HomeMy WebLinkAboutNCC232884_ESC Approval Submitted_20231009 DEPARTMENT OF PUBLIC UTILITIES
Post Office Box 2263
SMITHFIELD,NC 27577
(919) 989-5075
September 1, 2023
LETTER OF APPROVAL
John H. Richard
RRT Development, LLC
PO Box 190
Clayton,NC 27528
RE: Project Name: Grabtown Road Subdivision (Roads& Infrastructure Only)
Project ID: JC#23-021 -P
Disturbed Acres Approved: 12.35 acres
Stream Classification: Neuse River(WS-V;NSW)
Submitted By: Stocks Engineering
To Whom It May Concern:
Johnston County has reviewed the subject revised erosion and sedimentation control plan for the above
referenced development. We find the plan to be acceptable and hereby issue this Letter of Approval.
The attached Certificate of Approval must be posted at the job site. This plan shall expire three (3)
years following the date of approval, if no land disturbing activity has been undertaken, as is required
by Title 15A NCAC 4B .0129.
As of April 1, 2019, all new construction activities are required to complete and submit an electronic
Notice of Intent(eNOI) form requesting a Certificate of Coverage (COC)under the NCG010000
Construction Stormwater General Permit. After the form is reviewed and found to be complete,you
will receive a link with payment instructions for the $100 annual permit fee. After the fee is processed,
you will receive the COC via email. As the Financially Responsible Party shown on the FRO form
submitted for this project,you MUST obtain the COC prior to commencement of any land disturbing
activity. The eNOI form may be accessed at deq.nc.gov/NCG01. Please direct questions about
the eNOI form to the Stormwater Program staff in the Raleigh central office. If the owner/operator of
this project changes in the future, the new responsible party must obtain a new COC.
Title 15A NCAC 4B .0118(a) and the NCGO 1 permit require that the following documentation be kept
on file at the job site:
1. The approved E&SC plan as well as any approved deviation.
2. The NCG01 permit and the COC, once it is received.
3. Records of inspections made during the previous 30 days.
Also,this letter gives the notice required by G.S. 113A-61.1(a) of our right of periodic inspection to
insure compliance with the approved plan.
Letter of Approval
Grabtown Road Subdivision ESC
Project No.: 23-021
September 1,2023
North Carolina's Sedimentation Pollution Control Act is performance-oriented,requiring protection of
existing natural resources and adjoining properties. If, following the commencement of this project, the
erosion and sedimentation control plan is inadequate to meet the requirements of the Sedimentation
Pollution Control Act of 1973 (North Carolina General Statute 113A-51 through 66),this office may
require revisions to the plan and implementation of the revisions to insure compliance with the Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and State water
quality laws,regulations, and rules. In addition, local city or county ordinances or rules may also apply
to this land-disturbing activity. This approval does not supersede any other permit or approval.
Please note that this approval is based in part on the accuracy of the information provided in the
Financial Responsibility Form, which you provided. You are requested to file an amended form if there
is any change in the information included on the form. In addition, it would be helpful if you notify this
office of the proposed starting date for this project.
Please contact this office to schedule the preconstruction meeting before beginning land disturbing
activities.
Your cooperation is appreciated.
Sincerely,
9/021i 60a;a1�
Jessica Batten
Development Engineer/Stormwater Manager
cc: Charles Pender,Johnston County
Shannon Stanley,Johnston County