other government agencies (local, state, and federal) which have jurisdiction. The Permittee shall maintain a copy of the approved plans and specifications on file for the life of the facility. One (1) copy of the approved plans and specifications is enclosed for your records. If you have any questions about this Authorization to Construct, please contact Mike Templeton, at (919) 733-5083, extension 541. Sincerely, Y71,6`rr T. Stevens Director Enclosures: Project Plans and Specifications Engineer's Certification Form cc: Mr. William R. Lester, Hobbs, Upchurch & Associates (w/ certification form) Fayetteville Regional Office, Water Quality Technical Assistance and Certification Unit Central Files NPDES Unit Files ATC SUMMARY Town of Fairmont - Regional WWTP ATC No. 086550ACA Lumber River, Class C-Sw Lumber River Basin, 030751 Robeson County SCOPE The Town of Fairmont proposes to construct a 1.75 MGD regional wastewater treatment facility near Boardman. The Town will abandon its existing treatment plant (NC0021059), convert it to a central lift station, and pump its wastewater to the new plant. Treated effluent from the new plant will be pumped to the Lumber River. The project involves approximately 11 miles of force main in all. The influent and effluent pump stations and the influent and effluent force mains were permitted under permit number WQ0015832, issued January 11, 1999. The scope of the current review is limited to the new treatment facilities. The ATC was originally received July 27, 1998, and returned until the NPDES permit for the facility was issued on June 9, 1999. RECOMMENDATIONS 1. Approve the revised ATC request as submitted, in consideration of additional information provided by the design engineer. 2. Add comments to the approval letter linking it with the pump station/ force main project and addressing design capacity and industrial connection issues. REVIEW SUMMARY General The key issue in the design review is that the 1.75 MGD average design flow is considerably higher than current flows, which are around 0.5 MGD on a monthly average. Because the plant is designed with only two treatment trains, operators could face a significant challenge to meet permit limits across the full range of expected flows. The,flow projection for Fairmont was over -estimated in past planning efforts; DWQ issued speculative limits for 2.0 MGD in 1995. The flow was reduced to 1.75 MGD, and the Town received a FONSI for the new plant at that flow. Later reviews revealed that even the reduced flow was more than needed for the Town. Fairmont's plant is now being promoted as a regional treatment facility, with our support and consistent with more recent wastewater planning efforts in Robeson County and surrounding areas. The Town is having some success recruiting other communities to connect to the regional plant, and it now appears more likely that committed flows will approach a more comfortable 0.7-0.8 MGD by start- up. Design Issues The main issues with the plant design are: 1. The facility design appears reasonable for a plant treating 1.75 MGD of domestic wastewater. Current flows from committed contributors are approximately 0.5 MGD, and the design calculations look at both Year 1 and Average Design Flow conditions. 2. Having only two treatment trains limits the operators' options for running the plant at low initial flows. Even with only one train in operation and in extended aeration mode, the plant will be lightly loaded. The main challenge in the new plant may be in managing the biological solids: maintaining a healthy sludge in the system and keeping enough solids in the aeration basin to achieve adequate treatment. UNRESOLVED ISSUES It remains to be seen whether the Town can collect enough treatable wastewater to feed the plant at a reasonable level. As domestic -type flows approach and exceed 0.7 - 0.8 MGD, the operation of the plant should become relatively routine. The Town is recruiting industries, marketing the available capacity of the new plant. The initial design assumes that all of the wastewater to the plant is domestic in nature. DWQ should allow an industry to connect to the Town only after the industry has demonstrated that its wastewater is compatible with the treatment system. If the industry is a Significant Industrial User, the Town must develop and implement a local pretreatment program. - end - -2- ATC Review Notes Town of Fairmont - Regional WWTP ATC No. 086550ACA NPDES No. NCO086550 Lumber River, Class C-Sw Lumber River Basin, 030751 Robeson County A. PROJECT OVERVIEW The Town of Fairmont proposes to build a 1.75 MGD activated sludge wastewater treatment plant to treat wastewaters from Fairmont, Orrum, Proctorville, Boardman, and future municipal and/or industrial connections to be defined. The regional plant will be built to the south and west of the US Highway 74 crossing of the Lumber River near Boardman. The project is being funded by a $6-7M Farmer's Home Rural Development grant. Fairmont's existing treatment plant will be abandoned and converted to a central lift station. Wastewaters will be pumped to the new plant through approx. 11 miles of 12" 0 force main. Other pump stations will be added as needed for other planned and future connections. Treated effluent from the new plant will be pumped to the Lumber River through approx. mile of 12" 0 force main. The influent pump station and the influent and effluent force mains were already permitted under permit number WQ0015832, issued January 11, 1999. The scope of the current project includes the treatment facilities and the effluent pump station. A key issue in the design review is that the design flows are considerably higher than initial flows (1.75 vs. 0.5 MGD, monthly average values). The plant is designed with only two treatment trains, and the operators will face a significant challenge to meet permit limits through the full range of expected flows. The following is a compilation of design information for the new plant. B. PROCESS DESCRIPTION The proposed process consists of an activated sludge system (w/o primary clarification), chlorine disinfection w/ SO2 dechlorination, and cascade re -aeration. Waste sludge is thickened and aerobically digested, then held in a storage basin until trucked to a disposal site. During the first years of the plant's operation, when wastewater flows will be low, only one train of the activated sludge process will be operated, in extended aeration mode. As flows increase, operations will evolve to conventional mode using both treatment trains. The exact progression will be up to the judgment of the operators. The hydraulic capacity of the plant is adequate to allow nitrification, and this is included in the design. With addition of mixers at the influent end of the aeration basin(s), the plant could also provide denitrification, but the design does not address this possibility. C. DESIGN ASSUMPTIONS Year 1 Design Year NPDES Permit Monthly Hourly Monthly Hourly Effluent Average Maximum Average Maximum Limitations* WASTEWATER & EFFLUENT CHARACTERISTICS Flow (MGD) 0.5 1.25 1.75 4.375 1.75 BOD (mg/L) 200 200 200 200 15 TSS (mg/L) 200 200 200 200 30 TKN (mg/L) 50 50 50 50 — NH3-N (mg/L as N) -- -- — -- 4 Fecal Coliform (#/100rnQ -- -- -- -- 200 Residual Chlorine (ug/L) -- -- -- -- 28 Dissolved Oxygen (mg/L) -- -- -- -- 5 PROCESS ASSUMPTIONS MCRT (d) 20 -- 10 -- -- lb BOD/1,000 ft3 15 -- 15 -- -- RAS, WAS TSS (mg/L) 8,000 -- 8,000 -- -- Qr/Q ratio -- up to 200%** -- up to 57%** -- MLVSS:MLSS ratio 0.65 -- .65 -- -- PLANT SITE Temp (degC) 27 27 27 27 Site elevation (ft) 100 100 100 100 -- Monthly average values, except residual chlorine (daily maximum) *' 1.0 MGD pumping capacity D. HEADWORKS Bar Screen one manually cleaned unit, one mechanically cleaned, both rated at 1.0 MGD (2.5 MGD peak), w/ SS grates and 1/2" openings Grit Chamber =* aerated grit chamber w/ rolling aeration action -2- E. ACTIVATED SLUDGE Aeration Basins =* 2 rectangular basins @ 362,000 gal each = 724,000 gal total Coarse air diffusers w/ dome deflectors => 3 - 3,200 scfm blowers for entire plant; wide use of airlift pumps; 6,400 scfm reserved for aeration Given Calculated Typical Values Year 1 Design Year 1 Design (M&E, 3rd)' Results MLSS, mg/L 2,300 4,020 2,800 2,800 1,500-5,000 / See comment 1,200-3,000 below Hydraulic Retention Time (hrs) 21 *' 12* 17 9 4-8 / 18-36 ' Organic Loading F/M (IbBOD /lb MLVSS-d) 0.08 0.08 0.15*** 0.27*** 0.05-0.15 / 0.2-0.4 ° lb BOD/ 1,000 U 15 15 17.2 30.2 10-25 / 20-40 ° Sludge Wastage (gpd @ 4,620**** 8,140**** 9,380 32,800 8,000 mg/L TSS) MCRT (days) 20 10 11.3 6.4 20-30 / 5-15 ° AOTR 1,100 7,740 SOTR 1,690 11,840 Aeration HP req'd 21 145 Aeration Rate (scfm/1,000 ft3) -- -- -- 29.4 OK * Given as extended air/ conventional values; Table 10-5. *' Basin volume includes rapid mix and influent channel volumes *** Assuming 2,800 mg/L MLSS,1,820 mg/L MLVSS **** Calculation error as submitted The aeration basins were originally sized (8/18/97 calcs in EAA) based on a 10-day MCRT and an MLSS of 2,800 mg/L. The current design (7/98 calcs) uses that same volume, assumes MCRTs of 20 and 10 days (initial and design flows), and back -calculates the MLSS. The plant is described as starting in extended air mode, due to low organic loading rates, and converting to conventional activated sludge process as loadings increase. Most design values for the design year still fall into the range that is considered the extended air mode. Clarifiers 2 center -feed, peripheral -draw octagonal clarifiers, vacuum withdrawal of sludge thru rake arms. Dimensions: Diameter: Area: Side -Water Depth: Volume: 75 ft (approx.) 4,880 ft2 15.25 ft 557,000 gal each -3- . /A, Given Calculated Typical Values Year 1 Design Year 1 Design Results Surface Loading (gpd/ft2) 113 <350 102 179 200-400 / 400-800 Low 990 @ peak 600-800 / OK 1,000-1,200 Solids Loading (lb/02) ® 0.35 & 1 MGD recycle 3.7 26 3.7 6.1 4.8 -24 Low end Recycle Rate (MGD) 0.35 1.0 0.27 0.78 N 70 200 53 45 50-150 / 25-100 OK! Additional capacity to recycle mixed liquor would enhance denitrification capability. F. DISINFECTION Chlorine gas in 1-ton cylinders. Sulfur dioxide in lb cylinders. Both are dual -tank systems w/ automatic switch -over and alarms. Chlorine Contact Chamber => Dimensions: two chambers, each approx. 20.6 x 42.6 x 13 avg. depth Volume: approx. 85,300 gal each, 170,600 total Given Calculated Year 1 Design Year 1 Design Typical Values Results Detention Time, avg. (min) 110 64 245 140 30 std. OK Dechlorination Chamber => Dimensions: one chamber, approx. 20.6 x 19.4 x 12 avg. depth Volume: approx. 35,870 gal Given Calculated Typical Values Year 1 Design Year 1 Design & Source Results Detention Time (min) -- -- 103 30 30-60 OK -4- G. SOLIDS HANDLING Waste activated sludge is pumped continuously to a 30' 0 gravity thickener. Design calls for 8,000 mg/L TSS in, 2.5% solids out to digesters. The two square digesters operate in series. Sludge will periodically be decanted in the second digester cell and drained by gravity to the adjoining sludge storage basin. Given Calculated Typical Values Year 1 Design Year 1 Design & Source Results Gravity Thickener Solids Loading (Ib/02) -- 2.9 -- 3.1 OK Digesters Nos.1 & 2 Volume (gal) -- 376,000 -- -- -- HRT (days) -- 41 -- 36 OK Solids Loading -- 26 8.1 33 (lb VSS/1,000 ft3) Aeration •• -- -- 29.4 OK (scfm/1,000 ft3) Sludge Storage Volume (gal) -- 444,400 -- 454,400 OK Detention -• 73' -- 69' OK At 4% solids H. OTHER Design includes back-up power source: 500 KW (670 HP) unit. Total load for all three blowers plus all three effluent pumps is 435 HP. Plans, specs, and initial design calculations are stamped by Will Buie, no longer with Hobbs Upchurch. No revisions were made to the plans and specs, so new P.E. stamp is not required. Did not look at D.O. levels predicted at the outfall I. COMMENTS Main issue with the design is the under -loading in first years of operation, until flows reach 0.7-0.8 MGD. Controlling the sludge age (MCRT) and managing the solids inventory in the activated sludge system will probably be especially challenging during this time. DESIGN REFERENCES 1) Metcalf and Eddy, Inc. Wastewater Engineering, Treatment, Disposal, Reuse (3ro Ed.). McGraw-Hill, Inc., New York, N.Y., 1991 2) Great Lakes -Upper Mississippi Rive Board of State Public Health and Environmenal Managers, Recommended Standards for Wastewater Facilities (Ten States Standards, Health Education Services, Albany, N.Y., 1990 Edition. -5- IOWA ANAI; CALCULATION SHEET ,Y.—mA��a F PROJECT � f'L*G-N'7 R -\O �ITP NCDENR O �f CARouNA DenkmmzmT 0r SUBJECT S �O J S O Pt ENVIRONMCNT AND MxnxvAL Fte ctmc $ BY , 1 r/\VI.... DATE 4' n4 CHKD BY SHEET I OF DATE .............. 1 - (i Al", Gl `) .. .'+ .._. ._. .__. .,.,.... i................i..............._,........... _............. ...._... ....... .. .......... _._._.._ ....._._ _...... ...._.... ....._... ................,. .. .... ......... ..,...... i i i 1 i i W -vim t i ! i i • � >/ 7V�.JJJlllt.�'vv�777IIIVVViii� ��`��������"� j: i E i __.......... ... ........:.............. _...... ....! _ ._.. -= _ - - - - - - - - _ -- ..... .......... I 1 --_(^_-..1..- 1M, ...- ......... ` ...-..._ _«__._._-.-..._..... ._._ . _..... .. -..._. . _ _.. __-_—_ —_ __ ___ _ - _ . - .... ...__..... ........ _.. .. ..., ... _ .__ _—......._ V1 ' 3 ....... ........ 3......._..._..._.__._._..._._..._.-...._.__........._.._..... _ F ... .._.__. ...._ ._.__ .......... .......... .......... ......... ......... .......... ......... _._._ — __.._. ........_ _--_._ •i i i I t' I f S� ! '� ! k L i j ` ! , i 'RBI i E i 1 1 i Q f i !1 1 k i i S 1 i i E i i Z] ! .__..............j...-.. 7�/ .._...... ___- _._ ...... _____ _.._.... _ ._.__ _ —._ —__ .... .__.. ..._.. _ .._ .. _..._.Y.3 _.. ...._._ - ...._ _.._.._ i .. - --------.------ -.-..-..-..- _. ¢i ! E ! e i ......_-_-•-_-_.__-.i-..._.._._....i.................`...._.........-.................:.............. .......... ....._. ......_. ._.._. _.._. ........ ........ .......... ._.._.. ........... _._.... (R._...._.. .......... .,........ .......................... .......... �} i j ' i ( k i ! ! i I ! 1 ♦ ! 1 E i 1 ! k v I i i E s.)r} ! 1 ! i ! ! ! i j i I _..__._..{_.._...._.:...._.__._.j-.._.._.._. ....................... .....f.._.......__..,____}— __.._.. ° ._.... ._._ __._.-- ......... — i e f , i �•i•.t-/ L �! i i .....E i k j f k i i i i j I 1 E j i t ! i i V i 1 �s s j k k : j ^i i k i 1 i 3 i : , I ! ! 't j! j ..........._.. _. - ! k i � i _f I t j k j j i € € ! .-.............i_._.._........;.._._--__T-__-.......j..__-....._..�........_......• ......... ._. ................_..............'............_.j............. ..._._ ._......._t-............_._...............t......_..........':................i._.........._..j..............._i.............-.-:__.__..._.:•_.__._...«._.._...._...._........... .i....._...._.._j._. ----------- i I i : € j I j ! : ! ��•� � V i i j `•. i ! i 3 , i ' i s.� (S e0o j •RAJ_ • _..r.. ... .. , ! { ! ! ! i , a E o� .....__... - --1 _._._._...._...._..:.................:...-...........................:................. ;._.__.._._:..y.................:_........_...1..................._............:............-......... __._.........,.................._.. .............................. _. _. , .............. - ... ...._. ... ..... .... -, ... r . .... .. _ .._.._. .... _.. . _.__ _- t ......... , .,..........j........... . j- . _ .....,.. .. f,.. ..., i... .... - ... ... _ ... .. ......... ...... CALCULATION SHEET SHEET Z OF PROJECT SUBJECTD NoRTm CARoumA DePARTmocror bPb50 EWRONMZMT AND NxrupAL RL-.oumzs BY LhM' DATE CHKD BY DATE . .............. . .................. .......... - - - - - - - - - - . .. ..... .. . ............ ? ....... z . