HomeMy WebLinkAbout20181442 Ver 1_As-Built Credit Release_Dugout_SAW-2018-01883 DEPARTMENT OF THE ARMY WILMINGTON DISTRICT, CORPS OF ENGINEERS 69 DARLINGTON AVENUE WILMINGTON, NORTH CAROLINA 28403-1343 July 18, 2023 Regulatory Division SUBJECT: As-built baseline monitoring report approval and credit release associated with the RES Cape Fear 05 Umbrella Mitigation Bank, Dugout Mitigation Site Mr. Ben Carroll Resource Environmental Solutions 3600 Glenwood Avenue Suite 100 Raleigh, NC 27612 Dear Mr. Carroll: This letter is to inform you that the Wilmington District, Corps of Engineers (Corps) has reviewed the as-built baseline monitoring report for the RES Cape Fear 05 Umbrella Mitigation Bank (UMB), Dugout mitigation site (Action ID SAW-2018-01883), dated March 10, 2023, and revised on June 30, 2023. The Dugout site is in the Cape Fear River Basin (Hydrologic Unit Code 03030005), southeast of the intersection of Hwy 87 and Upton Tyson Road, adjacent to Grays Creek, in Cumberland County, NC. In accordance with Sec. 332.8(o)(9) of the Federal Mitigation Rule, the baseline monitoring report was provided to the North Carolina Interagency Review Team (NCIRT) for review and comment on March 21, 2023. A site meeting was also held on May 30, 2023, to assess the as-built site conditions. During this meeting, the NCIRT noted several actions that had to be completed prior to the approval of the as-built plans and associated credit release. The two major items included submittal of a plan to modify (reconstruct) and monitor reach TV1-C and revising the wetland credit calculations to remove constructed floodplain swales from wetland credit (a reduction of 0.042 credits). The attached minutes document result of the meeting and comments from the NCIRT. Following the meeting, the revised as-built baseline monitoring report dated June 30, 2023, was submitted to our office, which verifies completion of the required actions necessary to finalize the as-built report. Pursuant to the UMB Instrument approved on September 29, 2021, and the site- specific Dugout Final Mitigation Plan dated April 2021, 15 percent of the mitigation site’s -2- totalrestoration and enhancement creditsshall be available for sale immediately after the completion of implementation of the mitigation plan and Corpsapproval of the baseline monitoring report and as-built survey.By copy of this correspondence, we confirm that you have satisfied the above requirements for the as-built credit release, and 980.120 stream mitigation units (SMUs) and 0.921 wetland mitigation units (WMUs) are now available for sale. With this release, 1,960.240SMUs and 2.021 WMUs (30 percent of the total restoration and enhancement credits and 100 percent of the total preservation credits) have been released for sale.Theattached credit release schedule has been updatedto reflect the change in total wetland credit proposed to be generated on the site. Please ensure that future credit release requests utilize the updated credit release schedule. Please note that this electronic copy provided to you via email is your official copy. Should you wish to receive a paper copyof this correspondence, please contact us. Thank you for your time and cooperation. If you have any questions, please contact me by email at todd.tugwell@usace.army.milor by phone at (919) 210-6265. Sincerely, Todd Tugwell Chief, Mitigation Branch Enclosure cc (byemail): NCIRT Distribution List p p p p p p p p p p