Peck, Kaitlin
From:Farkas, Jim J
Sent:Friday, July 7, 2023 2:12 PM
To:Robbie Bell; rrojas@drbgroup.com
Cc:Peck, Kaitlin
Subject:RE: SWA000213; Station Pointe - Phase 1
Robbie,
I was looking over the informa?on you provided on 6/9/23. Everything looks good except for a few small issues:
Please correct the following:
- Please provided documenta?on showing that the Signing Official for the Applicant, Ric J. Rojas, is a principal
execu?ve officer of the level of vice-president or that he has the authoriza?on of someone that is a principal
execu?ve officer of the level of vice-president. This item is required per 15A NCAC 02H .1040(1)(a), 15A NCAC
02H .1043(3)(b), and Part F7 of the Applica?on. Organiza?on structures differ, so we just want to make sure that
“Division President” is comparable to a vice president (you can provide an org chart or other documenta?on
indica?ng this or a le?er from someone VP or higher authorizing Mr. Rojas to sign on their behalf). Alterna?vely,
you can have someone else (that is a principal execu?ve officer of the level of vice-president) listed as the
Applicant and sign the applica?on form.
- Applica?on Part E5 – Please revise the Total Project Area and Project Density values. The Total Project Area
value excludes the Surface Water Area (13,242 sf) from the Total Property Area (938,718 sf) and the Project
Density calcula?on is based on the Total Project Area. Please revise.
Please provide the following:
- 2x hard copies & 1x electronic copy of documenta?on that the Signing Official is at the level of VP or
higher/authoriza?on from someone of level VP or higher sta?ng that the Signing Official can sign on behalf of
the Applicant/revised Part D & Part G with someone of level VP or higher as the signing official.
- 2x hard copies & 1x electronic copy of the revised page of the Applica?on Form.
Hard copies should be mailed to me at the following address:
For FedEx/UPS:
Jim Farkas
512 N. Salisbury Street, Office 640M
Raleigh, NC 27604
For USPS:
Jim Farkas
1612 Mail Service Center
Raleigh, NC 27699-1612
Hand Delivery:
Please reach out to me prior to hand delivering a submission to make sure that I (or someone else in my group)
will be able to receive the submission. Do not leave the package in the foyer with the security guard.
NOTE: Hard copies should not be sent to a Regional Office. Doing so will delay the review process and the
submission package may be lost while being sent from the Regional Office to me in the Central Office.
Electronic copies should be uploaded at the following loca?on:
1
h?ps://edocs.deq.nc.gov/Forms/SW-Supplemental-Upload
Since these are really minor things, once I get the hard copies, anything else that may have changed from addressing
these issues, and the documents are uploaded to Laserfiche (Provided everything is s?ll in order), we can issue the
permit without doing another formal review.
Let me know if you have any ques?ons.
Jim Farkas
State Stormwater Engineer
North Carolina Department of Environmental Quality
Office: (919) 707-3646
Jim.farkas@deq.nc.gov
From: Peck, Kaitlin <kaitlin.peck@deq.nc.gov>
Sent: Thursday, June 29, 2023 3:57 PM
To: Robbie Bell <Robbie.Bell@bnkinc.com>; rrojas@drbgroup.com
Cc: Farkas, Jim J <Jim.Farkas@deq.nc.gov>; Joyner, Melissa <melissa.joyner@deq.nc.gov>
Subject: RE: SWA000213; Station Pointe Phase 1 (Harnett)
**Correc?on*
We received your post-construc?on stormwater Authoriza?on to Construct (ATC) permit applica?on for the subject
project on 6/9/2023. Reviews under the Fast-Track permi?ng process can take up to 30 calendar days to complete. You
can see where this project stands in the review queue by emailing Jim Farkas (He has an autoreply set up that has the
review queue on it). Please upload all documents that you mailed into our office through the link provided below. Be
sure to choose the Central Office as the Primary Contact office.
h?ps://edocs.deq.nc.gov/Forms/SW-Supplemental-Upload
IMPORTANT NOTE: Please ensure that each file is uploaded under its appropriate file type. Addi?onal file types can be
entered into the electronic form by clicking on the “Add Another Post-Construc?on File Upload” link directly below the
“State Stormwater Informa?on Uploads” sec?on of the form. YOU MUST CLICK ON THE “ADD ANOTHER POST-
CONSTRUCTION FILE UPLOAD” TO ADD ADDITIONAL FILE TYPES TO THE SUBMISSION. Merely changing the file type
dropdown as you upload the various files (without adding addi?onal file uploads) will upload all of the files as the last
file type selected, the submission will get flagged during review, and you will need to resubmit the files. Please do not
upload en?re plan sets through this form, but rather upload the relevant individual sheets under the appropriate file
type. Selec?ng the correct file type ensures that the files are properly named in the electronic repository and it helps
expedite the review process. NOTE: We do not require and we discourage the upload/submission of extraneous plan
sheets (such as ligh?ng plans, u?lity plans, striping plans, sight distance plans, etc…) as these files are not needed for
review.
2
Please type in permit #: SWA000213
This project will be reviewed by Jim Farkas, if you have any ques?ons, please contact them at jim.farkas@deq.nc.gov or
at 919-707-3646.