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . lit .......... . �kl I s �Z_ N 4 QWA CALCULATION SHEET Amfe ----%Moona SHEET —3 OF j NCDENR PROJECT s_ NORTH SUBJECT 0 8) 6 EWRONMEXT AND NAmj%AL RE50uRczs BY 9rDATE CHKD BY DATE 0 ....... ................. ........ . .... ------------- .. . .......... ....... ...... .. ........... . �a L I a a CALCULATION SHEET SHEET OF PROJECT NGDE NR SUBJECT at�4,-o NoRTH mum DePARTmzmT or &MRONMEM AND NmuRAL Resomces BY P'-O' DATE CHKD BY DATE . . . . . .... . . . . . . . . . . . . . . . c..... i_.___ ,_ . ........... ................. Ql: \14 ............ .............. ..... ... I.... Vtrt .. ........ ML ....... .... ............................................................. .. . ......... .......... . ........... . .......... .. .............. . .... ... . ...... .. ................ r Ir - - - - - - - - - - - - . . . . .... . . .. . ... ............. o"310 E041 % NCDENR NoRrM CARouu& DzFARTmE r oR Ewmommm r AND NxruRAL RESouRCES CALCULATION SHEET SHEET 5 OF PROJECT SUBJECT 06b55�0 hch BY M 0 DATE CHKD BY DATE f + ; r CALCULATION SHEET PROJECT (�-' � SHEET ` OF RCDENR SUBJECT 0&6SS-QATC& No►rrN CAROuNA DEPARTMENT oR EmVIRONNENT AND NmuRAL RESOURCES BY PL'T' DATE CHKD BY DATE IL J _ E , 5,I00 -goo + o,5►6(IS) Ito :So Ny *10 I, Z �, Use, — Rau-,Lkloc io,, wvdry IS r CALCULATION SHEET SHEET OF PROJECT NCDENR SUBJECT Q8lot55b NoRTm CARoum DePAmmew or EPMRONMEW AND Nxru ResouRGes BY 1AIV DATE CHKD BY DATE 3,4JE0 Jp 4 @ Z.s bo �P z, I 4t�o P� 4 3 qLT SIud �, Zv(o dt0. S OIL * \J ' = 37-6,oM 4 4w oAA Job Name: Town of Fairmont W WTP HUANo. FR9605 Date: I8-Aug-97 Description: Aeration Basin Sizing and Parameter Calculation Worksheet Formulas: Sludge Age (days) = Suspended Solids In Aeration Suspended Solids To Aeration MLSS (mg/1) = Desired Suspended Solids In Aeration Weight Of Water In Aeration MCRT (days) = Suspended Solids In Aeration SS In WAS +SS In Effluent Food To Microorganism Ratio = BOD To Aeration - MLVSS in Aeration ,r l Input Parameters: Calculated Parameters: Wastewater Flow & Influent Conditions: Calculated Parameter: Peak Wet Weather Flow(mgd)= 4.375 ADF BOD5 Deslmyed(Ibday)=> 2,700 Design Year Flow, ADF (mgd) = 1.750 ADF Ammonia -Nitrogen Destroyed (Ibday)=> 671 Stan-Up'Anticipated Flow(mgd)- 0.500 Yr.l B0D5Destmyed(Ib/day)=> 771 Design Sludge Return Rate (mgd) = 1.000 Yr.l Ammonia -Nitrogen Destroyed (IWday) => 192 Influent BOD5 (mg/1) = 200 Influent TSS(mg/1)= 200 Oxygen Rain Influent TKN(mgtl)= 50 ADF Actual sfer Rete,AOTR(Ibtday)=> �. 7,138 Effluent BODS Required(mg1I)= IS ADF Standaansfer Rate, SOTR(IWday)-> /0" I0,926 E(Bueml TSS Required(mg/1)= 30 Yr.l Actualmfer Rare, AOTR(lb/day)=> 2,040 Emuent NHS-N(mg/1)= 4 Yc1 Standaransfer Rate, SOTR(lbtday)� 3,122 Max Temperature (deg C) = 27 Site Elevation= too HP Required Temperature Correction Them 1.024 HP At Av eDaily Flow=> 182 Satiation D.O. at Temp, Elev Cst (mg/I) = 7.99 HP At Y 1 Flow-> 52 Design Assumptions Reactor Basin Volume (Based on IbBOD/1000 euft) P/I)= Desig/WAS 2,800 Volume Required (gols) —> - 673,219 Yr.l I)= 2,800 Detention Time (hrs)=> 9.23 RASoncentation(mg1l)= 8,000 Transfer Alpha Value = 0.90 System Mass Requirements Transfer Beta Value = 0.95 System Man ZBOD x MCRT x Yield (lb) 20,251 Mean C/Residence Time (days) 10 Volume Required (gal) 967,199 Operatin Dissolved Oxygen, Cis(mg/1)= lb BO1000 cut R Aeration Vol - 2.00 30 Detention Time (hrs)=> 11.89 r-a o+o w..}I98 C.0-LA Sludge Yield (lb TSS/Ib BOD5 Destroyed) = 0.75 Selected Volume- Input Value (gals) r 87, 0 Volatile SS Fraction (h4,VSSMB.SS)- 0.65 -+J' a Selected Basin Evaluation 1/ Rate Coemclents � 000 T ADF Detention Tim (hrs)�> � I1.93 Its Oxygen/lb BOD5 Applied = 1.50 ta Yr.I Detention T' e(hrs)Y> 41.76 Its Oxygen/lb NH3-N Applied = 4.60 Mixing HPRcq red => 174 ADF Process Required 52 HP Coefficients ADFFood Mass(Ib BOD/Ib MASS)=> 0.20 Its 02B r= 2.50 YcIII F oMass(Ib BODAb MLSS)=> •O.00' BHP/1 Cu Ft= 1.5 ADF SI ge Wasting Rate (gpd)=> 23,888 Yr.IS ge Wasting Rate(gpd)=> 28,575 Hobbs, Upchurch & Associates, P.A. Consulting Engineers 290 S.W. Broad Street a Post Office Box 1737 • Southern Pines, NC 28388 March 30, 2000 Mr. Mike Templeton N.C. Department of Environment & Natural Resources Division of Water Quality 1617 Mail Service Center Raleigh, North Carolina 27699-1617 Re: Fairmont Wastewater Treatment Plant ATC No. 086550ACA HUA No. FR9605.G Dear Mr. Templeton: �® FAX: 919/733-0719 Total 34 pages including cover Attached is the design and performance calculations for the diffused air system for the Fairmont Regional Wastewater Treatment Plant. Should you have any questions, please do not hesitate to contact our office. Sincerely, HOBBS, UPCHURCH & ASSOCIATES, P.A. Bill Lester, Jr., P.E. Governmental Division Manager p L��1OdL� n Ili APR 3 - 2000 BENR - WATER QUALITY POINT S011RCE BRANCH Southern Pines, NC • Telephone 910-692-5616 • Fax 910.692-7342 • e-mail: huamain@pinehurst.net Myrtle Beach • Kill Devil Hills • Raleigh WATER POLLUTION CONTROL CORP. June 25, 1998 Tony Combs Combs & Associates, Inc. P.O. BOX 32185 Charlotte, NC 28232-2185 RE: Fairmont, NC WPCC Project # 9770-97S Dear Tony, Attached is a revised design for the above mentioned project. Please note that the design contains performance calculations for the following basins. These performance calculations are based on supplying SD 1000 single drop diffusers in quantities equal to the indicated number on the drawings. The basin and number of diffusers indicated on the drawings are as follows: Aeration Basins # 1 &2 Aerobic Digesters # 1 &2 Sludge Holding Basin Thickener Pre -Mix Basin Rapid Mix Basin Aerated Influent Channel 96 Diffusers per Basin, 192 Diffusers Total 40 Diffusers per Basin, 80 Diffusers Total 104 Diffusers 8 Diffusers 10 Diffusers 60 Diffusers There are also five (5). single droplegs with single diffusers. One (1) in Aerobic Digester #2, one (1) in Clarifier Loading Basin # 1, one (1) in the Grit Chamber and two (2) in Clarifier Loading Basin #2. WPCC intends to supply these diffuser assemblies as shown on the drawings. There are also several airlift pumps shown on the drawings. These are located in the following basins and are sized as shown on the drawings. Basin Number of Airlift Pumps Diameter of Airlift Pump Rapid Mix Basin Aerobic Digester # 1 Aerobic Digester #2 0 SANITAIR EO al 2 C: Clarifier Loading Basin #2 3 10 6 4 16 9333 N. 49th Street Brown Deer, WI 53223 phone: 414-365-2200 fax: 414-365-2210 Web Sites: http://www.sanitaire.com http://www.abjwastewater.com SANITAIRE\ABJ All dimensions for the basins are consistent with the dimensions on the drawings and the previous design that I sent you. The loadings for the aeration basins and the air rates for the other basins are the same as the previous design. The only parameters that have changed for the aeration basins is Alpha (a) and Beta (R). Since we are providing a coarse bubble system, these values need to be adjusted to reflect the change in diffuser selection. Also, only the AVE and PEAK conditions are included for the aeration basins. The AVE2 condition no longer applies to a coarse bubble application. There are detail drawings included of the single drop diffuser that WPCC proposed to supply for this project. The dropleg material is stainless steel and the deflector plate is PVC. If you have any questions, please give Jon Butt or me a call. Sincerely, WATER POLLUTION CONTROL CORP. Christopher J. Tippery Sales Technician C: Hobbs, Upchurch & Associates, Inc. 290 SW Broad Street Southern Pines, NC 28388 ATTN: Will Buie r . a SANRAIR EO WATER POLLUTION CONTROL CORP. GBANITAIRE0 SINGLE DROP DIFFUSER AERATION EQUIPMENT for Fairmont, NC Aeration Basins #1 &2 CONSULTING ENGINEER: Hobbs, Upchurch & Associates SANITAIRE #9770-97S June 25, 1998 cjt Osetupsftr3 9333 N. 49th Street Brown Deer. WI 53223 phone: 414-365-2200 fax: 414-365-2210 Web Sites: http://www.sanitaire.com http://www.abiwastewater.com <TAN`KAGE 2 TRAINS EACH CONSISTING OF: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . •:PASS PARALLEL ZONE SUBMERGENCE REACTOR VOLUME . :NO. REACTORS PROCESS (FEET) DIMENSIONS (FEET) (KCF/PASS): .............................................................................. 