Loading...
HomeMy WebLinkAboutBuckwater Repair Plan - MY5 MEMORANDUM TO:    401 Permit Reviewer    FROM:    Carolyn Lanza, Wildlands Engineering         DATE:    July 7, 2023    RE:    Project Repair Plan ‐ Supporting Documentation        BUCKWATER MITIGATION SITE        Orange County, NC       On behalf of the North Carolina Department of Mitigation Services (NCDMS), Wildlands Engineering, Inc.  (Wildlands) is requesting a new water quality certification for an existing stream mitigation project in  Orange County, NC.  The Buckwater Mitigation Site was originally permitted in March of 2018 under the  NC Division of Water Resources (NCDWR) Water Quality General Certification Number 4134 and the US  Army Corps of Engineers (USACE) Nationwide Permit Number 27.  The project was constructed between  April of 2018 and April of 2019.    Minor repairs are now needed for this mitigation site and the previous water quality certification for the  project has expired.  The repairs are relatively minor and will be permitted by the USACE under the  Nationwide Permit Number 3.  However, we have been informed by NCDWR that a new water quality  certification will be needed.  A repair plan for the project site is attached to this memo.  Most of the  repairs are simply replacing structures that were originally constructed but have become damaged and  repairing bank erosion.  In total, the repairs will be constructed on 238 linear feet of the project.  The  total length of the original project is 16,276 LF (MY0 Annual Report, September 2019).      We hope this water quality certification for the repair work can be processed in a timely manner.  If you  have additional questions or need more information about the repair plan to issue the new water  quality certification, please do not hesitate to contact me at 313‐969‐7318 or at  clanza@wildlandseng.com should you have any questions.    Sincerely,    Carolyn Lanza  Environmental Scientist   Buckwater Mitigation Site DMS Project No. 97084 Monitoring Year 5 - 2023 Reach Start Station End Station Length (LF) Description Planned 2023 Management Action 314+20 314+30 10 Piping rock sill; souring left bank. Riffle upstream of piping sill is stable and providing grade control. Remove rock sill and tamp down left bank. 314+40 314+70 30 Piping angled log riffle due to log sills being improperly keyed in. Riffle material is providing grade control. Remove angled log riffle, rebuild as native riffle. N/A Perched culvert due to piping rock sills below. 408+42 409+20 78 Nine piping rock sills. Original construction of rock sills were built upstream to downstream preventing proper sealing of structures. 451+40 451+70 30 Six piping rock sills. Original construction of rock sills were built upstream to downstream preventing proper sealing of structures. Rebuild rock sill structures downstream to upstream. 453+00 453+50 50 Four piping log sills and two piping rock sills due to erosion around log sills. Rebuild structures and remove boulder toe along banks. T6 Reach 3 517+80 518+20 40 Four piping log sills due to erosion around log sill.Remove log sills and replace with boulder sills. Not applicable (N/A): Lengths not associated with instances (points) Table 1. Areas of Concern and Management Actions T4 T4B Reach 1 T3 Reach 2 408+42 Rebuild rock sill structures downstream to upstream and remove boulder toe along banks. !( !( !( !( !( !( !( !( !( !( !( !(!( !( !(!( !( !( !( T4 T5 T8 T2 T3 Reach 1 Buckwater Creek Reach 4 T6AT6 Reach 1 T7A T6 Reach 3 T3 Reach 2 T6 Reach 2 T1 Reach 2 T6B Buckwater Creek Reach 7 T1 Reach 1 T7 Reach 3 T7 Reach 2 T7 Reach 1 T4B Reach 1 T9 T4A Reach 1 Buckwater Creek Reach 1 T4A Reach 3 T4A Reach 2 Buckwater Creek Reach 2 Buckwater Creek Reach 8 Buckwater Creek Reach 3 Buckwater Creek Reach 6 Buckwater Creek Reach 5 Figure 1. Integrated Current Condition Plan View Buckwater Mitigation Site DMS Project No. 97084 Monitoring Year 5 - 2023 Orange County, NC ¹0 800400 Feet 2021 Aerial Photography Conservation Easement Internal Crossing Existing Wetlands Stream Approach Restoration Enhancement I Enhancement II No Credit Stream Areas of Concern Utility Easement !(Reach Breaks Piping Log Sills Piping Log Sills Piping Rock Sills and Perched Culvert Piping Rock Sills Piping Log and Rock SillsPiping Rock Sill Stream Area of Concern Photographs T3 R2 STA 314+20 - 314+30 – Piping Rock Sill (3/24/2023) T3 R2 STA 314+40 - 314+70 – Piping Angled Log Riffle (3/24/2023) T3 R2 STA 314+40 - 314+70 – Piping Angled Log Riffle (3/24/2023) T3 R2 STA 314+40 - 314+70 – Piping Angled Log Riffle (3/24/2023) T4 STA 408+42 – Perched Culvert (3/24/2023) T4 STA 408+42 – 409+20 – Piping Rock Sills (3/24/2023) T4 STA 408+42 – 409+20 – Piping Rock Sills (3/24/2023) T4B R1 STA 451+40 – 451+70 – Piping Rock Sills (3/24/2023) T4B R1 STA 451+40 – 451+70 – Piping Rock Sills (3/24/2023) T4B R1 STA 451+40 – 451+70 – Piping Rock Sills (3/24/2023) T4B R1 STA 453+00 – 453+50 – Piping Log and Rock Sills (3/24/2023) T4B R1 STA 453+00 – 453+50 – Piping Log and Rock Sills (3/24/2023) T6 R3 STA 517+80 – 518+20 – Piping Log Sills (3/24/2023) T6 R3 STA 517+80 – 518+20 – Piping Log Sills (3/24/2023) T6 R3 STA 517+80 – 518+20 – Piping Log Sills (3/24/2023)