HomeMy WebLinkAbout_External_ RE_ PNG Line 142 Project (SAW-2021-01288 & DWR 20210364) Bi-weekly Status UpdateFrom:
Bailey, David E CIV USARMY CESAW (USA)
To:
DePalma. Alicia; Thomas, Zachary T
Cc:
Morris, Tom E.; Tripp. Brad
Subject:
[External] RE: PNG Line 142 Project (SAW-2021-01288 & DWR 20210364) Bi-weekly Status Update
Date:
Wednesday, July 12, 2023 12:19:47 PM
CAUTION: External email. Do not click links or open attachments unless verified. Report suspicious emails with the
Report Message button located on your Outlook menu bar on the Home tab.
Thanks Alicia! I greatly appreciate your diligence in sending the reports and providing updates of
project status. You have our approval to discontinue sending monitoring reports to the Corps. We
consider Special Condition 4 of the NWP 12 verification dated 7/11/2022, and Special Condition 5 of
the NWP 12/13 verification dated 3/13/2023, to be in compliance for this project. If, however, issues
arise with activities involving aquatic resources on this project please keep us in the loop.
Sincerely,
Dave Bailey
David E. Bailey, PWS
Regulatory Project Manager
US Army Corps of Engineers
CE-SAW-RG-R
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
Mobile: (919) 817-2436
Email: David. E.Bailey2Pusace.army.mil
We would appreciate your feedback on how we are performing our duties. Our automated
Customer Service Survey is located at: https://regulatory.ops.usace.army.mil/customer-service-
s u rve
Thank you for taking the time to visit this site and complete the survey.
From: DePalma, Alicia <Alicia.DePalma@duke-energy.com>
Sent: Tuesday, July 11, 2023 4:14 PM
To: Bailey, David E CIV USARMY CESAW (USA) <David.E.Bailey2@usace.army.mil>; Thomas, Zachary
T <zachary.thomas@ncdenr.gov>
Cc: Morris, Tom E. <Tom.Morris2@duke-energy.com>; Tripp, Brad <Brad.Tripp@duke-energy.com>
Subject: [Non-DoD Source] RE: PNG Line 142 Project (SAW-2021-01288 & DWR 20210364) Bi-weekly
Status Update
Good afternoon,
Please find the bi-weekly status report for the subject project attached. Note, all wetland and stream
crossings have been completed and the overall project construction is about 95% complete. Then
we'll have to wait for the permanent vegetation to get established to gain approval from DEMLR to
remove ESC measures which may take several months. Would you like to continue to receive the bi-
weekly reports?
From: De Palma, Alicia
Sent: Tuesday, June 27, 2023 2:02 PM
To: David.E.Bailey2na usace.army.mil; Thomas, Zachary T <zachary.thomasna ncdenr.gov>
Cc: Morris, Tom E. <Tom.Morris2Pduke-energv.com>; Tripp, Brad <Brad.TriWW duke-energv.com>
Subject: RE: PNG Line 142 Project (SAW-2021-01288 & DWR 20210364) Bi-weekly Status Update
Good afternoon,
Please find the bi-weekly status report for the subject project attached.
From: De Palma, Alicia
Sent: Tuesday, June 13, 2023 3:22 PM
To: David.E.Bailey2na usace.army.mil; Thomas, Zachary T <zachary.thomas(CDncdenr.gov>
Cc: Morris, Tom E.<Tom.Morris2(cDduke-energv.com>; Tripp, Brad <Brad.Tripp(cDduke-ener.Qv.com>
Subject: RE: PNG Line 142 Project (SAW-2021-01288 & DWR 20210364) Bi-weekly Status Update
Good afternoon,
Please find the bi-weekly status report for the subject project attached. Note, the pipe shown above
ground, spanning S-10 and S-11 in the photos is HDD pipe stringing for the Shotwell Rd HDD.
From: De Palma, Alicia
Sent: Tuesday, May 30, 2023 12:47 PM
To:'David.E.Bailey2@usace.army.mil' <David.E.BaileyMDusace.army.mil>;'Thomas, Zachary T'
<zachary.thomas(cDncdenr.gov>
Cc: Morris, Tom E. <Tom.Morris2Pduke-energv.com>; Tripp, Brad <Brad.TriWW duke-energv.com>
Subject: RE: PNG Line 142 Project (SAW-2021-01288 & DWR 20210364) Bi-weekly Status Update
Good afternoon,
Please find the bi-weekly status report for the subject project attached.
