HomeMy WebLinkAboutExternal_ Nationwide Permit 12 verification - Revised Site 11_ Piedmont Natural Gas_ Line 142 Natural Gas Pipeline_ Wake and Johnston Counties_ SAW-2021-01288From: Bailey, David E CIV USARMY CESAW (USA)
To: Morris, Tom E.
Cc: DePalma. Alicia Knowles; John Farmer; Thomas, Zachary T; Keith Gualtieri; Camden Brunick; Isenhour. Kimberly
T CIV USARMY CESAW (USA)
Subject: [External] Nationwide Permit 12 verification - Revised Site 11: Piedmont Natural Gas, Line 142 Natural Gas
Pipeline, Wake and Johnston Counties; SAW-2021-01288
Date: Monday, March 13, 2023 8:13:55 AM
Attachments: 2021-01288 NWP 12 Tearsheet - Revised.odf
2021NWP12.odf
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an
attachment to Report Spam.
up
Please see the attached Nationwide Permit 12 verification, including Special Conditions and terms
and conditions, revised for Site 11 of the above referenced project. Importantly, this verification
includes a Compensatory Mitigation requirement.
Note that hard copies of the attached documents will not be distributed unless specifically
requested. Please let me know if you have any questions.
Sincerely,
Dave Bailey
David E. Bailey, PWS
Regulatory Project Manager
US Army Corps of Engineers
CE-SAW-RG-R
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
Mobile: (919) 817-2436
Email: David. E.Bailey2Pusace.army.mil
We would appreciate your feedback on how we are performing our duties. Our automated
Customer Service Survey is located at: https://re.gulatory.ops.usace.army.mil/customer-service-
s u rve
Thank you for taking the time to visit this site and complete the survey.
From: John Farmer <John.Farmer@eli-Ilc.com>
Sent: Thursday, January 19, 2023 4:20 PM
To: Bailey, David E CIV USARMY CESAW (USA) <David.E.Bailey2@usace.army.mil>; Thomas, Zachary
T <zachary.thomas@ncdenr.gov>
Cc: DePalma, Alicia Knowles <Alicia.DePalma@duke-energy.com>; Morris, Tom E.
<Tom.Morris2@duke-energy.com>; Keith Gualtieri <Keith.Gualtieri@eli-Ilc.com>
Subject: [Non-DoD Source] PNG- Line 142 Streambank Stabilization Revision; Johnston County, NC
January 19, 2023
David E. Bailey, PWS Zach Thomas
Regulatory Project Manager
US Army Corps of Engineers
CE-SAW-RG-R
3331 Heritage Trade Drive, Suite 105
Wake Forest, NC 27587
919.817.2436
DdVIU.t.ra
Environmental Program Consultant
NCDEQ-Division of Water Resources
1628 Mail Center
Raleigh, NC 27699-1628
919.791.4255
zachary.thomasna ncdenr.gov
RE: PRE -CONSTRUCTION NOTIFICATION (PCN)
PNG- LINE 142 MOD & STREAMBANK STABILIZATION
JOHNSTON COUNTY, NORTH CAROLINA
Gentlemen:
On December 13, 2022, Piedmont Natural Gas (PNG) submitted a Pre -Construction Notification
(PCN) for modification to the Line 142 natural gas project. The modification consisted of (1) a change
from horizontal directional drill (HDD) to open -cut trenching due to geological constraints on
construction between Station 189+00 and Station 209+00 and (2) streambank stabilization along a
50-ft stretch of Beddingfield Creek which parallels and flows north of the natural gas easement east
of Shotwell Road.
On January 12, 2023, PNG received provisional approval from USACE via email for the modification
to the project as described above.
Since that time, the streambank stabilization grading has been refined to ensure that no fill is placed
in the floodplain associated with Beddingfield Creek. Attached is the revised plan sheet indicating
the proposed stabilization through the laying back of the existing streambank on a 1.25:1 slope and
then stabilizing with Flexamat. This streambank stabilization does not change the wetland and
stream impact tables submitted in the modification on December 13, 2022.
If you have any questions, please contact me at your convenience.
Sincerely,
John L. Farmer, PE, CPESC, TN QHP
Energy Land & Infrastructure, LLC (PLLC in NC)
745 South Church Street, Suite 801
Murfreesboro, TN 37130
(615) 383-6300 Office
iohn.farmerna eli-Ilc.com