HomeMy WebLinkAboutNCC202455_NOT Closeout Documents_20230710 Sedimentation/Construction Stormwater Inspection Report
North Carolina Department of Environmental Quality
Land Resources: 127 Cardinal Drive Extension,Wilmington,NC 28405 (910) 796-7215
County: Onslow Project: Duke Energy Jacksonville Substation River basin: White Oak
Person financially responsible:Duke Energy Progress,LLC-Alan Lewis, Project#: ONSLO-2020-030
Manager
Address: 410 S Wilmington St,Raleigh,NC 27601
1. Project Location: Gum Branch Road,Jacksonville
Pictures: No
2. Weather and soil conditions: Sunny and workable Initial inspection: No
3. Is site currently under notice of violation? No
4. Is the site in compliance with S.P.C.A.and rules? Yes If no,check violations below:
5. Violations:
6. Is the site in compliance with NPDES Permit NCG010000 Construction Stormwater requirements? Yes
Describe:
7. Has sedimentation damage occurred since last inspection? No If Yes,where? (check all that apply)
Degree of damage:
8. Contact made with(name): None Title:
Inspection report: Sent Report Date given/sent: November 19,2021
9. Corrective action needed:
10. Comments: Project appears complete and stabilized.File will be closed.Any further/future development
will require a new permit application to be submitted.
Permanent ground cover sufficient to restrain erosion has been established.No additional
self-monitoring or self-inspections are required.Project is in compliance and released under
the SPCA.Termination of coverage under the NPDES General Stormwater Permit for
Construction Activities(NCG01)must be requested by the permittee via a Notice of
Termination(NOT).The NOT is available
at:https://edocs.deq.nc.gov/Forms/NCG01-Termination.Please note that this correspondence
must be uploaded as part of completing the NOT process.
Reported by: Connor Musial Others present:
Date of inspection: November 16,2021 Time arriving on site: 1:45 PM Time leaving site: 2:10 PM
CC: