HomeMy WebLinkAboutNCC232415_ESC Approval Submitted_20230816 (71.,ROY COOPERGovernor ELIZABETH S.BISER Secretary wok,,
DOUGLAS R.ANSEL NORTH CAROLINA
Interim Director Environmental Quality
March 6, 2023
LETTER OF APPROVAL WITH MODIFICATIONS
Mecklenburg County
Attention: Leslie Johnson, Assistant County Manager
600 East 4th Street, 11 th Floor
Charlotte,North Carolina 28208
RE: Project Name: West Branch Rock River Rehabilitation and WQ Project
Project ID: MECKL-2020-083
Acres Approved: 56.0
County: Mecklenburg
City: Davidson
Location: Grey Road
River Basin: Yadkin-Pee Dee
Stream Classification: Other
Submitted By: Kimley Horn&Associates, Inc.
Date Received by LQS: February 27, 2023
Plan Type: Revised
Dear Mr. Johnson:
This office has reviewed the subject erosion and sedimentation control plan. We find the plan to be
acceptable with modifications and hereby issue this letter of Approval with Modifications. The
Modifications Required for Approval are listed on the attached page. This plan approval shall expire three
(3)years following the date of approval, if no land-disturbing activity has been undertaken, as is required
by Title 15A NCAC 4B .0129.
As of April 1, 2019, all new construction activities are required to complete and submit an electronic
Notice of Intent(eNOI) form requesting a Certificate of Coverage (COC)under the NCG010000
Construction General Permit. After the form is reviewed and found to be complete,you will receive a link
with payment instructions for the $100 annual permit fee. After the fee is processed,you will receive the
COC via email. As the Financially Responsible Party shown on the FRO form submitted for this project,
you MUST obtain the COC prior to commencement of any land disturbing activity. The eNOI form may
be accessed at deq.nc.gov/NCG01. Please direct questions about the eNO1 form to the Stormwater
Program staff in the Raleigh central office. If the owner/operator of this project changes in the future,the
new responsible party must obtain a new COC.
Title 15A NCAC 4B .0118(a) and the NCG01 permit require that the following documentation be kept on
file at the job site:
1. The approved E&SC plan as well as any approved deviation.
D E Q North Carolina Department of Environmental Quality I Division of Energy,Mineral,and Land Resources
Mooresville Regional Office 1610 East Center Avenue,Suite 301 I Mooresville,North Carolina 28115
tinellet\ 704-663-1699
Letter of Approval with Modifications
Mecklenburg County
March 6, 2023
Page 2 of 3
2. The NCG01 permit and the COC, once it is received.
3. Records of inspections made during the previous 30 days.
Also, this letter gives the notice required by G.S. 113A-61.1(a) of our right of periodic inspection to
ensure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Act is performance-oriented, requiring protection of
existing natural resources and adjoining properties. If, following the commencement of this project, it is
determined that the erosion and sedimentation control plan is inadequate to meet the requirements of the
Sedimentation Pollution Control Act of 1973 (North Carolina General Statute 113A-51 through 66), this
office may require revisions to the plan and implementation of the revisions to ensure compliance with the
Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and State water
quality laws,regulations, and rules. In addition, local city or county ordinances or rules may also apply to
this land-disturbing activity. This approval does not supersede any other permit or approval.
Please note that this approval is based in part on the accuracy of the information provided in the Financial
Responsibility Form, which you provided. You are requested to file an amended form if there is any
change in the information included on the form. In addition, it would be helpful if you notify this office of
the proposed starting date for this project.
Your cooperation is appreciated.
Sincerely,
George Adams
George D Adams
Assistant Regional Engineer
Land Quality Section
GDA/cys
Enclosure: Certificate of Approval
Modifications Required for Approval
NCGO1 Fact Sheet
c: Inspection Department
Kimley-Horn Project Manager
Attention: Jason Claudio-Diaz, PE, CFM
200 South Tryon, Suite 200
Charlotte,North Carolina 28202
�� ��➢ North Carolina Department of Environmental Quality Division of Energy,Mineral,and Land Resources
•;��j Mooresville Regional Office 1610 East Center Avenue,Suite 301 I Mooresville,North Carolina 28115
704-663-1699
Letter of Approval with Modifications
Mecklenburg County
March 6, 2023
Page 3 of 3
MODIFICATIONS REQUIRED FOR APPROVAL
Project Name: West Branch Rock River Rehabilitation and WQ Project
Project ID: MECKL-2020-083
County: Mecklenburg
Reviewed by: George D. Adams
1. This approval applies to the revised plan received on February 27, 2023. All previous approvals and
modifications may still be applicable.
2. Additional measures may be required- The applicant is responsible for the control of sediment on-site. If
the approved erosion and sedimentation control measures prove insufficient, the applicant must take
those additional steps necessary to stop sediment from leaving this site. [15A NCAC 4B .0115]
North Carolina Department of Environmental Quality Division of Energy,Mineral,and Land Resources
Mooresville Regional Office 1610 East Center Avenue,Suite 301 I Mooresville,North Carolina 28115