From: De Palma, Alicia
Sent: Tuesday, May 16, 2023 1:18 PM
To: David.E.Bailey2Pusace.army.mil; Thomas, Zachary T <zachary.thomas(CDncdenr.gov>
Cc: Morris, Tom E.<Tom.Morris2(cDduke-energv.com>; Tripp, Brad <Brad.TriWW(c duke-energv.com>
Subject: RE: PNG Line 142 Project (SAW-2021-01288 & DWR 20210364) Bi-weekly Status Update
Good afternoon,
Please find the bi-weekly status report for the subject project attached.
From: DePalma, Alicia
Sent: Tuesday, May 2, 2023 2:23 PM
To:'David.E.Bailey2@usace.army.mil' <David.E.Bailey2Pusace.army.mil>;'Thomas, ZacharyT'
<zachary.thomas(@ncdenr.gov>
Cc: Morris, Tom E. <Tom.Morris2Pduke-energv.com>; Tripp, Brad <Brad.Tripp(a duke-energv.com>;
'Parham, Michael A' <Michael.Parhamna duke-energv.com>
Subject: RE: PNG Line 142 Project (SAW-2021-01288 & DWR 20210364) Bi-weekly Status Update
Good afternoon,
Please find the bi-weekly status report for the subject project attached.
Alicia DePalma
Environmental Siting, Licensing & Permitting Support
4720 Piedmont Row Drive
Charlotte, NC 28210
(704) 763-9311
alicia.depalmana duke-energv.com
From: DePalma, Alicia
Sent: Tuesday, April 18, 2023 1:43 PM
To:'David.E.Bailey2@usace.army.mil' <David.E.Bailey2Pusace.army.mil>;'Thomas, ZacharyT'
<zachary.thomas(@ncdenr..Qov>
Cc: Morris, Tom E. <Tom.Morris2(@duke-energv.com>; Tripp, Brad <Brad.Tripp(a duke-energv.com>;
'Parham, Michael A' <Michael.Parham(cDduke-energv.com>
Subject: RE: PNG Line 142 Project (SAW-2021-01288 & DWR 20210364) Bi-weekly Status Update
Good afternoon,
Please find the bi-weekly status report for the subject project attached.
Alicia DePalma
Environmental Siting, Licensing & Permitting Support
4720 Piedmont Row Drive
Charlotte, NC 28210
(704) 763-9311
aIicia.depaImana duke-energv.com
From: DePalma, Alicia
Sent: Tuesday, April 4, 2023 10:38 AM
To: David.E.Bailey2na usace.army.mil; Thomas, Zachary T <zachary.thomas(CDncdenr.gov>
Cc: Morris, Tom E. <Tom.Morris2(@duke-energv.com>; Tripp, Brad <Brad.Tripp(a duke-energv.com>;
'Parham, Michael A' <Michael.Parhamna duke-energv.com>
Subject: RE: PNG Line 142 Project (SAW-2021-01288 & DWR 20210364) Bi-weekly Status Update
Good morning,
Please find the bi-weekly status report for the subject project attached.
Have a great day.
Alicia DePalma
Environmental Siting, Licensing & Permitting Support
4720 Piedmont Row Drive
Charlotte, NC 28210
(704) 763-9311
alicia.depalmana duke-energv.com
From: DePalma, Alicia
Sent: Tuesday, March 21, 2023 1:43 PM
To:'David.E.Bailey2@usace.army.mil' <David.E.Bailey2Pusace.army.mil>;'Thomas, ZacharyT'
<zachary.thomas(@ncdenr..Qov>
Cc: Morris, Tom E. <Tom.Morris2(@duke-energv.com>; Tripp, Brad <Brad.Tripp(a duke-energv.com>;
Parham, Michael A <Michael.Parham(cDduke-energv.com>
Subject: RE: PNG Line 142 Project (SAW-2021-01288 & DWR 20210364) Bi-weekly Status Update
Good afternoon,
Please find the bi-weekly status report for the subject project attached.
For the Shotwell Road HDD modification and Streambank Stabilization work, we should now have all
necessary environmental permits acquired. We submitted the 404 and 401 approvals to DEMLR for
their records per the condition of their ESC modification approval and we received a floodplain
permit from the Town of Clayton for the stream stabilization.
Thank you.
