HomeMy WebLinkAbout2019-00845 Permit Non-compliance Notice.pdf U.S. ARMY CORPS OF ENGINEERS WILMINGTON DISTRICT Action Id. SAW-2019-00845 County:Wake U.S.G.S. Quad:NC-Lake Wheeler NOTIFICATION OF PERMIT NONCOMPLIANCE Responsible Party: Clayton Properties Group,Inc./Mungo Homes Attn: Brett Clark Address: 2521 Schieffelin Road,Suite 116 Apex,NC 27502 E-mail: bclarkAmungo.com Property Size(acres) —173 Nearest Town Garner Nearest Waterway UT to Swift Creek River Basin Neuse USGS HUC 03020201 Coordinates 35.693574,-78.676601 Location description: The proiect area is located on the south side of Simpkins Road,and the west side of US Highway 401 (Fayetteville Road),approximately 0.75 mile southwest from their intersection,in Garner,Wake County,North Carolina. Reference the Nationwide Permit(NWP 29)verification issued to you for the Georgia's Landing residential development, dated 6/29/2022. Description of Activity: This letter is the result of a visit to your property on 2/28/2023,where the extent of the permit non- compliance in potential waters of the US was determined.The activities of concern included the following(reference the planset included in the NWP 29 verification): 1) Impact#s 1 and 29(Sheet No./Map C): a. Rip rap bank stabilization under the bottomless arch culvert,necessary to maintain the pre-existing stream channel width under this structure,was not installed; 2) Impact#s 2,3,and 30(Sheet No./Map E): a. Rip rap bank stabilization under the bottomless arch culvert,necessary to maintain the pre-existing stream channel width under this structure,was not installed; b. Clearing and grubbing within wetland areas occurred both up-and down-stream of the culvert outside of authorized wetland impact limits; c. The stream channel has been over-widened both up-and down-stream of the culvert,outside of the authorized stream impact limits. 3) Impact#s 7,8A,8B,9,and 10(Sheet No./Map G): a. The culvert was authorized provided that the inverts of the inlet and outlet of the culvert were buried 1' below the stream bed; The inlet invert appears to be placed essentially at-grade with the stream bed.The outlet invert is perched approximately 3-4 inches above the stream bed. b. Rock check dams remain within the stream channel both up-and down-stream of the culvert,outside of the authorized stream impact limits. Applicable Law(s): ®Section 301 (Clean Water Act,33 USC 1311) ❑Section 10(Rivers and Harbors Act,33 USC 403) Enforcement Type: ❑Unauthorized Activity ®Permit Non-Compliance You are hereby notified that the above-described work is not in compliance with the Department of the Army(DA)NWP 29 verification issued to you on 6/29/2022.Any additional work in waters or wetlands in non-compliance with this permit may be considered an intentional violation of federal law. We hereby request you take the following actions to resolve this matter(see following page): Within 30 days of the date of this correspondence, a. Per items la and 2a above,install the rip rap benches within the two bottomless arch culverts according to the permitted plans,such that the pre-disturbance natural-bottom stream channel width is maintained through these structures and ties in with the undisturbed stream channels up-and down-stream of these structures.The resulting channels through the culvert are to be underlaid by natural stream bottom sediment,rather than rip rap. Ensure that all sediment and erosion control including dewatering occurs during this activity; b. Per item 2b and 2c above,propose a plan to restore natural wetland grade and contour where necessary,as well as the stream channel at pre-disturbance profile,to tie in between undisturbed stream channel segments and the channel to be re-established under the culvert per item a above.Also propose a planting plan for these wetland and stream bank areas for Corps approval using regionally appropriate native wetland and riparian vegetation,respectively.This work must be completed within 30 days of Corps approval. c. Per item 3a,propose a plan for this culvert to achieve compliance with permit conditions.Not that,in addition to not being in compliance with the permitted plans,this crossing currently does not comply with NWP General Condition 2 or Regional Condition B.9.This work must be completed within a 30 days of Corps approval. d. Per item 3b,remove all in-stream check dams,as such structures were not authorized by the Corps in their present locations. e. Please provide a status update on the dam breach(Sheet No./Map D),including timing on when the final proposed grade will be achieved and the 28-foot-wide rip rap pad will be installed. f. Please self-inspect the remaining permitted impacts and crossings of waters where no impacts were authorized on this project(see NWP 29 Special Condition 2)and provide pictures and a brief narrative of their construction status and compliance status per the authorized plans,Special Conditions,and NWP General and Regional conditions. Failure to comply with this request may result in referral of this case to the United States Attorney.Violations of the Clean Water Act can result in administrative penalties,civil penalties of up to$27,500 per day of violation,criminal fines or imprisonment. If there are any questions regarding this notification or the Corps of Engineers regulatory program,please contact David E. Bailey at (919)817-2436 or David.E.Bailey2(&usace.army.mil. Corps Regulatory Official: Date:2023.03.02 15:18:42-05'00' Date: 03/02/2023 Copies furnished by e-mail: Rick Trone,WithersRavenel,rtrone(&withersravenel.com Troy Beaseley,WithersRavenel,tbeasley(iDwithersravenel.com Zach Thomas,NCDWR,zachary.thomas&ncdenr.gov Enclosures 20230223 Compliance Notes and Pictures.pdf