HomeMy WebLinkAbout20220439 Ver 1_As-Built Credit Release_Juniper TractDEPARTMENT OF THE ARMY
WILMINGTON DISTRICT, CORPS OF ENGINEERS
69 DARLINGTON AVENUE
WILMINGTON, NORTH CAROLINA 28403-1343
November 1, 2023
Regulatory Division
SUBJECT: As-built baseline monitoring report approval and credit release associated
with the Lower Cape Fear UMB - Juniper Tract, Action ID SAW-2019-01067
Mr. Jon Vincent
LCFUMB, LLC
1015 Ashes Drive, Suite 202
Wilmington, North Carolina 28403
Dear Mr. Vincent:
This letter is to inform you that the Wilmington District, Corps of Engineers (Corps)
has reviewed the as-built baseline monitoring report for the Lower Cape Fear Umbrella
Mitigation Bank (UMB) - Juniper Tract, dated April 2023, and the subsequent Mitigation
Plan Addendum (modification) dated July 31, 2023. The Juniper Tract is in the Cape
Fear River Basin (Hydrologic Unit Code 03030005), located on the south side of Mill
Creek Road SE and north of Danford Road, in Brunswick County, NC.
In accordance with Sec. 332.8(o)(9) of the Federal Mitigation Rule, the baseline
monitoring report was provided to the North Carolina Interagency Review Team
(NCIRT) for review and comment on June 1, 2023. A site meeting was also held on
July 13, 2023, to assess the as-built site conditions. During this meeting, the NCIRT
noted several actions that had to be completed prior to the approval of the as-built plans
and associated credit release, which resulted in a modification request. The two major
items submitted with the modification included the removal of sections of road within the
site from creditable areas and the submittal of a plan to repair a failing structure on a
tributary. Both items were addressed with the July 31st submittal, and no additional
comments were received during the IRT review of the project modification request.
Pursuant to the UMB Instrument approved on January 23, 2013, and the site-
specific Juniper Tract Final Mitigation Plan dated October 6, 2021, 15 percent of the
mitigation site’s total restoration and enhancement credits shall be available for sale
immediately after the completion of implementation of the mitigation plan and Corps
approval of the baseline monitoring report and as-built survey. By copy of this
-2-
correspondence, we confirm that you have satisfied the above requirements for the as-
built credit release, and 822.900 Stream Mitigation Units (SMUs), 5.000 Riparian
Wetland Mitigation Units and 45.700 Non-Riparian WMUs are now available for sale.
Please note that this correspondence corrects an error associated with our letter of
December 15, 2022, that provided the initial release of credits for this site. The initial
letter mistakenly released an additional 9.6 Non-Riparian WMUs; however, the
approved mitigation plan incorporated these credits within the total to be released
annually. Accordingly, with this release, 1,645.800 SMUs, 10.200 Riparian WMUs and
94.300 Non-Riparian WMUs (30 percent of the site’s total credit) are now available for
sale. The attached credit release schedule has been updated to reflect all changes to
the credit release schedule. Please ensure that future credit release requests utilize the
updated credit release schedule.
Please note that this electronic copy provided to you via email is your official copy.
Should you wish to receive a paper copy of this correspondence, please contact us.
Thank you for your time and cooperation. If you have any questions, please contact me
by email at todd.tugwell@usace.army.mil or by phone at (919) 210-6265.