Alicia DePalma
Environmental Siting, Licensing & Permitting Support
4720 Piedmont Row Drive
Charlotte, NC 28210
(704) 763-9311
alicia.depalmana duke-energv.com
From: DePalma, Alicia
Sent: Tuesday, March 7, 2023 1:59 PM
To: David.E.Bailey2na usace.army.mil; Thomas, Zachary T <zachary.thomas(CDncdenr.gov>
Cc: Morris, Tom E. <Tom.Morris2(@duke-energv.com>; Tripp, Brad <Brad.Tripp(a duke-energv.com>;
Parham, Michael A <Michael.Parhamna duke-energv.com>
Subject: RE: PNG Line 142 Project (SAW-2021-01288 & DWR 20210364) Bi-weekly Status Update
Good afternoon,
Please find the bi-weekly status report for the subject project attached.
Zach- Can you provide a status update of where the modification we submitted for this project
stands in your queue at this point? Any update that we can provide to our senior management
would be helpful.
Thank you.
From: DePalma, Alicia
Sent: Tuesday, February 21, 2023 1:15 PM
To: David.E.Bailey2Pusace.army.mil; Thomas, Zachary T <zachary.thomas(CDncdenr..Qov>
Cc: Morris, Tom E. <Tom.Morris2(@duke-energv.com>; Tripp, Brad <Brad.Tripp(a duke-energv.com>;
Parham, Michael A <Michael.Parham(cDduke-energv.com>
Subject: RE: PNG Line 142 Project (SAW-2021-01288 & DWR 20210364) Bi-weekly Status Update
Attached is the bi-weekly status report for the subject project.
Alicia DePalma
Environmental Siting, Licensing & Permitting Support
4720 Piedmont Row Drive
Charlotte, NC 28210
(704) 763-9311
alicia.depalmaPcluke-energv.com
From: DePalma, Alicia
Sent: Tuesday, February 7, 2023 3:01 PM
To: David. E.Bailey2@usace.army.miI; Thomas, Zachary T <zachary.thomas@ncdenr.gov>
Cc: Morris, Tom E. <Tom.Morris2(cDduke-energv.com>; Tripp, Brad <Brad.Trippna duke-energv.com>;
Parham, Michael A <Michael.Parhamna duke-energv.com>
Subject: RE: PNG Line 142 Project (SAW-2021-01288 & DWR 20210364) Bi-weekly Status Update
Good afternoon,
Attached is the bi-weekly status report for the subject project.
Alicia DePalma
Environmental Siting, Licensing & Permitting Support
4720 Piedmont Row Drive
Charlotte, NC 28210
(704) 763-9311
alicia.depalmana duke-energv.com
From: DePalma, Alicia
Sent: Tuesday, January 24, 2023 2:29 PM
To:'David.E.Bailey2@usace.army.mil' <David.E.Bailey2(@usace.army.mil>;'Thomas, ZacharyT'
<zachary.thomasna ncdenr.gov>
Cc: Morris, Tom E. <Tom.Morris2Pduke-energv.com>; Tripp, Brad <Brad.Trippna duke-energv.com>;
Parham, Michael A <Michael.Parhamna duke-energv.com>
Subject: RE: PNG Line 142 Project (SAW-2021-01288 & DWR 20210364) Bi-weekly Status Update
Good afternoon,
Attached is the bi-weekly status report for the subject project.
Mr. Thomas,
Please let us know if you have any questions or if you need anything further from our team on our
proposed Line 142 modification and streambank stabilization PCN submittal from 12/13/2022. As
you can see from the attached bi-weekly report, this project is actively in construction so it would be
ideal to receive all our necessary approvals for the project modifications without having to
demobilize and remobilize resulting in less impact on property owners. Again, let us know if there is
anything we can do to help with your review.
Thank you.
Alicia DePalma
Environmental Siting, Licensing & Permitting Support
4720 Piedmont Row Drive
Charlotte, NC 28210
(704) 763-9311
alicia.depalmana duke-energv.com
From: DePalma, Alicia
Sent: Tuesday, January 10, 2023 1:52 PM
To:'David.E.Bailey2@usace.army.mil' <David.E.Bailey2Pusace.army.mil>;'Thomas, Zachary T'
<zachary.thomas(@ncdenr.gov>
Cc: Morris, Tom E. <Tom.Morris2Pduke-energv.com>; Tripp, Brad <Brad.Tripp(a duke-energv.com>;
Parham, Michael A <Michael.Parhamna duke-energv.com>
Subject: RE: PNG Line 142 Project (SAW-2021-01288 & DWR 20210364) Bi-weekly Status Update
Happy New Year!
Attached is the bi-weekly status report for the subject project.
Also, a PCN was submitted mid- December for the proposed Line 142 modification and streambank
stabilization; please let us know the status and if you have any questions.
Thank you.
Alicia DePalma
Environmental Siting, Licensing & Permitting Support
4720 Piedmont Row Drive
Charlotte, NC 28210
(704) 763-9311
alicia.depalmana duke-energv.com
From: DePalma, Alicia
Sent: Thursday, December 22, 2022 9:27 AM
To: David.E.Bailey2(cDusace.army.mil; Thomas, Zachary T <zachary.thomas(CDncdenr..Qov>
Cc: Morris, Tom E. <Tom.Morris2Pduke-energv.com>; Tripp, Brad <Brad.TriQQ(a duke-energv.com>;
Parham, Michael A <Michael.Parham(cDduke-energv.com>
Subject: RE: PNG Line 142 Project (SAW-2021-01288 & DWR 20210364) Bi-weekly Status Update
Good morning,
I will be out of the office next week, so please find the status report for the subject project attached.
From: DePalma, Alicia
Sent: Tuesday, December 13, 2022 2:26 PM
To: David.E.Bailey2Pusace.army.mil; Thomas, Zachary T <zachary.thomas(CDncdenr.gov>
Cc: Morris, Tom E. <Tom.Morris2(@duke-energv.com>; Tripp, Brad <Brad.Tripp(a duke-energv.com>;
Parham, Michael A <Michael.Parham(cDduke-energv.com>
Subject: RE: PNG Line 142 Project (SAW-2021-01288 & DWR 20210364) Bi-weekly Status Update
Attached is the most recent bi-weekly status report for the subject project.
Additionally, attached are photos of the stream bank requiring stabilization. My understanding is
that the submar mat would only be applied to the stream bank and not applied within the stream
channel.
Lastly, the PCN was submitted today for the proposed modifications and the stream bank
stabilization. Please let us know if you have any questions.
From: DePalma, Alicia
Sent: Tuesday, November 29, 2022 10:44 AM
To:'David.E.Bailey2@usace.army.mil' <David.E.Bailey2Pusace.army.mil>;'Thomas, ZacharyT'
<zachary.thomasna ncdenr.gov>
Cc: Morris, Tom E. <Tom.Morris2Pduke-energv.com>; Tripp, Brad <Brad.Trippna duke-energv.com>;
Parham, Michael A <Michael.Parhamna duke-energv.com>
Subject: RE: PNG Line 142 Project (SAW-2021-01288 & DWR 20210364) Bi-weekly Status Update
Good morning,
I hope everyone had a wonderful Thanksgiving. Please find the attached bi-weekly report for the
subject project which includes photos of stream crossings where pipeline installation has been
completed.
Additionally, I sent the attached email on November 18th regarding our proposed project
modifications in addition to a small proposed streambank restoration effort. Please advise on the
preferred method for submitting a modification to the existing permits and authorizations- whether
to resubmit the PCN application or provide the necessary documents via email to each office (Corps
and DWR). Also, with the proposed streambank restoration work to be completed under non -
reporting Nationwide Permit 13- Bank Stabilization, are there any written approvals required from
DWR?
Let me know if you'd like me to set up a Teams Meeting or call to discuss further.
Alicia DePalma
Environmental Siting, Licensing & Permitting Support
4720 Piedmont Row Drive
Charlotte, NC 28210
(704) 763-9311
alicia.depalmana duke-energv.com
From: DePalma, Alicia
Sent: Tuesday, November 15, 2022 11:31 AM
To: David.E.Bailey2Pusace.army.mil; Thomas, Zachary T <zachary.thomas(CDncdenr..Qov>
Cc: Morris, Tom E.<Tom.Morris2(@duke-energ_v.com>; Tripp, Brad <Brad.Tripp(a duke-energ_v.com>;
Parham, Michael A <Michael.Parham(cDduke-energv.com>
Subject: RE: PNG Line 142 Project (SAW-2021-01288 & DWR 20210364) Bi-weekly Status Update
On behalf of Piedmont Natural Gas, please find the attached bi-weekly report for the subject project.