Thank you,
Kaitlin Peck
Environmental Specialist
North Carolina Department of Environmental Quality
Office: (919) 707-9209
Kaitlin.peck@deq.nc.gov
From: Peck, Kaitlin
Sent: Thursday, June 29, 2023 3:53 PM
To: Robbie Bell <Robbie.Bell@bnkinc.com>; rrojas@drbgroup.com
Cc: Farkas, Jim J <Jim.Farkas@deq.nc.gov>; Joyner, Melissa <melissa.joyner@deq.nc.gov>
Subject: SWA000213; Station Pointe Phase 1 (Harnett)
Good A?ernoon,
We received your post-construc?on stormwater Authoriza?on to Construct (ATC) permit applica?on for the subject
project on 6/29/2023. Reviews under the Fast-Track permi?ng process can take up to 30 calendar days to complete.
You can see where this project stands in the review queue by emailing Jim Farkas (He has an autoreply set up that has
the review queue on it). Please upload all documents that you mailed into our office through the link provided
below. Be sure to choose the Central Office as the Primary Contact office.
h?ps://edocs.deq.nc.gov/Forms/SW-Supplemental-Upload
IMPORTANT NOTE: Please ensure that each file is uploaded under its appropriate file type. Addi?onal file types can be
entered into the electronic form by clicking on the “Add Another Post-Construc?on File Upload” link directly below the
“State Stormwater Informa?on Uploads” sec?on of the form. YOU MUST CLICK ON THE “ADD ANOTHER POST-
CONSTRUCTION FILE UPLOAD” TO ADD ADDITIONAL FILE TYPES TO THE SUBMISSION. Merely changing the file type
dropdown as you upload the various files (without adding addi?onal file uploads) will upload all of the files as the last
file type selected, the submission will get flagged during review, and you will need to resubmit the files. Please do not
upload en?re plan sets through this form, but rather upload the relevant individual sheets under the appropriate file
type. Selec?ng the correct file type ensures that the files are properly named in the electronic repository and it helps
expedite the review process. NOTE: We do not require and we discourage the upload/submission of extraneous plan
3
sheets (such as ligh?ng plans, u?lity plans, striping plans, sight distance plans, etc…) as these files are not needed for
review.
Please type in permit #: SWA000213
This project will be reviewed by Jim Farkas, if you have any ques?ons, please contact them at jim.farkas@deq.nc.gov or
at 919-707-3646.
Thank you,
Kaitlin Peck
Environmental Specialist
North Carolina Department of Environmental Quality
Office: (919) 707-9209
Kaitlin.peck@deq.nc.gov
From: Robbie Bell <Robbie.Bell@bnkinc.com>
Sent: Thursday, June 8, 2023 9:08 AM
To: Peck, Kaitlin <kaitlin.peck@deq.nc.gov>; rrojas@drbgroup.com
Cc: Farkas, Jim J <Jim.Farkas@deq.nc.gov>; Joyner, Melissa <melissa.joyner@deq.nc.gov>
Subject: \[External\] RE: Station Pointe Phase 1; Angier, Harnett County
CAUTION: External email. Do not click links or open attachments unless verified. Report suspicious emails with the Report Message
button located on your Outlook menu bar on the Home tab.
Kaitlin,
I see what you are talking about. We do show leader lines over to the wetland areas but they are not defined in detail
and especially the wetland areas that will be recorded with phase 1 and protected.
Will send out today.
Thanks,
Kirby R (Robbie) Bell, Jr. PE, CPESC
robbie.bell @bnkinc.com
P: 919.851.4422
D: 919.645.3540
4
Bass, Nixon & Kennedy, Inc.
6310 Chapel Hill Road, Suite 250
Raleigh, NC 27607
bnkinc.com
Serving the Triangle and surrounding areas since 1969
From: Peck, Kaitlin <kaitlin.peck@deq.nc.gov>
Sent: Wednesday, June 07, 2023 4:04 PM
To: rrojas@drbgroup.com; Robbie Bell <robbie.bell@BNKInc.com>
Cc: Farkas, Jim J <Jim.Farkas@deq.nc.gov>; Joyner, Melissa <melissa.joyner@deq.nc.gov>
Subject: Station Pointe Phase 1; Angier, Harnett County
Good A?ernoon,
I hope you are doing well.
We received your application for a new Fast-Track post-construction stormwater permit on 5/30/23 At this time, the
submission is not administratively complete and cannot be accepted for review in its current condition. Please provide
the following submittal items within 30 calendar days (by close of business on 7/7/23) so that we may accept the project
and begin the review process, otherwise, the project will be returned as administratively incomplete.
2x original hard copies and 1x electronic copy of a site plan corrected to depict wetlands on the project site.
Currently it states that wetlands are present on site, but their locations are not indicated. This item is required
per 15A NCAC 02H .1043(3)(f) and per Section F, 4 of the Application.
NOTE: This is an administrative completeness review, not a detailed engineering review, there may be other issues that
may be brough up during the engineering review.
If these items are received within the stipulated timeframe, we can accept the project and begin the review process.
Once accepted, reviews under the Fast-Track permitting process can take up to 30 calendar days per statute.
Hard copies should be mailed to the following address:
For FedEx/UPS:
Jim Farkas
512 N. Salisbury Street, Office 640E
Raleigh, NC 27604
For USPS:
Jim Farkas
5
1612 Mail Service Center
Raleigh, NC 27699-1612
If you have any ques?ons, please contact Kaitlin Peck at Kaitlin.peck@deq.nc.gov or at (919) 707-9209.
Thank you,
Kaitlin Peck
Environmental Specialist
North Carolina Department of Environmental Quality
Office: (919) 707-9209
Kaitlin.peck@deq.nc.gov