1 1 AEROBIC 15.50 80.00 L X 36.67 W X 16.50 D 48.40: ............................................................................. TOTAL VOLUME PER TRAIN 48.4004 AERATED VOLUME PER TRAIN 48.4004 DESIGN DATA -------- :COND. NO. BOD NH3-N OXYGEN ------------------• AIR WATER TEMP.: TRAINS (#/DAY) (#/DAY) (#/DAY) (SCFM) (DEG. C. ) :AVE 2 2921 511.087 6732.5 A @20 :PEAK 2 5842 1022.17 13464 A @20 DESIGN PARAMETERS ----------------- --------------------- ------------------------------------------------! ! COND. AOR/SOR ALPHA BETA THETA D.O. AMB. 02/ 02/ SRT ! ! (ppm) !---------------------------------------------------------------------! ( PS IA) BOD5 NH3 ( DAYS) ! !AVE @.90 @.95 @1.024 @2.0 14.6 1.5 4.6 ! !PEAK @.90 @.95 @1.024 @2.0 14.6 1.5 4.6 ! NOTES: @-PRECEDING A VALUE INDICATES AN ASSUMPTION BY SANITAIRE A -INDICATES ACTUAL (AOR) OXYGEN REQUIREMENT S-INDICATES STANDARD CONDITION (SOR) OXYGEN REQUIREMENT ROUND TANKS ARE EVALUATED AS SQUARE TANKS OF EQUAL SURFACE AREA IF THE AOR/SOR PARAMETER IS NOT GIVEN, THEN ITS VALUE WILL BE CALCULATED LATER IF SUITABLE ALPHA, BETA, D.O., THETA, PRESSURE AND TEMPERATURE DATA IS SUPPLIED. INDICATED PRESSURE IS EQUIVALENT TO SITE ELEVATION OF 60 FEET Pa e 2 of 5 PERFORMANCE SUMMARY EQUIPMENT: TYPE: SINGLE DROP DIFFUSER NUMBER OF ASSEMBLIES: 6 NUMBER DIFFUSERS/ASSEMBLY: 32 OXYGEN TRANSFER PERFORMANCE BASED ON: EACH HEADER AT CENTER OF 26.67 FEET WIDE AERATION BAND AND 15.50 FEET OF SUBMERGENCE. OXYGEN PERFORMANCE IS CORRELATED TO PLACEMENT GEOMETRY, DIFFUSER SUBMERGENCE, AND AIR RATE PER UNIT TANK VOLUME - (NOTE: SCFM/DIFFUSER DOES NOT DISPLAY SIGNIFICANT CORRELATION TO COARSE BUBBLE DEVICE PERFORMANCE USING THESE PARAMETERS) --------------------------------------------- CONDITION: AVE PEAK --------------------------------------------- TANKAGE: . NO. TANKS 2 2 VOLUME/TANK (KCF) : 48.4 48.4 TOTAL VOLUME (KCF) 96.8 96.8 OXYGEN TRANSFER: 02 (#/DAY) AOR 6732.5 13464 AOR/SOR : .67764 .67764 02 (#/DAY) STD. COND. 9935.1 19870 02 (#/DAY/KCF) STD.CND. 102.6 205.2 STD. COND. EFF. (o) 10.3 11.6 SAFETY FACTOR (o) 10 10 AIR RATES: TOTAL SCFM 3839.6 6780.1 SCFM/ASSEMBLY 639.9 1130.0 SCFM/KCF 39.6 70.0 SCFM/DIFFUSER 19.9 35.3 PSIG REQUIRED AT 6.9 7.2 TOP OF DROPLEG POWER ESTIMATES: : *TOTAL BHP REQUIRED 148.2 271.3 STD. COND.(#02/BHP/HR) 2.79 3.05 SITE (#02/BHP/HR) ---------------------------------------------- 1.89 2.06 NOTE: BHP QUOTED ASSUMES ADIABATIC COMPRESSION, 70% MECHANICAL EFFICIENCY AND 0.3 PSI AIR MAIN HEADLOSS. MORE ACCURATE VALUES FOR POWER WILL DEPEND ON ACTUAL BLOWER, MOTOR, AND PLANT PIPING DESIGN. Page 3 of 5 9 OXYGEN TRANSFER CORRECTION FACTOR: AOR/SOR ------------------------------------------ THE RATIO OF ACTUAL SITE OXYGEN TRANSFER TO STANDARD CONDITION OXYGEN TRANSFER, (AOR/SOR), IS DEPENDENT ON A NUMBER OF FACTORS: 20 STANDARD CONDITION TEMPERATURE (DEG.C) T : OPERATING WATER TEMPERATURE (DEG. C) BETA : FIELD/STD.COND. 02 SATURATION RATIO THETA : OPERATING WATER TEMPERATURE FACTOR D.O. : OPERATING OXYGEN CONCENTRATION (MG/L) P : STD. COND. AMBIENT C SURF : CLEARWATER SURFACE 02 SATURATION Sc PRESSURE (1 ATMOSPHERE) T AT OPERATING TEMPERATURE (MG/L) P : OPERATING AMBIENT 9.07 : CLEARWATER SURFACE 02 SATURATION SITE PRESSURE (PSIA) AT 20 DEG. C. (MG/L) * ALPHA : FIELD/STD.COND. C SAT : STD. COND. AERATED 02 SATURATION KLA RATIO 20 IN THE TANK (MG/L) T-20 * . (THETA) (ALPHA) [ (BETA) (C SAT ) (CSURF /9.07) (P /P ) - (D.O.) ] 20 T SITE SC :AOR/SOR= ----------------------------------------------------------------- (C SAT ) 20 --------------------------------------------------------------------------- WATER * . :COND. ALPHA BETA THETA DO P TEMP. C SAT C SURF AOR/SOR: ppm site :----------------------------------------------------------------------------: deg.0 20 T :AVE @.90 @.95 @1.024 @2.0 14.6 @20 10.245 9.070 0.6776 :PEAK @.90 @.95 @1.024 @2.0 14.6 @20 10.245 9.070 0.6776 NOTE: @-PRECEEDING A VALUE INDICATES AN ASSUMPTION STANDARD CONDITIONS FOR OXYGEN TRANSFER IMPLIES: CLEARWATER AT 20 DEG. C.,• ZERO DISSOLVED OXYGEN AND 1 ATMOSPHERE AMBIENT PRESSURE. Page 4 of 5 c ONE AERATION ASSEMBLY HEADLOSS CALCULATED FOR THE AVE CONDITION AIR RATE PER ASSEMBLY= 639.93 SCFM ASSUMED OPERATING TEMPERATURE= 100 DEG F. ASSUMED TOTAL PRESSURE AT TOP OF DROPLEG= 6.911 PSIG DIFFUSER CONNECTORS SPACED AT 1.125 FT CENTERS HEADER 1 IS APPROX. 34.9 FT LONG WITH 32 DIFFUSER CONNECTORS ------------------- NODE APP. EQU DIA. SCFM CFM VEL. VEL. HEADLOSS TOTAL STATIC * LENGTH PRESS. PRESS. PRESS. PRESS. (FT) (IN) (FPS) (PSI) (PSI) (PSIG) (PSIG) -------------------------------------------- 1 E 6.3 10 639.9 462.3 14.8 2.44E-03 3.14E-04 6.911 6.909 2 17.5 10 639.9 462.3 14.8 2.44E-03 8.72E-04 6.910 6.908 3 T 25.8 10 639.9 462.4 14.8 2.44E-03 1.29E-03 6.909 6.907 ***** HEADER 1 ***** 4 36.8 10 0.0 0.0 0.0 0.00E+00 4.58E-04 6.909 6.909 ---------------------------------------------------------------------------- (STATIC HEADER PRESSURE DIFFERENTIAL IN ASSEMBLY= 1.98E-03 PSI) (AVERAGE HEADER PRESSURE IN ASSEMBLY = 6.9076 PSIG) ---------------------------------------------------------------------------- A: NET AVERAGE HEADLOSS FROM TOP OF DROPLEG TO HEADER= 3.922E-03 PSI B: DIFFUSER HEADLOSS= 1.412E-01 PSI AT 19.998 SCFM/DIFF, ONE SD1000 DIFFUSER PER DROP C: 15.500 FEET OF SUBMERGENCE= 6.7115 PSIG ---------------------------------------------------------------------------- TOTAL PRESSURE REQ'D AT TOP OF DROP, (A+B+C)= 6.8566 PSIG (FRICTION HEADLOSS (A+B) = 1.451E-01 PSI) NOTE: * -LABELS FOR APPURTENANCES- ------------------------ R-REDUCER, T-BRANCH FLOW TEE, RT-LINE FLOW TEE, E-90 DEG. ELBOW B-WIDE OPEN BUTTERFLY VALVE, S-SWING PEDESTAL & KNEE JOINTS. Pacie 5 of 5 ri 9ANrrA1RBll WATER POLLUTION CONTROL CORP. riBANITAIRE'9 SINGLE DROP DIFFUSER AERATION EQUIPMENT for Fairmont, NC Aerobic Digester#1 CONSULTING ENGINEER: Hobbs, Upchurch & Associates SANITAIRE #9770-97S June 25,1998 cjt c:lsetupslfairl 9333 N. 49th Street Brown Deer, WI 53223 phone: 414-365-2200 fax: 414-365-2210 Web Sites: http://www.sanitaire.com http://www.abjwastewater.com ='I'ANKAGE 1 TRAINS EACH CONSISTING OF: .............................................................................. .:PASS PARALLEL ZONE SUBMERGENCE REACTOR VOLUME : :NO. REACTORS PROCESS (FEET) DIMENSIONS (FEET) (KCF/PASS): .............................................................................. 1 1 AEROBIC 15.50 42.25 L X 36.75 W X 16.50 D 25.62: ................. .................. .......................................... : TOTAL VOLUME PER TRAIN 25.6193 AERATED VOLUME PER TRAIN 25.6193 DESIGN DATA .-----------------------------------------------------------: :COND. NO. BOD NH3-N OXYGEN AIR WATER TEMP.: TRAINS (#/DAY) (#/DAY) (#/DAY) (SCFM) (DEG. C. ) :.25 FT 1 310.538 @20 :20 S/K 1 512.3 @„_ DESIGN PARAMETERS ----------------- --------------------------------------------------------------------- ! COND. AOR/SOR ALPHA BETA THETA D.O. AMB. 02/ 02/ SRT (ppm) (PSIA) BOD5 NH3 (DAYS) --------------------------------------------------------------------- l.2S/FT 14.6 !20 S/K 14.6 i NOTES: @-PRECEDING A VALUE INDICATES AN ASSUMPTION BY SANITAIRE A -INDICATES ACTUAL (AOR) OXYGEN REQUIREMENT S-INDICATES STANDARD CONDITION (SOR) OXYGEN REQUIREMENT ROUND TANKS ARE EVALUATED AS SQUARE TANKS OF EQUAL SURFACE AREA IF THE AOR/SOR PARAMETER IS NOT GIVEN, THEN ITS VALUE WILL BE CALCULATED LATER IF SUITABLE ALPHA, BETA, D.O., THETA, PRESSURE AND TEMPERATURE DATA IS SUPPLIED. INDICATED PRESSURE IS EQUIVALENT TO SITE ELEVATION OF 60 FEET lPacre 2 of-4 PERFORMANCE SUMMARY EQUIPMENT: TYPE: SINGLE DROP DIFFUSER NUMBER OF ASSEMBLIES: 2 NUMBER DIFFUSERS/ASSEMBLY: 20 OXYGEN TRANSFER PERFORMANCE BASED ON: EACH HEADER AT CENTER OF 21.13 FEET WIDE AERATION BAND AND 15.50 FEET OF SUBMERGENCE. OXYGEN PERFORMANCE IS CORRELATED TO PLACEMENT GEOMETRY, DIFFUSER SUBMERGENCE, AND AIR RATE PER UNIT TANK VOLUME. (NOTE: SCFM/DIFFUSER DOES NOT DISPLAY SIGNIFICANT CORRELATION TO COARSE BUBBLE DEVICE PERFORMANCE USING THESE PARAMETERS) --------------------------------------------- CONDITION: . .2S/FT 20 S/K --------------------------------------------- TANKAGE: NO. TANKS 1 1 VOLUME/TANK (KCF) : 25.6 25.6 TOTAL VOLUME (KCF) 25.6 25.6 OXYGEN TRANSFER: 02 (#/DAY) AOR AOR/SOR 02 (#/DAY) STD. COND. 603.0 1056.6 02 (#/DAY/KCF) STD . CND . 