Alicia DePalma
Environmental Siting, Licensing & Permitting Support
4720 Piedmont Row Drive
Charlotte, NC 28210
(704) 763-9311
alicia.depalmaPcluke-energ_v.com
From: DePalma, Alicia
Sent: Tuesday, November 1, 2022 10:39 AM
To: 'Cohn, Colleen M'<colleen.cohn(@ncdenr.gov>;'David.E.Bailey2@usace.army.miI'
<David.E.Bailey2(cDusace.army.mil>
Cc: Morris, Tom E. <Tom.Morris2Pduke-energ_v.com>; Tripp, Brad <Brad.Tripp(a duke-energ_v.com>;
Parham, Michael A <Michael.Parham(cDduke-energ_v.com>
Subject: RE: PNG Line 142 Project (SAW-2021-01288 & DWR 20210364) Bi-weekly Status Update
On behalf of Piedmont Natural Gas, please find the attached bi-weekly report for the subject project.
As mentioned in my email last Thursday, the project team will be reevaluating designs for the
Shotwell Road HDD while the remaining sections of the project will continue. We'll continue to notify
your offices accordingly as additional information is available.
Alicia DePalma
Environmental Siting, Licensing & Permitting Support
4720 Piedmont Row Drive
Charlotte, NC 28210
(704) 763-9311
alicia.depalmaPcluke-energ_v.com
From: DePalma, Alicia
Sent: Tuesday, October 18, 2022 12:22 PM
To: Cohn, Colleen M <colleen.cohn(@ncdenr.gov>; David. E.Bailey2(@usace.army.miI
Cc: Morris, Tom E. <Tom.Morris2Pduke-energ_v.com>; Tripp, Brad <Brad.TriQQ(a duke-energ_v.com>;
Parham, Michael A <Michael.ParhamPduke-energ_v.com>
Subject: RE: PNG Line 142 Project (SAW-2021-01288 & DWR 20210364) Bi-weekly Status Update
On behalf of Piedmont Natural Gas, please find the attached bi-weekly report for the subject project.
From: DePalma, Alicia
Sent: Tuesday, October 4, 2022 1:01 PM
To: Cohn, Colleen M <colleen.cohnna ncdenr.gov>; David. E.Bailey2(@usace.army.miI
Cc: Morris, Tom E. <Tom.Morris2Pduke-energv.com>; Tripp, Brad <Brad.TriQQ(a duke-energv.com>;
Parham, Michael A <Michael.Parhamna duke-energv.com>
Subject: RE: PNG Line 142 Project (SAW-2021-01288 & DWR 20210364) Bi-weekly Status Update
On behalf of Piedmont Natural Gas, please find the attached bi-weekly report for the subject project.
From: DePalma, Alicia
Sent: Tuesday, September 20, 2022 10:57 AM
To: Cohn, Colleen M <colleen.cohn(cDncdenr..Qov>; David. E.Bailey2Rusace.army.miI
Cc: Morris, Tom E. <Tom.Morris2(@duke-energv.com>; Tripp, Brad <Brad.TriQQ(a duke-energv.com>;
Parham, Michael A <Michael.Parham(cDduke-energv.com>
Subject: RE: PNG Line 142 Project (SAW-2021-01288 & DWR 20210364) Bi-weekly Status Update
Good morning,
On behalf of Piedmont Natural Gas, please find the attached bi-weekly report.
Alicia DePalma
Environmental Siting, Licensing & Permitting Support
4720 Piedmont Row Drive
Charlotte, NC 28210
(704) 763-9311
alicia.depalmaPcluke-energv.com
From: DePalma, Alicia
Sent: Tuesday, September 6, 2022 1:24 PM
To: Cohn, Colleen M <colleen.cohn(@ncdenr.gov>; David. E.Bailey2(@usace.army.miI
Cc: Morris, Tom E. <Tom.Morris2Pduke-energv.com>; Tripp, Brad <Brad.TriQQ(a duke-energv.com>;
Parham, Michael A<Michael.ParhamPduke-energv.com>
Subject: PNG Line 142 Project (SAW-2021-01288 & DWR 20210364) Bi-weekly Status Update
On behalf of Piedmont Natural Gas, please find the attached bi-weekly report as requested in the
PNG Line 142 Project's Nationwide Permit (SAW-2021-01288) special conditions Item #4, "Once
construction begins within crossings subject to this authorization, compliance reports must be
submitted to the Corps of Engineers, Raleigh Regulatory Field Office and North Carolina Division of
Water Resources on a bi-weekly basis, until construction within these areas is complete.'.
Please let us know if you have any questions or need additional information.
Alicia DePalma
Environmental Siting, Licensing & Permitting Support
4720 Piedmont Row Drive
Charlotte, NC 28210
(704) 763-9311
alicia.depalmana duke-energv.com