HomeMy WebLinkAbout20201095 Ver 1_As-Built Credit Release_Double Rock_SAW-2020-01532DEPARTMENT OF THE ARMY
WILMINGTON DISTRICT, CORPS OF ENGINEERS
69 DARLINGTON AVENUE
WILMINGTON, NORTH CAROLINA 28403-1343
September 27, 2023
Regulatory Division
SUBJECT: As-built baseline monitoring report approval and credit release associated
with the Wildlands Catawba 01 Umbrella Mitigation Bank, Double Rock Mitigation Site
Ms. Andrea Eckardt
Wildlands Engineering, Inc.
1430 Mint Street
Suite 104
Charlotte, NC 28203
Dear Ms. Eckardt:
This letter is to inform you that the Wilmington District, Corps of Engineers (Corps)
has reviewed the as-built baseline monitoring report for the Wildlands Catawba 01
Umbrella Mitigation Bank (UMB), Double Rock mitigation site (Action ID SAW-2020-
01532), dated July 28, 2023. The Double Rock site is in the Catawba River Basin
(Hydrologic Unit Code 03050101), east of Stikeleather Rd. and north of Mt. Wesley
Church Rd., approximately six miles southwest of Taylorsville in Alexander County, NC.
In accordance with Sec. 332.8(o)(9) of the Federal Mitigation Rule, the baseline
monitoring report was provided to the North Carolina Interagency Review Team
(NCIRT) for review and comment on August 3, 2023. A site meeting was also held on
August 16, 2023, to assess the as-built site conditions. The attached minutes document
the results of the meeting. NCIRT report review comments and site meeting action
items outlined in the attached comment memo should be addressed and included in the
Year 1 monitoring report.
Pursuant to the UMB Instrument approved on July 25, 2022, and the site-specific
Double Rock Final Mitigation Plan dated June 29, 2022, 15 percent of the mitigation
site’s total restoration and enhancement credits shall be available for sale immediately
after the completion of implementation of the mitigation plan and Corps approval of the
baseline monitoring report and as-built survey. By copy of this correspondence, we
confirm that you have satisfied the above requirements for the as-built credit release,
and 669.690 stream mitigation units (SMUs) are now available for sale. With this
-2-
release, 1,444.880 SMUs (30 percent of the total restoration and enhancement credits
and 100 percent of the total preservation credits) have been released for sale.
Please note that this electronic copy provided to you via email is your official copy.
Should you wish to receive a paper copy of this correspondence, please contact us.
Thank you for your time and cooperation. If you have any questions, please contact the
Project Manager, Steve Kichefski, by email at Steven.L.Kichefski@usace.army.mil or by
phone at (828) 933-8032.
Sincerely,
Todd Tugwell
Chief, Mitigation Branch
Enclosure
cc (by email):
NCIRT Distribution List
Project Name:
Sponsor Name:
USACE Action ID:
NCDWQ Action ID:
Non-Forested
Wetland
Credits
Warm
Water
Cool
Water
Cold
Water
Riparian
Riverine
Riparian
Non-Riverine Non-Riparian Coastal
4556.1
Scheduled
Releases
Warm
Water
Cool
Water
Cold
Water
Scheduled
Releases
Riparian
Riverine
Riparian
Non-Riverine Non-Riparian Scheduled
Releases Coastal
1 (Bank/Site Establishment)1, 2 15%778.19 15%15%Dec-22 10/20/2022
2 (Year 0/As-Built)3 15%666.69 15%15%Aug-23
3 (Year 1 Monitoring)10%444.46 10%10%Mar-24
4 (Year 2 Monitoring)10%444.46 10%15%Mar-25
5 (Year 3 Monitoring)10%444.46 15%20%Mar-26
6 (Year 4 Monitoring)5%222.23 5%10%Mar-27
7 (Year 5 Monitoring)10%444.46 15%15%Mar-28
8 (Year 6 Monitoring)5%222.23 5%NA NA Mar-29
9 (Year 7 Monitoring)10%444.46 10%NA NA Mar-30
Stream Bankfull Standard4 10%444.46 NA NA NA NA NA NA Varies4
Total Credits Release to Date 4,556.10 -
Date
4 - A 10% reserve of credits to be held back until the bankfull event performance standard has been met.