23.5 41.2 STD. COND. EFF. (%) 7.75 8.23 SAFETY FACTOR ( %) 10 10 AIR RATES: TOTAL SCFM 310.5 512.3 SCFM/ASSEMBLY 155.2 256.1 SCFM/KCF 12.1 20 SCFM/DIFFUSER : 7.76 12.8 PSIG REQUIRED AT 6.9 7.1 TOP OF DROPLEG POWER ESTIMATES: *TOTAL BHP REQUIRED 11.9 20.2 STD. COND.(#02/BHP/HR) 2.09 2.17 SITE ( #02 /BHP/HR) --------------------------------------------- NOTE: BHP QUOTED ASSUMES ADIABATIC COMPRESSION, 70%; MECHANICAL EFFICIENCY AND 0.3 PSI AIR MAIN HEADLOSS. MORE ACCURATE VALUES FOR POWER WILL DEPEND ON ACTUAL BLOWER, MOTOR, AND PLANT PIPING DESIGN. Pa e 3 of 4 ONE AERATION ASSEMBLY HEADLOSS CALCULATED FOR THE .2S/FT CONDITION AIR RATE PER ASSEMBLY= 155.27 SCFM ASSUMED OPERATING TEMPERATURE= 100 DEG F. ASSUMED TOTAL PRESSURE AT TOP OF DROPLEG= 6.911 PSIG DIFFUSER CONNECTORS SPACED AT 1.750 FT CENTERS HEADER 1 IS APPROX. 33.3 FT LONG WITH 20 DIFFUSER CONNECTORS NODE APP. EQU. DIA. SCFM CFM VEL. VEL. HEADLOSS TOTAL STATIC * LENGTH PRESS. PRESS. PRESS. PRESS. (FT) (IN) (FPS) (PSI) (PSI) (PSIG) (PSIG) 1 E 4.6 4 155.3 112.2 24.0 6.43E-03 1.33E-03 6.910 6.904 2 17.5 4 155.3 112.2 24.0 6.43E-03 5.04E-03 6.905 6.899 3 T 15.5 4 155.3 112.2 24.0 6.43E-03 4.46E-03 6.901 6.894 ***** HEADER 1 ***** 4 34.0 4 0.0 0.0 0.0 0.00E+00 2.45E-03 6.898 6.898 ---------------------------------------------------------------------------- (STATIC HEADER PRESSURE DIFFERENTIAL IN ASSEMBLY= 3.98E-03 PSI) (AVERAGE HEADER PRESSURE IN ASSEMBLY - 6.8962 PSIG) ---------------------------------------------------------------------------- A: NET AVERAGE HEADLOSS FROM TOP OF DROPLEG TO HEADER= 1.527E-02 PSI B: DIFFUSER HEADLOSS= 9.094E-02 PSI AT 7.763 SCFM/DIFF, ONE SD1000 DIFFUSER PER DROP C: 15.500 FEET OF SUBMERGENCE= 6.7115 PSIG ---------------------------------------------------------------------------- TOTAL PRESSURE REQ'D AT TOP OF DROP, (A+B+C)= 6.8177 PSIG (FRICTION HEADLOSS (A+B)= 1.062E-01 PSI) NOTE: * -LABELS FOR APPURTENANCES- ------------------------ R-REDUCER, T-BRANCH FLOW TEE, RT-LINE FLOW TEE, E-90 DEG. ELBOW B-WIDE OPEN BUTTERFLY VALVE, S-SWING PEDESTAL & KNEE JOINTS. [page 4 of 4 a. sANrrAlvi F-0 WATER POLLUTION CONTROL CORP. ri SANITAIFIE0 SINGLE DROP DIFFUSER AERATION EQUIPMENT for Fairmont, NC Aerobic Digester #2 CONSULTING ENGINEER: Hobbs, Upchurch & Associates SANITAIRE #9770-97S June 26,1998 cjt cAsetupsVairl 9333 N. 49th Street Brown Deer, WI 53223 phone: 414-365-2200 fax: 414-365-2210 Web Sites: http://www.sanitaire.com http://www.abjwastewater.com c TANKAGE 1 TRAINS EACH CONSISTING OF: .............................................................................. :PASS PARALLEL ZONE SUBMERGENCE REACTOR VOLUME . :NO. REACTORS PROCESS (FEET) DIMENSIONS (FEET) (KCF/PASS): .............................................................................. 1 1 AEROBIC 15.50 40.66 L X 36.75 W X 16.50 D 24.65: .............................................................................. TOTAL VOLUME PER TRAIN 24.654 AERATED VOLUME PER TRAIN 24.654 DESIGN DATA :-----------------------------------------------------------: :COND. NO. BOD NH3-N OXYGEN AIR WATER TEMP.: TRAINS (#/DAY) (#/DAY) (#/DAY) (SCFM) (DEG. C. ) :.25 FT 1 298.838 @20 :20 S/K 1 493.0 @_ DESIGN PARAMETERS ----------------- !---------------------------------------------------------------------! ! COND. AOR/SOR ALPHA BETA THETA D.O. AMB. 02/ 02/ SRT ! ! (ppm) (PSIA) BOD5 NH3 (DAYS) ! !---------------------------------------------------------------------! !.2S/FT 14.6 ! !20 S/K 14.6 ! r r NOTES: @-PRECEDING A VALUE INDICATES AN ASSUMPTION BY SANITAIRE A -INDICATES ACTUAL (AOR) OXYGEN REQUIREMENT S-INDICATES STANDARD CONDITION (SOR) OXYGEN REQUIREMENT ROUND TANKS ARE EVALUATED AS SQUARE TANKS OF EQUAL SURFACE AREA IF THE AOR/SOR PARAMETER IS NOT GIVEN, THEN ITS VALUE WILL BE CALCULATED LATER IF SUITABLE ALPHA, BETA, D.O., THETA, PRESSURE AND TEMPERATURE DATA IS SUPPLIED. INDICATED PRESSURE IS EQUIVALENT TO SITE ELEVATION OF 60 FEET Pacre 2 of 4 PERFORMANCE SUMMARY EQUIPMENT: TYPE: SINGLE DROP DIFFUSER NUMBER OF ASSEMBLIES: 2 NUMBER DIFFUSERS/ASSEMBLY: 20 OXYGEN TRANSFER PERFORMANCE BASED ON: EACH HEADER AT CENTER OF 20.33 FEET WIDE AERATION BAND AND 15.50 FEET OF SUBMERGENCE. OXYGEN PERFORMANCE IS CORRELATED TO PLACEMENT GEOMETRY, DIFFUSER SUBMERGENCE, AND AIR RATE PER UNIT TANK VOLUME. (NOTE: SCFM/DIFFUSER DOES NOT DISPLAY SIGNIFICANT CORRELATION TO COARSE BUBBLE DEVICE PERFORMANCE USING THESE PARAMETERS) --------------------------------------------- CONDITION: : .2S/FT 20 S/K --------------------------------------------- TANKAGE: NO. TANKS 1 1 VOLUME/TANK (KCF) 24.6 24.6 TOTAL VOLUME (KCF) 24.6 24.6 OXYGEN TRANSFER: 02 ( #/DAY) AOR AOR/SOR 02 (#/DAY) STD. COND. 580.2 1029.5 02 (#/DAY/KCF) STD.CND. 23.5 41.7 STD. COND. EFF. (o) 7.75 8.33 SAFETY FACTOR (%} 10 10 AIR RATES: TOTAL SCFM 298.8 493.0 SCFM/ASSEMBLY 149.4 246.5 SCFM/KCF 12.1 20 SCFM/DIFFUSER 7.47 12.3 PSIG REQUIRED AT 6.9 7 TOP OF DROPLEG POWER ESTIMATES: *TOTAL BHP REQUIRED 11.5 19.2 STD. COND.(#02/BHP/HR) 2.09 2.22 SITE (#02/BHP/HR) --------------------------------------------- NOTE: BHP QUOTED ASSUMES ADIABATIC COMPRESSION, 70% MECHANICAL EFFICIENCY AND 0.3 PSI AIR MAIN HEADLOSS. MORE ACCURATE VALUES FOR POWER WILL DEPEND ON ACTUAL BLOWER, MOTOR, AND PLANT PIPING DESIGN. Page 3 of 4 ONE AERATION ASSEMBLY HEADLOSS CALCULATED FOR THE .2S/FT CONDITION AIR RATE PER ASSEMBLY= 149.42 SCFM ASSUMED OPERATING TEMPERATURE= 100 DEG F. ASSUMED TOTAL PRESSURE AT TOP OF DROPLEG= 6.911 PSIG DIFFUSER CONNECTORS SPACED AT 1.750 FT CENTERS HEADER 1 IS APPROX. 33.3 FT LONG WITH 20 DIFFUSER CONNECTORS ----------------------------------- NODE APP. EQU. DIA. SCFM CFM VEL. VEL. HEADLOSS TOTAL STATIC * LENGTH PRESS. PRESS. PRESS. PRESS. (FT) (IN) (FPS) (PSI) (PSI) (PSIG) (PSIG) 1 E 4.6 4 149.4 107.9 23.1 5.95E-03 1.23E-03 6.910 6.904 2 17.5 4 149.4 108.0 23.1 5.96E-03 4.67E-03 6.906 6.900 3 T 15.5 4 149.4 108.0 23.1 5.96E-03 4.13E-03 6.901 6.896 ***** HEADER 1 ***** 4 33.3 4 0.0 0.0 0.0 0.00E+00 2.22E-03 6.899 6.899 ---------------------------------------------------------------------------- (STATIC HEADER PRESSURE DIFFERENTIAL IN ASSEMBLY= 3.74E-03 PSI) (AVERAGE HEADER PRESSURE IN ASSEMBLY = 6.8974 PSIG) ---------------------------------------------------------------------------- A: NET AVERAGE HEADLOSS FROM TOP OF DROPLEG TO HEADER= 1.412E-02 PSI B: DIFFUSER HEADLOSS= 8.629E-02 PSI AT 7.471 SCFM/DIFF, ONE SD1000 DIFFUSER PER DROP C: 15.500 FEET OF SUBMERGENCE= 6.7115 PSIG ---------------------------------------------------------------------------- TOTAL PRESSURE REQ'D AT TOP OF DROP, (A+B+C)= 6.8119 PSIG (FRICTION HEADLOSS (A+B)= 1.004E-01 PSI) NOTE: * -LABELS FOR APPURTENANCES- ------------------------ R-REDUCER, T-BRANCH FLOW TEE, RT-LINE FLOW TEE, E-90 DEG. ELBOW B-WIDE OPEN BUTTERFLY VALVE, S-SWING PEDESTAL & KNEE JOINTS. Page 4 of 4l r WATER POLLUTION CONTROL CORP. ri SANITAIRE'9 SINGLE DROP DIFFUSER AERATION EQUIPMENT for Fairmont, NC Sludge Holding Tank CONSULTING ENGINEER: Hobbs, Upchurch & Associates SANITAIRE #9770-97S June 26,1998 cjt Osetupsftr4 9333 N. 49th Street Brown Deer, Wt 53223 phone: 414-365-2200 fax: 414-365-2210 Web Sites: http://www.sanitaire.com http://www.abiwastewater.com SANrrAiR F-0 ABJ"4 .,s TANKAGE 1 TRAINS EACH CONSISTING OF: .......................................................0......0........ :PASS PARALLEL ZONE SUBMERGENCE REACTOR VOLUME��: :NO. REACTORS PROCESS (FEET) DIMENSIONS (FEET) (KCF/PASS): ..................................... ....... ................ ................ . 1 1 AEROBIC 15.50 56.79 L X 64.83 W X 16.50 D 60.75: .................................................0....0....0....0............. TOTAL VOLUME PER TRAIN 60.7497 AERATED VOLUME PER TRAIN 60,7497 DESIGN DATA :-----------------------------------------------------------• :COND. NO. BOD NH3-N OXYGEN AIR WATER TEMP.: TRAINS (#/DAY) (#/DAY) (#/DAY) (SCFM) (DEG. C. ) :.25 FT 1 736.364 @20 :20 S/K 1 1214.9 @20 DESIGN PARAMETERS ----------------- !---------------------------------------------------------------------! ! COND. AOR/SOR ALPHA BETA THETA D.O. AMB. 02/ 02/ SRT ! ! (ppm) (PSIA) BOD5 NH3 (DAYS) ! !---------------------------------------------------------------------! !.2S/FT 14.6 ! !20 S/K 14.6 ! r r NOTES: @-PRECEDING A VALUE INDICATES AN ASSUMPTION BY SANITAIRE A -INDICATES ACTUAL (AOR) OXYGEN REQUIREMENT S-INDICATES STANDARD CONDITION (SOR) OXYGEN REQUIREMENT ROUND TANKS ARE EVALUATED AS SQUARE TANKS OF EQUAL SURFACE AREA IF THE AOR/SOR PARAMETER IS NOT GIVEN, THEN ITS VALUE WILL BE CALCULATED LATER IF SUITABLE ALPHA, BETA, D.O., THETA, PRESSURE AND TEMPERATURE DATA IS SUPPLIED. INDICATED PRESSURE IS EQUIVALENT TO SITE ELEVATION OF 60 FEET Pa e 2 of 4 r . . PERFORMANCE SUMMARY EQUIPMENT: TYPE: SINGLE DROP DIFFUSER NUMBER OF ASSEMBLIES: 3 NUMBER DIFFUSERS/ASSEMBLY: 35 OXYGEN TRANSFER PERFORMANCE BASED ON: EACH HEADER AT CENTER OF 18.93 FEET WIDE AERATION BAND AND 15.50 FEET OF SUBMERGENCE. OXYGEN PERFORMANCE IS CORRELATED TO PLACEMENT GEOMETRY, DIFFUSER SUBMERGENCE, AND AIR RATE PER UNIT TANK VOLUME. (NOTE: SCFM/DIFFUSER DOES NOT DISPLAY SIGNIFICANT CORRELATION TO COARSE BUBBLE DEVICE PERFORMANCE USING THESE PARAMETERS) --------------------------------------------- CONDITION: : .2S/FT 20 S/K --------------------------------------------- TANKAGE: . NO. TANKS : 1 1 VOLUME/TANK (KCF) 60.7 60.7 TOTAL VOLUME (KCF) 60.7 60.7 OXYGEN TRANSFER: 02 (# /DAY) AOR AOR/SOR 02 (#/DAY) STD. COND. 1429.9 2595.8 02 (#/DAY/KCF) STD.CND. 23.5 42.7 STD. COND. EFF. (%) 7.75 8.52 SAFETY FACTOR (o) 10 10 AIR RATES: TOTAL SCFM 736.3 1214.9 SCFM/ASSEMBLY 245.4 404.9 SCFM/KCF 12.1 20 SCFM/DIFFUSER 7.01 11.5 PSIG REQUIRED AT 6.9 7 TOP OF DROPLEG POWER ESTIMATES: *TOTAL BHP REQUIRED 28.4 47.4 STD. COND. (##02/BHP/HR) 2.09 2.27 SITE (#02/BHP/HR) --------------------------------------------- NOTE: BHP QUOTED ASSUMES ADIABATIC COMPRESSION, 700-, MECHANICAL EFFICIENCY AND 0.3 PSI AIR MAIN HEADLOSS. MORE ACCURATE VALUES FOR POWER WILL DEPEND ON ACTUAL BLOWER, MOTOR, AND PLANT PIPING DESIGN. Page 3 of 4 ONE AERATION ASSEMBLY HEADLOSS CALCULATED FOR THE .2S/FT CONDITION AIR RATE PER ASSEMBLY= 245.45 SCFM ASSUMED OPERATING TEMPERATURE= 100 DEG F. ASSUMED TOTAL PRESSURE AT TOP OF DROPLEG= 6.911 PSIG DIFFUSER CONNECTORS SPACED AT 1.900 FT CENTERS HEADER 1 IS APPROX. 64.6 FT LONG WITH 35 DIFFUSER CONNECTORS --------------------------------------------------- NODE APP. EQU. DIA. SCFM CFM VEL. VEL. HEADLOSS TOTAL STATIC * LENGTH PRESS. PRESS. PRESS. PRESS. (FT) (IN) (FPS) (PSI) (PSI) (PSIG) (PSIG) 1 E 5.4 6 245.5 177.3 16.2 2.94E-03 4.92E-04 6.911 6.908 2 17.5 6 245.5 177.3 16.2 2.94E-03 1.60E-03 6.909 6.906 3 T 19.7 6 245.5 177.4 16.2 2.94E-03 1.80E-03 6.908 6.905 ***** HEADER 1 ***** 4 20.0 6 168.3 121.6 11.1 1.38E-03 1.30E-03 6.906 6.905 5 R 5.1 4 168.3 121.6 26.0 7.56E-03 1.73E-03 6.905 6.897 6 82.7 4 0.0 0.0 0.0 0.00E+00 7.00E-03 6.898 6.898 ---------------------------------------------------------------------------- (STATIC HEADER PRESSURE DIFFERENTIAL IN ASSEMBLY= 7.91E-03 PSI) (AVERAGE HEADER PRESSURE IN ASSEMBLY = 6.8996 PSIG) ---------------------------------------------------------------------------- A: NET AVERAGE HEADLOSS FROM TOP OF DROPLEG TO HEADER= 1.186E-02 PSI B: DIFFUSER HEADLOSS= 7.927E-02 PSI AT 7.013 SCFM/DIFF, ONE SD1000 DIFFUSER PER DROP C: 15.500 FEET OF SUBMERGENCE= 6.7115 PSIG ---------------------------------------------------------------------------- TOTAL PRESSURE REQ'D AT TOP OF DROP, (A+B+C)= 6.8026 PSIG (FRICTION HEADLOSS (A+B)= 9.113E-02 PSI) NOTE: * -LABELS FOR APPURTENANCES- ------------------------ R-REDUCER, T-BRANCH FLOW TEE, RT-LINE FLOW TEE, E-90 DEG. ELBOW B-WIDE OPEN BUTTERFLY VALVE, S-SWING PEDESTAL & KNEE JOINTS. Page 4 of 4 C rj SAwrAiR E10 WATER POLLUTION CONTROL CORP. OBANITAIRF.'9 SINGLE DROP DIFFUSER AERATION EQUIPMENT for Fairmont, NC Thickener Pre -Mix Basin CONSULTING ENGINEER: Hobbs, Upchurch & Associates SANITAIRE #9770-97S June 25,1998 cjt OsetupslfaW 9333 N. 49th Street Brown Deer, Wl 53223 phone: 414-365-2200 fax: 414-365-2210 Web Sites: http://www.sanitaire.com http://www.abjwastewater.com ABI"A r °'TANKAGE 1 TRAINS EACH CONSISTING OF: .............................................................................. :PASS PARALLEL ZONE SUBMERGENCE REACTOR VOLUME . :NO. REACTORS PROCESS (FEET) DIMENSIONS (FEET) (KCF/PASS): .............................................................................. 1 1 AEROBIC 13.00 30.00 L X 4.00 W X 14.00 D 1.68: ............................................................................. TOTAL VOLUME PER TRAIN 1.68 AERATED VOLUME PER TRAIN 1.68 DESIGN DATA •-----------------------------------------------------------• :COND. NO. BOD NH3-N OXYGEN AIR WATER TEMP.: TRAINS (#/DAY) (#/DAY) (#/DAY) (SCFM) (DEG. C. ) :.25 FT 1 24 @20 :20 S/K 1 33.6 @_ DESIGN PARAMETERS ----------------- !---------------------------------------------------------------------! ! COND. AOR/SOR ALPHA BETA THETA D.O. AMB. 02/ 02/ SRT ! (ppm) (PSIA) BOD5 NH3 (DAYS) ! !---------------------------------------------------------------------! l.2S/FT 14.6 ! !20 S/K 14.6 ! ! NOTES: @-PRECEDING A VALUE INDICATES AN ASSUMPTION BY SANITAIRE A -INDICATES ACTUAL (AOR) OXYGEN REQUIREMENT S-INDICATES STANDARD CONDITION (SOR) OXYGEN REQUIREMENT ROUND TANKS ARE EVALUATED AS SQUARE TANKS OF EQUAL SURFACE AREA IF THE AOR/SOR PARAMETER IS NOT GIVEN, THEN ITS VALUE WILL BE CALCULATED LATER IF SUITABLE ALPHA, BETA, D.O., THETA, PRESSURE AND TEMPERATURE DATA IS SUPPLIED. INDICATED PRESSURE IS EQUIVALENT TO SITE ELEVATION OF 60 FEET lPacre 2 of 4 PERFORMANCE SUMMARY EQUIPMENT: TYPE: SINGLE DROP DIFFUSER NUMBER OF ASSEMBLIES: 1 NUMBER DIFFUSERS/ASSEMBLY: 8 OXYGEN TRANSFER PERFORMANCE BASED ON: EACH HEADER AT SIDE OF 4.00 FEET WIDE AERATION BAND AND 13.00 FEET OF SUBMERGENCE. OXYGEN PERFORMANCE IS CORRELATED TO PLACEMENT GEOMETRY, DIFFUSER SUBMERGENCE, AND AIR RATE PER UNIT TANK VOLUME. (NOTE: SCFM/DIFFUSER DOES NOT DISPLAY SIGNIFICANT CORRELATION TO COARSE BUBBLE DEVICE PERFORMANCE USING THESE PARAMETERS) --------------------------------------------- CONDITION: . .2S/FT 20 S/K --------------------------------------------- TANKAGE: . NO. TANKS 1 1 VOLUME/TANK (KCF) 1.68 1.68 TOTAL VOLUME (KCF) 1.68 1.68 OXYGEN TRANSFER: 02 (#/DAY) AOR AOR/SOR 02 (#/DAY) STD. COND. 39.0 54.7 02 (#/DAY/KCF) STD.CND. 23.2 32.5 STD. COND. EFF. (OU 6.5 6.5 SAFETY FACTOR M 10 10 AIR RATES: TOTAL SCFM 23.9 33.6 SCFM/ASSEMBLY 23.9 33.6 SCFM/KCF 14.2 20 SCFM/DIFFUSER 2.99 4.2 PSIG REQUIRED AT 5.8 5.9 TOP OF DROPLEG POWER ESTIMATES: *TOTAL BHP REQUIRED .80117 1.13 STD. COND.(#02/BHP/HR) 2.03 2.00 SITE (#02/BHP/HR) --------------------------------------------- NOTE: BHP QUOTED ASSUMES ADIABATIC COMPRESSION, 70% MECHANICAL EFFICIENCY AND 0.3 PSI AIR MAIN HEADLOSS. MORE ACCURATE VALUES FOR POWER WILL DEPEND ON ACTUAL BLOWER, MOTOR, AND PLANT PIPING DESIGN. Pa e 3 of 4 ONE AERATION ASSEMBLY HEADLOSS CALCULATED FOR THE .2S/FT CONDITION AIR RATE PER ASSEMBLY= 24.00 SCFM ASSUMED OPERATING TEMPERATURE= 100 DEG F. ASSUMED TOTAL PRESSURE AT TOP OF DROPLEG= 5.829 PSIG DIFFUSER CONNECTORS SPACED AT 4.000 FT CENTERS HEADER 1 IS APPROX. 