Sincerely,
Todd Tugwell
Chief, Mitigation Branch
Enclosure
cc (by email):
NCIRT Distribution List
Juniper Tract – Final Mitigation Plan
Lower Cape Fear Umbrella Mitigation Bank
Lower Cape Fear River Basin (HUC 03030005)
October 6, 2021
54
Task Project Milestone Projected Completion
1 Approval of Mitigation Plan December 2021
2 Recordation of Conservation Easement Deed January 2022
3 Initiation of Site Earthwork March 2022
4 Mitigation Site Earthwork Completed August 2022
5 Mitigation Site Planting and Installation of Monitoring Devices December 2022 or February 2023
6 Submittal of As-Built Report March 2023
7 First Year Annual Monitoring October 2023
8 Submittal of Monitoring Report #1 to IRT April 15, 2024
9 Submittal of Monitoring Report #2 to IRT April 15, 2025
10 Submittal of Monitoring Report #3 to IRT April 15, 2026
11 Submittal of Monitoring Report #4 to IRT April 15, 2027
12 Submittal of Monitoring Report #5 to IRT April 15, 2028
13 Submittal of Monitoring Report #6 to IRT April 15, 2029
14 Submittal of Monitoring Report #7 to IRT April 15, 2030
Table 18. Sample Credit Release Schedule (Non-Riparian Wetlands)
Task
Projected
Completion
Date
Percentage of
Wetland Credits
Released
(% Cumulative)
Number of Credits
Released
1. Recordation of Conservation
Easement 12/2021 15 (15) 48.6
2.Completion of Physical and
Biological Improvements 12/2022 15 (30) 48.6
3.Year 1 Monitoring Report 4/2024 10 (40) 32.4
4. Year 2 Monitoring Report 4/2025 10 (50) 32.4
5. Year 3 Monitoring Report 4/2026 15 (65) 48.5
6.Year 4 Monitoring Report *4/2026 5 (70) 16.2
7. Year 5 Monitoring Report 4/2028 15 (85) 48.5
8. Year 6 Monitoring Report *4/2029 5 (90) 16.2
9.Year 7 Monitoring Report 4/2030 10 (100) 32.4
Total 100% 323.8
*Vegetation plot data may not be required with monitoring reports submitted during these monitoring years
unless directed by the IRT.
314.6
45.7
47.2
47.2
31.5
31.5
31.5
15.7
15.7
NOTE: PER AS-BUILT AND MIT PLAN ADDENDUM, CREDITS WERE REDUCED FROM
MITIGATION PLAN DUE TO TREES NOT HARVESTED AND PLANTED AND ROAD NOT
SUFFICIENTLY REMOVED.
CREDIT RELEASE TABLES REVISED JULY 2023
Table 17. Project Timeline
Juniper Tract – Final Mitigation Plan
Lower Cape Fear Umbrella Mitigation Bank
Lower Cape Fear River Basin (HUC 03030005)
October 6, 2021
55
Table 19. Sample Credit Release Schedule (Riparian Non-Riverine Wetlands)
Task
Projected
Completion
Date
Percentage of
Wetland Credits
Released
(% Cumulative)
Number of Credits
Released
1.Recordation of Conservation
Easement 01/2022 15 (15) 5.2
2. Completion of Physical and
Biological Improvements 12/2022 15 (30) 5.2
3.Year 1 Monitoring Report 4/2024 10 (40) 3.5
4. Year 2 Monitoring Report 4/2025 10 (50) 3.5
5. Year 3 Monitoring Report 4/2026 15 (65) 5.2
6. Year 4 Monitoring Report *4/2026 5 (70) 1.8
7.Year 5 Monitoring Report 4/2028 15 (85) 5.2
8. Year 6 Monitoring Report *4/2029 5 (90) 1.7
9. Year 7 Monitoring Report 4/2030 10 (100) 3.5
Total 100% 34.8
*Vegetation plot data may not be required with monitoring reports submitted during these monitoring years
unless directed by the IRT.
Table 20. Sample Credit Release Schedule (Streams)
Task
Projected
Completion
Date
Percentage of
Stream Credits
Released
(% Cumulative)
Number of Credits
Released
1. Recordation of Conservation
Easement 01/2022 15 (15) 822.9
2.Completion of Physical and
Biological Improvements 12/2022 15 (30) 822.9
3.Year 1 Monitoring Report 4/2024 10 (40) 548.6
4. Year 2 Monitoring Report 4/2025 10 (50) 548.6
5.Year 3 Monitoring Report 4/2026 10 (60) 548.6
6. Year 4 Monitoring Report *4/2026
5 (65)
(75**)
274.3
(822.9**)
7. Year 5 Monitoring Report 4/2028
10 (75)
(85**) 548.6
8.Year 6 Monitoring Report *4/2029
5 (80)
(90**) 274.3
9. Year 7 Monitoring Report 4/2030
10 (90)
(100**) 548.6
Total 100% 5,486
*Vegetation plot data may not be required with monitoring reports submitted during these monitoring years
unless directed by the IRT.
**10% reserve of credits to be held back until the bankfull event performance standard has been met
33.8
5.0
5.0
5.0
3.4
3.4
3.4
1.7
1.7
NOTE: CREDITS REDUCED FROM MITIGATION PLAN DUE TO SPOIL AREA AND TREES NOT
HARVESTED AND PLANTED.