HomeMy WebLinkAbout20230806 Ver 1_DMF Comments_20230807Meilinger, Michael J
From: Harding, Kimberlee k
Sent: Monday, August 7, 2023 1:53 PM
To: Meilinger, Michael J
Subject: FW: [External] Additional Information - Hammocks Beach State Park Mainland LS CAMA Major Permit
(SAW 2023-01327)
From: McKinney, Mary -Margaret <MaryMargaret.McKinney@davey.com>
Sent: Monday, August 7, 2023 11:54 AM
To: Harding, Kimberlee k <Kimberlee.Hard ing@deq.nc.gov>; Hair, Sarah E CIV USARMY CESAW (USA)
<Sarah.E.Hair@usace.army.mil>; Weychert, Curtis R <curt.weychert@deq.nc.gov>; Guthrie, Kara L
<Kara.Guthrie@deq.nc.gov>; Dunn, Maria T. <maria.dunn@ncwildlife.org>; Bodnar, Gregg <gregg.bodnar@deq.nc.gov>;
Cannon, Amanda J <Amanda.Cannon@deq.nc.gov>
Cc: Windsor, Matt <matt.windsor@ncparks.gov>; lexiaw <lexiaw@nccoast.org>; Sarah Bodin <sarahb@nccoast.org>;
April Hall <aprilh@nccoast.org>; Rudd, Morgan <Morgan.Rudd @davey.com>; Cervera, Juan C
<juan.cervera@ncparks.gov>; Farrell, Christine E <christine.farrell@ncparks.gov>
Subject: [External] Additional Information - Hammocks Beach State Park Mainland LS CAMA Major Permit (SAW 2023-
01327)
CAUTION: External email. Do not click links or open attachments unless verified. Report suspicious emails with the Report Message
button located on your Outlook menu bar on the Home tab.
Good morning all,
We appreciate your review and comments of the Hammocks Beach State Park Mainland CAMA Permit
application. We would like to provide additional information to assist with your review. See below for more on
that information and our anticipated timeline for submittal.
1. Per discussions with DEQ and received comments, we are revising the project alignment to include 10'
gaps in the main sill and revising the project narrative to reflect this change, resolve previously
identified discrepancies between the narrative and other documents, provide additional information
on erosion, and clarify the location of the sills. We will have new maps, shapefiles, and a revised
narrative to all no later than Friday, 11 August 2023.
In the revised narrative, we are clarifying that the landward edge of the main sill will be 5 feet from
the edge of coastal wetlands and at no point will the waterward edge of the structure (the offset
baffles) be more than 25 feet from the edge of coastal wetlands. This will be more clearly described in
the revised narrative.
3. Information regarding our findings of no anticipated impacts to currently listed T&E species will be
provided no later than August 11.
4. Seine surveys were conducted along the entire alignment the week of July 24. Information from these
surveys will be provided no later than August 11. In the revised narrative, we are clarifying that to
protect juvenile shrimp and finfish, no in -water work will occur from April 1 through July 31 of any
year.
The revised shapefiles our SAV survey locations, and published "SAV Onslow 2021 Final" SAV mapping
available from NCDEQ at https://data-
ncdenr.oDendata.arceis.com/datasets/34f32f64bl29428185949722038fbl68. These are the same SAV
areas shown at
https://www.arcgis.com/apps/webappviewer/index.htmI?id=de86f3bb9e634005b12f69a8a5947367&
extent=-8547966.9341%2C4122310.0151%2C-8519303.0485%2C4139317.2539%2C102100.
6. Can you please direct us to any available written guidance on the frequency of SAV survey transects as
we consider how best to respond to SAV impact concerns and supplement the information provided to
date? We have less than 30 days to conduct any surveys on this project and upcoming permit
applications we would like to submit over the fall and winter, so we would appreciate guidance as soon
as possible.
Best,
Mary -Margaret McKinney
Mary -Margaret S McKinney, RF
Director of Coastal Restoration
Native Shorelines, a Davey Company
252.333.9852 mary-margeretiLDnativeshorelines.com
Unkedln: linked.com/in/marymorgaratmckinney
www.nativeshorelines.com
Email correspondence to and from this address may be subject to the North Carolina Public Records Law and may be disclosed to third parties by an authorized