28.0 FT LONG WITH 8 DIFFUSER CONNECTORS --- -------------------------------------------------- NODE APP. EQU. DIA. SCFM CFM VEL. VEL. HEADLOSS TOTAL STATIC * LENGTH PRESS. PRESS. PRESS. PRESS. (FT) (IN) (FPS) (PSI) (PSI) (PSIG) (PSIG) 1 E 4.6 4 24.0 18.3 3.9 1.62E-04 3.34E-05 5.829 5.829 2 15.0 4 24.0 18.3 3.9 1.62E-04 1.09E-04 5.829 5.829 3 T 15.5 4 24.0 18.3 3.9 1.62E-04 1.12E-04 5.829 5.829 ***** HEADER 1 ***** 4 28.0 4 0.0 0.0 0.0 O.00E+00 5.07E-05 5.829 5.829 ---------------------------------------------------------------------------- (STATIC HEADER PRESSURE DIFFERENTIAL IN ASSEMBLY= 1.11E-04 PSI) (AVERAGE HEADER PRESSURE IN ASSEMBLY = 5.8286 PSIG) ---------------------------------------------------------------------------- A: NET AVERAGE HEADLOSS FROM TOP OF DROPLEG TO HEADER= 3.600E-04 PSI B: DIFFUSER HEADLOSS= 1.273E-01 PSI AT 3.000 SCFM/DIFF, ONE SD1000 DIFFUSER PER DROP C: 13.000 FEET OF SUBMERGENCE= 5.6290 PSIG ---------------------------------------------------------------------------- TOTAL PRESSURE REQ'D AT TOP OF DROP, (A+B+C)= 5.7567 PSIG (FRICTION HEADLOSS (A+B)= 1.277E-01 PSI) NOTE: * -LABELS FOR APPURTENANCES- ------------------------ R-REDUCER, T-BRANCH FLOW TEE, RT-LINE FLOW TEE, E-90 DEG. ELBOW B-WIDE OPEN BUTTERFLY VALVE, S-SWING PEDESTAL & KNEE JOINTS. Pa e 4 of 4 { WATER POLLUTION CONTROL CORP. SANITAIRE° SINGLE DROP DIFFUSER AERATION EQUIPMENT for Fairmont, NC Rapid Mix Basin CONSULTING ENGINEER: Hobbs, Upchurch & Associates SANITAIRE #9770-97S June 25, 9 998 cjt c:%setupsVair6 9333 N. 49th Street Brown Deer. WI 53223 phone: 414-365-2200 fax: 414-365-2210 Web Sites: http://www.sanitaire.com http://www.abiwastewater.com 8ANMAIR F-e . ABJ 7M i .r TANKAGE 1 TRAINS EACH CONSISTING OF: .............................................................................. :PASS PARALLEL ZONE SUBMERGENCE REACTOR VOLUME . :NO. REACTORS PROCESS (FEET) DIMENSIONS (FEET) (KCF/PASS): .............................................................................: 1 1 AEROBIC 16.80 25.17 L X 10.00 W X 17.80 D 4.48: .............................................................................. TOTAL VOLUME PER TRAIN 4.47954 AERATED VOLUME PER TRAIN 4.47954 DESIGN DATA ------------ :COND. NO. BOD NH3-N OXYGEN AIR WATER TEMP.: TRAINS (#/DAY) (#/DAY) (#/DAY) (SQFM) (DEG. C. ) :40 S K 1 179.1 @20 DESIGN PARAMETERS ----------------- !---------------------------------------------------------------------! ! COND. AOR/SOR ALPHA BETA THETA D.O. AMB. 02/ 02/ SRT ! (ppm) (PSIA) BODS NH3 (DAYS) ! !---------------------------------------------------------------------! !40 S/K 14.6 ! i i NOTES: @-PRECEDING A VALUE INDICATES AN ASSUMPTION BY SANITAIRE A -INDICATES ACTUAL (AOR) OXYGEN REQUIREMENT S-INDICATES STANDARD CONDITION (SOR) OXYGEN REQUIREMENT ROUND TANKS ARE EVALUATED AS SQUARE TANKS OF EQUAL SURFACE AREA IF THE AOR/SOR PARAMETER IS NOT GIVEN, THEN ITS VALUE WILL BE CALCULATED LATER IF SUITABLE ALPHA, BETA, D.O., THETA, PRESSURE AND TEMPERATURE DATA IS SUPPLIED. INDICATED PRESSURE IS EQUIVALENT TO SITE ELEVATION OF 60 FEET Wage 2 of L4J PERFORMANCE SUMMARY EQUIPMENT: TYPE: SINGLE DROP DIFFUSER NUMBER OF ASSEMBLIES: 1 NUMBER DIFFUSERS/ASSEMBLY: 10 OXYGEN TRANSFER PERFORMANCE BASED ON: EACH HEADER AT SIDE OF 10.00 FEET WIDE AERATION BAND AND 16.80 FEET OF SUBMERGENCE. OXYGEN PERFORMANCE IS CORRELATED TO PLACEMENT GEOMETRY, DIFFUSER SUBMERGENCE, AND AIR RATE PER UNIT TANK VOLUME. (NOTE: SCFM/DIFFUSER DOES NOT DISPLAY SIGNIFICANT CORRELATION TO COARSE BUBBLE DEVICE PERFORMANCE USING THESE PARAMETERS) ------------------------------------ CONDITION: : 40 S/K ------------------------------------ TANKAGE: NO. TANKS 1 VOLUME/TANK (KCF) 4.47 TOTAL VOLUME (KCF) 4.47 OXYGEN TRANSFER: 02 ( # /DAY) AOR AOR/SOR 02 (#/DAY) STD. COND. 532.0 02 (#/DAY/KCF) STD.CND. 118.7 STD. COND. EFF. (%) 11.8 SAFETY FACTOR (o) 10 AIR RATES: TOTAL SCFM 179.1 SCFM/ASSEMBLY 179.1 SCFM/KCF 40 SCFM/DIFFUSER 17.9 PSIG REQUIRED AT 7.5 TOP OF DROPLEG POWER ESTIMATES: *TOTAL BHP REQUIRED 7.41 STD. COND.(#02/BHP/HR) 2.98 SITE (#02/BHP/HR) ------------------------------------ NOTE: BHP QUOTED ASSUMES ADIABATIC COMPRESSION, 70% MECHANICAL EFFICIENCY AND 0.3 PSI AIR MAIN HEADLOSS. MORE ACCURATE VALUES FOR POWER WILL DEPEND ON ACTUAL BLOWER, MOTOR, AND PLANT .PIPING DESIGN. Pacre 3 of 4 ONE AERATION ASSEMBLY HEADLOSS CALCULATED FOR THE 40 S/K CONDITION AIR RATE PER ASSEMBLY= 179.18 SCFM ASSUMED OPERATING TEMPERATURE= 100 DEG F. ASSUMED TOTAL PRESSURE AT TOP OF DROPLEG= 7.474 PSIG DIFFUSER CONNECTORS SPACED AT 2.500 FT CENTERS HEADER 1 IS APPROX. 22.5 FT LONG WITH 10 DIFFUSER CONNECTORS NODE APP. EQU. DIA. SCFM CFM VEL. VEL. HEADLOSS TOTAL STATIC * LENGTH PRESS. PRESS. PRESS. PRESS. (FT) (IN) (FPS) (PSI) (PSI) (PSIG) (PSIG) 1 E 4.6 4 179.2 126.1 26.9 8.34E-03 1.72E-03 7.473 7.464 2 18.8 4 179.2 126.2 27.0 8.35E-03 7.03E-03 7.466 7.457 3 T 15.5 4 179.2 126.2 27.0 8.35E-03 5.79E-03 7.460 7.452 ***** HEADER 1 ***** 4 22.5 4 0.0 0.0 0.0 0.00E+00 2.10E-03 7.458 7.458 ---------------------------------------------------------------------------- (STATIC HEADER PRESSURE DIFFERENTIAL IN ASSEMBLY= 6.25E-03 PSI) (AVERAGE HEADER PRESSURE IN ASSEMBLY - 7.4546 PSIG) ---------------------------------------------------------------------------- A: NET AVERAGE HEADLOSS FROM TOP OF DROPLEG TO HEADER= 1.977E-02 PSI B: DIFFUSER HEADLOSS= 1.164E-01 PSI AT 17.918 SCFM/DIFF, ONE SD1000 DIFFUSER PER DROP C: 16.800 FEET OF SUBMERGENCE= 7.2744 PSIG ---------------------------------------------------------------------------- TOTAL PRESSURE REQ'D AT TOP OF DROP, (A+B+C)= 7.4106 PSIG (FRICTION HEADLOSS (A+B)= 1.362E-01 PSI) NOTE: * -LABELS FOR APPURTENANCES- ------------------------ R-REDUCER, T-BRANCH FLOW TEE, RT-LINE FLOW TEE, E-90 DEG. ELBOW B-WIDE OPEN BUTTERFLY VALVE, S-SWING PEDESTAL & KNEE JOINTS. Page 4 of 41 WATER POLLUTION CONTROL CORP. ri SANITAIRE'o SINGLE DROP DIFFUSER AERATION EQUIPMENT for Fairmont, NC Aerated Influent Channel CONSULTING ENGINEER: Hobbs, Upchurch & Associates SANITAIRE #9770-97S June 25,1998 cjt cAsetupsftr5 9333 N. 49th Street Brown Deer. WI 53223 phone: 414-365-2200 fax: 414-365-2210 Web Sites: http://www.sanitaire.com http://www.abjwastewater.com ABI TM BANrrAsR E0 :.;TANKAGE 1 TRAINS EACH CONSISTING OF: .............................................................................. :PASS PARALLEL ZONE SUBMERGENCE REACTOR VOLUME . :NO. REACTORS PROCESS (FEET) DIMENSIONS (FEET) (KCF/PASS): .............................................................................. 1 1 AEROBIC 16.80 177.00 L X 4.00 W X 17.80 D 12.60: .............................................................................. TOTAL VOLUME PER TRAIN 12.6024 AERATED VOLUME PER TRAIN 12.6024 DESIGN DATA :-----------------------------------------------------------: :COND. NO. BOD NH3-N OXYGEN AIR WATER TEMP.: TRAINS (#/DAY) (#/DAY) (#/DAY) (SCFM) (DEG. C. ) :3 S LF 1 531 @20 . DESIGN PARAMETERS ----------------- ---------------------------------------------------------------------! ! COND. AOR/SOR ALPHA BETA THETA D.O. AMB. 02/ 02/ SRT ! (ppm) (PSIA) BODS NH3 ( DAYS) ! ---------------------------------------------------------------------! !3 S/LF 14.6 NOTES: Q-PRECEDING A VALUE INDICATES AN ASSUMPTION BY SANITAIRE A -INDICATES ACTUAL (AOR) OXYGEN REQUIREMENT S-INDICATES STANDARD CONDITION (SOR) OXYGEN REQUIREMENT ROUND TANKS ARE EVALUATED AS SQUARE TANKS OF EQUAL SURFACE AREA IF THE AOR/SOR PARAMETER IS NOT GIVEN, THEN ITS VALUE WILL BE CALCULATED LATER IF SUITABLE ALPHA, BETA, D.O., THETA, PRESSURE AND TEMPERATURE DATA IS SUPPLIED. INDICATED PRESSURE IS EQUIVALENT TO SITE ELEVATION OF 60 FEET Pacre 2 of 4 PERFORMANCE SUMMARY ------------------- EQUIPMENT: TYPE: SINGLE DROP DIFFUSER NUMBER OF ASSEMBLIES: 1 NUMBER DIFFUSERS/ASSEMBLY: 60 OXYGEN TRANSFER PERFORMANCE BASED ON: EACH HEADER AT SIDE OF 4.00 FEET WIDE AERATION BAND AND 16.80 FEET OF SUBMERGENCE. OXYGEN PERFORMANCE IS CORRELATED TO PLACEMENT GEOMETRY, DIFFUSER SUBMERGENCE, AND AIR RATE PER UNIT TANK VOLUME. (NOTE: SCFM/DIFFUSER DOES NOT DISPLAY SIGNIFICANT CORRELATION TO COARSE BUBBLE DEVICE PERFORMANCE USING THESE PARAMETERS) ------------------------------------ CONDITION: :3 S/LFT ------------------------------------ TANKAGE: NO. TANKS 1 VOLUME/TANK (KCF) 12.6 TOTAL VOLUME (KCF) 12.6 OXYGEN TRANSFER: 02 (#/DAY) AOR AOR/SOR 02 (#/DAY) STD. COND. 1616.9 02 (#/DAY/KCF) STD.CND. 128.3 STD. COND. EFF. (%) 12.1 SAFETY FACTOR (%) 10 AIR RATES: . TOTAL SCFM 530.9 SCFM/ASSEMBLY 530.9 SCFM/KCF 42.1 SCFM/DIFFUSER 8.84 PSIG REQUIRED AT 7.4 TOP OF DROPLEG POWER ESTIMATES: *TOTAL BHP REQUIRED 21.7 STD. COND.