Contingencies (if any): Credit Release 1 is 15% R&EII and 100% Preservation
Signature of Wilmington District Official Approving Credit Release
1 - The first credit release milestone is based on the potential credits stated in the approved mitigation plan.
2 - The first credit release shall occur upon establishment of the mitigation bank, which includes the following criteria:
1) Execution of the MBI or UMBI by the Sponsor and the USACE;
2) Approval of the final Mitigation Plan;
3) Mitigation bank site must be secured;
4) Delivery of the financial assurances described in the Mitigation Plan;
5) Recordation of the long-term protection mechanism and title opinion acceptable to the USACE;
6) 404 permit verification for construction of the site, if required.
3 - The second credit release is based on the credit totals from the as-built survey, and may differ slightly from the credit totals stated in the mitigation plan.
Current and Future Credit Releases
Credit Release Milestone
Stream Credits Forested Wetland Credits Non-Forested Wetland
Credits Projected
Release Date
Actual Release
Date
Potential Credits from As-Built Survey
SAW-2020-01532 Year Project Instituted:2022
2020-1095v1 Date Prepared:10/21/2022
Total Potential Credits
Credit Classification
Stream Credits Forested Wetland Credits
Potential Credits from Mitigation Plan
Wilmington District Mitigation Bank Credit Release Schedule
Double Rock Mitigation Site County:Alexander
Wildlands Holdings VI, LLC 8-Digit HUC:03050101
27 Sep 2023
DEPARTMENT OF THE ARMY
WILMINGTON DISTRICT, CORPS OF ENGINEERS
69 DARLINGTON AVENUE
WILMINGTON, NORTH CAROLINA 28403-1343
CESAW-RG/Kichefski September 27, 2023
MEMORANDUM FOR RECORD
SUBJECT: Action ID # SAW-2020-01532, NCIRT Review Comments on the Wildlands
Catawba 01 Umbrella Mitigation Bank, Double Rock Mitigation Site As-built & Baseline
Monitoring Report
Erin Davis/Steve Kichefski, USACE:
As-built/MY0 Report Comments –
1.Redline Drawing Sheets 2.3 and 2.5 show additional wetland and buffer planting
areas within the project conservation easement. Please include coverage of
these areas in the random plot sampling over the duration of the monitoring
period.
2.With site planting being completed after the standard IRT deadline of March 15th,
please closely monitor stem stress and mortality during the MY1 veg survey.
Assessment of supplemental planting needs is encouraged early in an effort to
avoid an extension of the monitoring period.
IRT Site Visit August 16, 2023, Wildlands Action Items –
1.Please provide updates on the Randall Tributary and Elk Shoals Creek bank
erosion repairs, including adjacent access/staging area veg cover, in the MY1
report.
2.In the MY1 report please include a status update of the presence of Murdannia
keisak onsite and any completed or planned treatments.
Steve Kichefski
Mitigation Project Manager
Mitigation Branch
MEETING MINUTES
MEETING: CATAWBA 01 UMBRELLA MITIGATION BANK – DOUBLE ROCK MITIGATION SITE
MY0 IRT Credit Release Site Walk
Catawba River Basin 03050101; Alexander County, NC
USACE Action ID No. SAW‐2020‐01532
NCDWR # 2020‐1095 v1
Wildlands Project No. W45024
DATE: Wednesday, August 16, 2023, 9:30 am
LOCATION: Stikeleather Road
Hiddenite, NC
Attendees
Kirsten Gimbert, Wildlands
Noyes Harrigan, Wildlands
Brandon Romeo, Wildlands
Erin Davis, USACE
Steven Kichefski, USACE
Maria Polizzi, NCDWR
Dave McHenry, NCWRC
Meeting Minutes
The meeting began at 9:40 am. Brandon presented an overview of the site and the order in which the group
would walk each reach. The IRT then provided general feedback on the project and indicated areas they would
like to see during the site walk. To start, the group walked to the top of Randell Tributary. After getting to the
top of Randell the group walked down stream to the confluence and then walked up to the top of Elk Shoals
Creek. Then the group walked up to the top of Stikeleather Tributary. After getting to the top of Stikeleather the
group walked back down the reach and up Matheson Tributary and ended at Matheson Tributary A by the BMP.
