Loading...
HomeMy WebLinkAboutNC0026441_Quarterly SOC Progress Report (Q3 2023)_20231030Town of Siler City-Siler City WWTP EMC SOC WQ S22-033 Quarterly SOC Progress Report 3rd Quarter 2023 Please accept this submittal as a quarterly progress report for the work and activities of the Town of Siler City under the Special Order By Consent. Scheduled Activities paragraph 2(a) Quarterly Reports Quarterly Nutrient Optimization Report and Quarterly SOC Report were submitted on July 30, 2023 Collection System Permit WQCS00056 Permit for Main Interceptor Replacement Project was Submitted on February 28, 2023, Sewer Extension Permit was issued on April 19, 2023. ARPA Sewer Rehabilitation Project Engineering Report was submitted on May 1, 2023, (not a formal activity), ER review is pending with NCDEQ however Survey work is complete, and design is underway for this project. Permit submittals are expected to be completed on schedule by November 30. All other Activities are scheduled for future quarters and are currently expected to be on schedule. NPDES Permit NC0026441 IUP Permits were issued to Mountaire Farms, Brookwood Farms, and the Siler City Water Treatment Plant on May 19, 2023. Mountaire Farms requested an adjudicatory hearing for their permit which was held on July 21. Mountaire is currently appealing the results of the hearing. Supplemental Aeration Equipment has been installed in the oxidation ditch basins. The installation was complete on May 26, 2023, with initial email notification on May 30 and a formal letter on June 29, 2023, notifying NCDEQ of completion. All other Activities are scheduled for future quarters and are currently expected to be on schedule. Water Treatment Plant IUP Permit was issued to the Siler City Water Treatment Plant on May 19, 2023. Construction of the WTP Pretreatment Improvements is still underway. During a meeting on October 27, 2023, the Contract indicated that there are 3 outstanding items to be ready to put the system into operation. A flow meter which was shipped with the wrong connection type, delivery of sand and polymer (scheduled for October 31, 2023) and wiring of a torque switch. They expect the equipment could be ready to startup by November 3rd however resolution to these issues must be completed. McGill Associates has been retained to provide Engineering services for the WTP Solids Handling Improvements and is currently preparing an Engineering Report evaluating alternative configurations. Action Items under Paragraph 4(a) Phase 1 All Action Items associated with Phase 1 have been completed. Phase 2 Town is working to obtain all permits and funding required to begin construction for the WWTP. Approval of the State budget begins the process with NCDEQ DWI. The Town expects to submit plans and specifications to DWI for review and approval in November 2023 and will work to advertise for Bids as soon as DWI approval is available. As noted above, supplemental aeration equipment installation was completed on May 26, 2023. As noted above, the Town is issued updated IUPs on May 19, 2023 Phase 3 No overflows from the Town's WTP have occurred from date of execution of the SOC. As noted above, the WTP pretreatment system improvements schedule has been delayed and is expected to be complete in mid -November. Phase 4 Activities are scheduled for future quarters. Additional Wastewater Flow Pursuant to Paragraph 4 Issuance of flow has been given to: Brookwood Farms 25,000 GPD Jersey Mike's 520 GPD Ingle Street Subdivision 1080 GPD @ 120 gallons will be reduced to 675 GPD @ 75 gallons, when HB600 goes into effect. Wolfspeed construction 40,000 GPD Project Ice 4000 GPD Deliverance Church 1195 GPD