(#02/BHP/HR) 3.09 SITE (#02/BHP/HR) ------------------------------------ NOTE: BHP QUOTED ASSUMES ADIABATIC COMPRESSION, 70o MECHANICAL EFFICIENCY AND 0.3 PSI AIR MAIN HEADLOSS. MORE ACCURATE VALUES FOR POWER WILL DEPEND ON ACTUAL BLOWER, MOTOR, AND PLANT PIPING DESIGN. Pa e 3 of 4 ONE AERATION ASSEMBLY HEADLOSS CALCULATED FOR THE 3 S/LFT CONDITION AIR RATE PER ASSEMBLY= 531.00 SCFM ASSUMED OPERATING TEMPERATURE= 100 DEG F. ASSUMED TOTAL PRESSURE AT TOP OF DROPLEG= 7.474 PSIG DIFFUSER CONNECTORS SPACED AT 2.900 FT CENTERS HEADER 1 IS APPROX. 171.1 FT LONG WITH 60 DIFFUSER CONNECTORS NODE APP. EQU. DIA. SCFM CFM VEL. VEL. HEADLOSS TOTAL STATIC * LENGTH PRESS. PRESS. PRESS. PRESS. (FT) (IN) (FPS) (PSI) (PSI) (PSIG) (PSIG) 1 E 5.9 8 531.0 373.8 18.9 4.09E-03 5.90E-04 7.474 7.470 2 18.8 8 531.0 373.9 18.9 4.09E-03 1.88E-03 7.472 7.468 3 T 23.0 8 531.0 373.9 18.9 4.09E-03 2.30E-03 7.470 7.466 ***** HEADER 1 ***** 4 80.0 8 283.2 199.4 10.1 1.16E-03 4.70E-03 7.465 7.464 5 R 4.5 6 283.2 199.5 18.2 3.82E-03 5.37E-04 7.464 7.461 6 254.0 6 0.0 0.0 0.0 0.00E+00 7.56E-03 7.457 7.457 ---------------------------------------------------------------------------- (STATIC HEADER PRESSURE DIFFERENTIAL IN ASSEMBLY= 8.71E-03 PSI) (AVERAGE HEADER PRESSURE IN ASSEMBLY - 7.4615 PSIG) ---------------------------------------------------------------------------- A: NET AVERAGE HEADLOSS FROM TOP OF DROPLEG TO HEADER= 1.292E-02 PSI B: DIFFUSER HEADLOSS= 1.066E-01 PSI AT 8.850 SCFM/DIFF, ONE SD1000 DIFFUSER PER DROP C: 16.800 FEET OF SUBMERGENCE= 7.2744 PSIG ---------------------------------------------------------------------------- TOTAL PRESSURE REQ'D AT TOP OF DROP, (A+B+C)= 7.3940 PSIG (FRICTION HEADLOSS (A+B)= 1.196E-01 PSI) NOTE: * -LABELS FOR APPURTENANCES- ------------------------ R-REDUCER, T-BRANCH FLOW TEE, RT-LINE FLOW TEE, E-90 DEG. ELBOW B-WIDE OPEN BUTTERFLY VALVE, S-SWING PEDESTAL & KNEE JOINTS. Pa e 4 of 74 I' W/ p AIR MAIN T.O.T. EL. I OP.OP! EG CONN. EL. 1 S.S. TEE S.S. PLUG I" S.S. UNION SANITAIRE TO HERE 3/4- SCH. 40 SEE DETAIL 63 I" SCH. 40 S.S. DROPLEG 3 X 3 X 1/4' S.S. ANGLE (TYP) 18"o PVC DEFLECTOR PLATE 37 REOUIRED ALTERNATE HEIGHT OF PLATE FOR EVERY OTHER OROPLEC. DROPLECS NEXT TO WALL OR COLUMN DO NOT HAVE PLATE. SD 1000 DIFFUSER SEE DETAIL NS-1 SHEET -27 AIR RELEASE EL. FLOOR EL. TION TA 10' -1- / 8 SPACES 0 1'-0' f. 8--0- 3 3 X 1/4- 31 S.S. ANCLE TANK 1 CAI II[Nrf1 -4, IL c f>Luo 5'-4' I" X 3/4' S.S. buSHINb SINGLE DROP DIFFUSER DET ALL be 0 1'd FPi rnmmrrrinu cvir ■m %144 l o c "I I oo. I art I M+rAw A •jft ftzj w 4 C.D r` ` ' c z O r= 1� CITY OF GREENSBORO NORTH CAROUNA T.Z. OSBORNE WASTEWATER TREATMENT PLANT r....4 a •t —cnM of —Q. -a&~ wow co..m s to«um AL SETTLING TANK DISTRIBUCON CHANNEL SINGLE DROP DIFFUSER SECTION SINGLE DROP DIFFUSER DErAll- SATA[RE wARP •a•w.ca ..scoMs� or of we so.lo.as -an 96-3530 s" \ O•K 1 r, we '+K E-27 SlINGLE DROP FFUSEr� DETA- D-1 F Hobbs, Upchurch & Associates, P.A. Consulting Engineers 290 S.W. Broad Street • Post Office Box 1737 , Southern Pines, NC 28388 March 19, 2000 Mr. Michael E. Templeton NCDENR Division of Water Quality NPDES Unit 1617 Mail Service Center Raleigh, North Carolina 27699-1617 Re: Town of Fairmont Wastewater Treatment Plant ATC No. 021059ACA HUA No. FR9605.p Dear Mike: Fax: (919) 733-0719 n� 6 IS Li L____.J Per our telephone conversation Thursday, I have summarized a list of equipment with specification reference. I will gladly add detail to this if that is what you need. I also discovered the same discrepancy in aeration volume as you mentioned. The specifications appear to be more accurate with a volume of 47,147 cf each. This does not appear to change the outcome of the design calculation results with respect to concept and feasibility. As you know, I am faced with a serious funding issue with Rural Development and I appreciate your assistance and cooperation in the approval of this project. If you should have any additional questions regarding this project, please do not hesitate to contact this office. Sincerely, HOBBS, UPCHUBLU AND ASSOCIATES, P.A. Bill Lester, Jr., P.E. Governmental Division Manager Cc: Ben Hill, Town Manager, Fairmont Southern Pines, NC a Telephone 910-692-5616 • Fax 910-692-7342 • e-mail: huamain@pinehurst.net Myrtle Beach • Kill Devil Hills • Raleigh Town of Fairmont, Robeson County, NC Wastewater Treatment Plant Summary of Design Elements Description Mechanical Cleaned Bar Screen Manual Bar Screen Grit Removal & Dewatering Equipment Aeration System Circular Clarifier Equipment Centrifugal Air Blower Sludge Thickener Pumps — Sludge Loading Pumps — Existing WWTP Pumps — Effluent Pump Station Pumps — Treatment Plant Instrumentation Refrigerated Sampler Airlift Pumps Flow Control Equipment Clorination/Dechlorination Equipment Dimensions/Capacity 1.0 mgd / 2.5 mgd max. 1.0 mgd / 2.5 mgd max. Rolling grit aeration Diffused Air System 6388 scfin total airflow SOTR = 215.8 lb/hr 75'0" dia. (octagonal basin) 3 ea @ 3200 scfin / 150 hp 30'0" dia., 15'6" s.w. depth Centrifugal Solids Handling 1 ea — 225 gpm @ 13.1' TDH Submersible Centrifugal 2 ea - 720 gpm @ 153' TDH, 75 hp 1 ea —1020 gpm @ 218' TDH, 125 hp Submersible Centrifugal 2 ea — 750 gpm @ 62' TDH, 25 hp 1 ea — 2000 gpm @ 108' TDH, 100 hp Submersible Centrifugal 2 ea — 250 gpm @ 35' TDH, 5 hp As Noted As Noted RAS — 4 ea @ 900 gpm (10") WAS/Scum — 4ea @ 140 gpm (4") Thick. Scum — 2 ea @ 250 gpm (6") Thick. Sludge — 2 ea @ 250 gpm (6") Relift — 3 ea @ 1200 gpm (12") Pivot Gates, Weir Gates, Inlet Stacks Chlorine/Sulfur Dioxide Reference Section 19 Page 1 Section 19 Page 1 Section 20 Page 1 Section 21 Page 1 Section 22 Page 1 Section 23 Page 1 Section 24 Page 1 Section 25 Page 4 Section 25 Page 6 Section 25 Page 7 Section 25 Page 7 Section 26 Page 1 Section 27 Page 1 Section 28 Page 1 Section 29 Page 1 Section 30 Page 1 c�! TOWN OF FAIRMONT P.O. Box 248, FAIRMONT, N.C. 28340, PHONE (91 O) 628-9766 FAX (91 O) 628-9584 March 9, 1999 Mr. Dave Goodrich, P.E. North Carolina Department of Environment and Natural Resources Division of Water Quality P.O. Box 29535 Raleigh, North Carolina 27626-0535 Re: Town of Fairmont Wastewater Treatment Plant, Robeson County Request for Authorization to Construct Facilities NPDES Permit No. NCO021059 Dear Mr. Goodrich, Please find the attached materials for your use in review of the referenced project: 1. Three (3) sets of plan drawings 2. Three (3) sets of project specifications 3. Three (3) sets of project design calculations 4. Check in the amount of $200.00 for the permit application fee When completed, this new regional wastewater treatment facilit� will serve the Town of Fairmont, and the Orrum Middle School, eliminating. both of their current discharges as a result. This plant also has the potential to serve several towns and communities in Robeson County and Columbus County. By action of this submittal, we are requesting that the Division of Water Quality grant formal Authorization to Construct this new Wastewater Treatment Plant. Please contact Mr. Bill Lester, P.E. at Hobbs, Upchurch & Associates, P.A. (910-692- 5616) should there be questions comments, or if additional information is needed for project review. We appreciate your cooperation in this matter. Sincerely TOWN OF FAIRMONT Ben Hill Town Manager cc: Bill Lester, Hobbs, Upchurch & Associates, P.A.