The meeting concluded at 12:00 PM. The following provides an overview of the discussions between Wildlands
and IRT members on the Double Rock Mitigation Site (project).
1. Opening Remarks
Erin commented about the structure material substitution (rock sills to log sills) on Stikeleather B
channel and asked whether Wildlands was concerned or took in consideration the type of materials
used since this is a steeper channel. Noyes asked if the IRT was concerned about the stability of the
logs overtime and Erin replied that they want to make sure the grade is kept and that no piping will
occur in the future, which can be a problem on steep B streams. Steve also commented on this
material substitution.
DOUBLE ROCK Mitigation Site – IRT Meeting Minutes
Wildlands Engineering, Inc. page 2
WILDLANDS CATAWBA 01 UMB – DOUBLE ROCK Mitigation Site
MY0 Credit Release IRT Site Walk
Steve commented on the planting timeline and questioned whether this may be a problem in the
future. Brandon replied that the plants looked healthy at the time of the as‐built vegetation install
and assessment and we will continue to monitor.
Erin and Steve both noted that they would like to see the repair area along Randell Tributary at
Station 211+65 and along Elk Shoals Reach 2 Station 126+55.
Maria commented on the fencing adjustment and asked why there was a shift in placement. Kirsten
replied that the original landowner had wanted the fence line further from the easement but had
passed away before the completion of the project and his son wanted to bring the pasture closer to
the easement line, so the fence location was moved. Kirsten added that large barrels were added to
the fence line at the stream crossing to help aid in keeping the cattle out of the easement.
Dave did not have any comments on the project.
2. Discussions Per Reach
Randell Tributary
Erin asked if we thought there may be an issue of scalloping in the future since the easement poles
are already shorter than the tall grass. Noyes replied that the site was walked with the landowner
after the easement signs were placed in the ground and the farmer knows where he can and cannot
mow. Wildlands will continue to monitor the site for easement encroachments.
Dave noticed some weeds growing on the sides and in some sections of the stream and asked if
anyone knew what it was. Wildlands later identified the species as Murdannia keisak or Asian
Spiderwort. Wildlands will continue to monitor these areas to make sure they do not continue to
impact the streamflow and/or stability of the channel.
The group stopped at the repair section, station 211+65, where Noyes described the bank erosion
that was occurring on the right bank just downstream of the log in the angled log riffle. He further
discussed repairs made by Wildlands Construction; laid back the banks to create a mini pool and
armored the bank with a boulder to prevent further erosion.
o Steve asked if the boulder toe was along the entire log riffle. Noyes replied that there was just
one boulder in that area armoring the bank.
o Erin responded that she is glad Wildlands was proactive with this repair and everything looks
stable.
o Dave asked if there have been any log piping issues on site. Noyes replied that there has not
been any piping issues and that the logs that were used were long and tied in well.
o The team noted that the vegetation had already grown back in the area of the repair.
Elk Shoals Creek
The group stopped at Station 126+55 to look at the repair area that eroded after construction. Steve
asked what the repair entailed. Noyes explained design concerns and that, despite the use of a rock
hammer to remove bedrock, the upstream pool depth was limited and that the excess energy led to
erosion below one of the logs in the angled log riffle just downstream of this pool. He added that the
repair involved resetting the log and armoring the section of bank to prevent any additional erosion.
