HomeMy WebLinkAboutNCC233182_ESC Approval Submitted (3)_20231024 Letter of Approval with Modifications
Dream Builders WS Construction, LLC
October 5, 2023
Page 3 of 3
MODIFICATIONS REQUIRED FOR APPROVAL
Project Name: Wynnfall Subdivision
Project ID: DAVID-2024-017
County: Davidson
Plan Review By: Jack Lawry-Popelka
Modifications pursuant to applicable North Carolina General Statutes and/or Regulations:
1. Please notify this office prior to your pre-construction conference for this project by calling
(336) 776-9800 and asking to speak with the Land Quality inspector for your county. [GS
113A-51, 15A NCAC 4B .0120]
2. Any off-site borrow and waste required for this project must come from a site with an
approved erosion control plan, a site regulated under the Mining Act of 1971, or a landfill
regulated by the Division of Solid Waste Management. Trash/debris from demolition
activities or generated by any activities on site must be disposed of at a facility regulated by
the Division of Solid Waste Management or per Division of Solid Waste Management or
Division of Water Resources rules and regulations. [15A NCAC 4B .0110]
3. Additional measures may be required - The applicant is responsible for the control of
sediment on-site. If the approved erosion and sedimentation control measures prove
insufficient, the applicant must take those additional steps necessary to stop sediment from
leaving this site. [15A NCAC 4B .0115]
4. The NCG01 has a $100 yearly fee and our office often receives closure inspection requests
days prior to yearly NCGO1 fee payment due dates. Be advised the project requires a closure
inspection report by DEMLR prior to filing the Notice of Termination (NOT) to terminate
NCGO1 coverage. The closure inspection should not be requested until after the site has
achieved full vegetative stabilization and measures have been removed. The removal of
temporary ESC measures, including basins, requires prior approval. Often, a full growing
season is necessary between initial seeding/mulching and removal of measures. Please plan
your construction accordingly to avoid contacting our office prematurely for a closure
inspection. Also be advised you may be asked for representative site pictures prior to a
closure inspection. [General Comment]
Ref: G.S. 113A-54.1 through G.S. 113A-57
Sections 15A NCAC 04A.0101 through 15A NCAC 04E.0504
General Permit NCG 010000 NPDES for Construction Activities