HomeMy WebLinkAboutSWA000200_email_20230307 (2)
Peck, Kaitlin
From:Farkas, Jim J
Sent:Tuesday, March 7, 2023 2:11 PM
To:Jeremy McCall
Subject:RE: \[External\] FW: \[External\]Stapleton Subdivision Phases 1 & 2 in Forsyth County
\[New BUA\] shouldn’t include existing BUA that is relocated on-site or changed from one type of BUA to another, only
the net increase in BUA should be used for \[New BUA\]. You are still required to exclude the existing BUA in the %BUA
calculation.
Jim Farkas
State Stormwater Engineer
North Carolina Department of Environmental Quality
Office: (919) 707-3646
Jim.farkas@ncdenr.gov
From: Jeremy McCall <jeremy@greenmountainengineers.com>
Sent: Tuesday, March 7, 2023 2:06 PM
To: Farkas, Jim J <Jim.Farkas@ncdenr.gov>
Subject: \[External\] FW: \[External\]Stapleton Subdivision Phases 1 & 2 in Forsyth County
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
Report Spam.
Good afternoon Jim,
If we are removing the existing impervious area do we still need to subtract that from the total project area?
Thank You,
Jeremy L. McCall, CFM, PE
Green Mountain Engineering, PLLC
1A Wendy Court
Greensboro, NC 27409
www.greenmountainengineers.com
Office 336.594-0643
Cell 336.870.0940
1
From: Farkas, Jim J <Jim.Farkas@ncdenr.gov>
Sent: Tuesday, March 7, 2023 8:34 AM
To: Will Derrickson <wderrickson@mungo.com>; contact@greenmountainengineers.com
Cc: Kay, Lily C <lily.kay@ncdenr.gov>
Subject: \[External\]Stapleton Subdivision Phases 1 & 2 in Forsyth County
Good Morning,
We received your application for a new Fast-Track ATC post-construction stormwater permit on 3/3/2023. At this time,
the submission is not administratively complete and cannot be accepted for review in its current condition. Please
provide the following submittal items within 30 calendar days (by close of business on 4/6/2023) so that we may accept
the project and begin the review process, otherwise, the project will be returned as administratively incomplete.
2x hard copies of the Application Form (or pages) with the following corrections made (A complete application is
required per 15A NCAC 02H .1043(3)(a)):
Part D2 – Please complete this information.
Part E4 – The stream index and classification number do not appear to be correct. This information can
be found at the following address:
https://experience.arcgis.com/experience/7073e9122ab74588b8c48ded34c3df55/ Please revise as
needed.
Part E5 – The project density does not appear to be calculated correctly. For a project with existing BUA,
the % BUA is calculated as \[New BUA\] / (\[Total Project Area\] – \[Existing BUA\]). Per the information in the
table, \[New BUA\] = 624,858 sf, \[Total Project Area\] = 2,577,537 sf, & \[Existing BUA\] = 6,243 sf. This
results in a percent BUA of 24.3% (624,858 sf / (2,577,537 sf – 6,243 sf) = 24.3%). NOTE: This is in excess
of the maximum allowable %BUA for a low-density project. Please revise as needed.
1x original signed and notarized/sealed hard copy of Parts G & H of the Application. 2x original signed hard
copies of this form are required and only one was provided (the other copy appears to be a photocopy).
2x hard copies of a construction sequence discussing how any future development on the project may be
phased. This item is required per 15A NCAC 02H .1043(3)(g). The construction sequence does not need to be
lengthy, just a brief description of how future development on the project (beyond what is shown on the
plans) will be phased. If no future development is planned for the project, you can simply state that in the
construction sequence. This item is different than the E&SC sequence of construction.
2x hard copies of official documentation showing the title and position of the signing official for the Applicant
and showing that the Applicant organization is in good standing with the Secretary of State. These items are
required per Part F7 of the Application and 15A NCAC 02H .1043(3)(b).
NOTE: This is an administrative completeness review, not a detailed engineering review, there may be other issues that
may be brought up during the engineering review. The following items were noted during the review, but do not need
to be addressed for administrative completeness:
- Untreated stormwater runoff cannot be directly discharged to a surface water (as appears to be the case with
the culvert near Lots 1 & 111) it must be released at the edge of the vegetated setback and allowed to flow
through the vegetated setback as dispersed flow (per 15A NCAC 02H .1003(4)(e)).
- There appears to be excessive piping for this project to be considered as low-density (notably the pipes located
between lots 14 & 15, 19 & 20, and 86 & 87). Per 15A NCAC 02H .1003(2)(c), vegetated conveyances should be
used in these locations.
If these items are received within the stipulated timeframe, we can accept the project and begin the review process.
Once accepted, reviews under the Fast-Track permitting process can take up to 30 calendar days per statute (one of our
two reviewer positions is currently vacant).
Hard copies should be mailed to the following address:
For FedEx/UPS:
Jim Farkas
2
512 N. Salisbury Street, Office 640M
Raleigh, NC 27604
For USPS:
Jim Farkas
1612 Mail Service Center
Raleigh, NC 27699-1612
If you have any questions, please contact Jim Farkas at jim.farkas@ncdenr.gov or 919-707-3646.
Thank you,
Jim Farkas
State Stormwater Engineer
North Carolina Department of Environmental Quality
Office: (919) 707-3646
Jim.farkas@ncdenr.gov
To view our privacy policies, please click here:
https://www.claytonhomes.com/privacy/
Disclaimer
The information contained in this communication from the sender is confidential. It is intended solely for use by the recipient and
others authorized to receive it. If you are not the recipient, you are hereby notified that any disclosure, copying, distribution or
taking action in relation of the contents of this information is strictly prohibited and may be unlawful.
This email has been scanned for viruses and malware, and may have been automatically archived by Mimecast, a leader in email
security and cyber resilience. Mimecast integrates email defenses with brand protection, security awareness training, web security,
compliance and other essential capabilities. Mimecast helps protect large and small organizations from malicious activity, human
error and technology failure; and to lead the movement toward building a more resilient world. To find out more, visit our website.
3