Noyes also explained that this repair approach was determined to have the least impact for a repair.
o Steve asked if the construction was done internally. Noyes responded that construction was
completed by Wildlands Construction.
DOUBLE ROCK Mitigation Site – IRT Meeting Minutes
Wildlands Engineering, Inc. page 3
WILDLANDS CATAWBA 01 UMB – DOUBLE ROCK Mitigation Site
MY0 Credit Release IRT Site Walk
o Steve mentioned that the use of a rock hammer goes under the same type of permit as an
percussive activities and in the future, they will need to be notified before this type of work is
done. Wildlands commented we will notified USACE before using a rock hammer on future
projects.
o Steve mentioned that one of the logs in the repair appeared a little high, but with consistent
flow, should be good to avoid dry rot and allow for aquatic passage. Both Steve and Erin asked if
the flow and drop on Elk Shoals is normal for this channel. Noyes and Brandon replied that yes
this is the flow we have been consistently observing along this reach.
o Erin and Maria commented on the small bare area along the floodplain adjacent to the repair.
Kirsten noted that this area was constructed about a month ago and will continue to be
monitored for vegetation growth by our monitoring team.
Erin asked if the internal crossing areas are clearly marked. Kirsten replied that yes, they are and
that the site was walked with the landowner and our land acquisition team to make sure the
landowner knows where all the signs are and what he can and cannot do. Kirsten also noted if
anything comes up in the future of the project regarding adding in a culvert or ford crossing in these
locations that Wildlands will be on site with the landowner to make sure he stays outside of the
easement.
Erin asked if the culvert at the top of Elk Shoals was backwatered to allow for aquatic passage.
Noyes replied that the culverts were backwatered as far as they could and Wildlands tried to back
up water to the upstream invert to allow for complete aquatic passage through the culvert.
Maria asked if Wildlands tried to lower the Division of Transportation culvert to help aid in aquatic
passage. Noyes replied that Wildlands does not touch, change, or modify DOT culverts in any way.
Steve asked what the drainage area for Elk Shoals Creek is. Kirsten replied that the drainage area for
Elk Shoals Creek is 2.15 sq. mi. at the downstream end of project and 0.93 sq. mi. at confluence with
Stikeleather tributary.
The group discussed the use of pollinator seed mises and the benefits of including this in early
successional years. IRT was pleased to see this was implemented on Double Rock.
The group discussed the HENA conservation efforts and the IRT was pleased with the overall project
efforts to work alongside USFWS and did not have any concerns regarding special permit conditions.
Stikeleather Tributary
Steve asked if the stream was raised. Noyes replied that the stream design approach implemented
was approximately a P1.5.
Erin and Steve commented again on their concern with the replacement of rock sills with log sills
due to logs lending themselves to piping and undercutting. Noyes replied that the logs used in the
log sills were large and keyed in well to the bank and matting.
Erin asked if we WL included a vegetation plot in the priority 2 floodplain per the Mitigation plan
comments. Brandon replied that yes, Wildlands included a vegetation plot within the priority 2
floodplain, and it is vegetation plot number 3.
DOUBLE ROCK Mitigation Site – IRT Meeting Minutes
Wildlands Engineering, Inc. page 4
WILDLANDS CATAWBA 01 UMB – DOUBLE ROCK Mitigation Site
MY0 Credit Release IRT Site Walk
Matheson Tributary, Matheson Tributary A, and Matheson Tributary B
The IRT did not have any comments on the BMP or the streams within this area.
3. Closing Remarks
Erin, Steve, David, and Maria remarked that the site looked good and that they did not have any
additional questions or concerns for Wildlands at this time and will review the meeting minutes
from this site walk.
These meeting minutes were prepared by Brandon Romeo and reviewed by Kirsten Gimbert and Noyes Harrigan on August
21, 2023, and represent the authors’ interpretation of events. Please report any discrepancies or corrections within 5
business days of receipt of these minutes.