Loading...
HomeMy WebLinkAboutNCG140516_Insp Rpt_20230707 Compliance Inspection Report Permit:NCG140516 Effective: Expiration: Owner: L&L Concrete LLC SOC: Effective: Expiration: Facility: Triangle Ready Mix County: Wake 237 International Dr Region: Raleigh Morrisville NC 27560 Contact Person:Keith Mercer Title: Phone: 919-459-4190 Directions to Facility: System Classifications: Primary ORC: Certification: Phone: Secondary ORC(s): On-Site Representative(s): Related Permits: Inspection Date: 07/07/2023 Entry Time 11:OOAM Exit Time: 01:10PM Primary Inspector:Thaddeus W Valentine Phone: Secondary Inspector(s): Reason for Inspection: Routine Inspection Type: Compliance Evaluation Permit Inspection Type: Ready Mix Concrete Stormwater/Wastewater Discharge COC Facility Status: ❑ Compliant Not Compliant Question Areas: Storm Water (See attachment summary) Page 1 of 3 Permit: NCG140516 Owner-Facility:L&L Concrete LLC Inspection Date: 07/07/2023 Inspection Type:Compliance Evaluation Reason for Visit: Routine Inspection Summary: I walked the site with the Owner Nelson Loureiro and teh consultant Bill Bremen with WithersRavenal to discuss what still needed to be done. The facility did remove the 250 gal. waste oil container by the stormwater inlet and cleaned up and removed all the oil drums, buckets and miscellaneous containers with oil in them and appeared to have cleaned up what had spilled. We viewed the drop inlet that was a concern because no outlet was seen in the basin from the inlet As expected, the init was filled to about 75%full with sediment and concrete materials.This is an effect of the discharge pipe being located below the water surface in the basin. There is no flow toward the basin and the discharge pipe sits below grade holding water and backwash from the basin. This placing of the discharge pipe has created a condition were the inlet vault and pipe will fill almost immediately with runoff from very small storm events and overflow into the woodline and stream adjacent to the basin. This causes the basin to be bypassed and the storm discharges to leave the site untreated. (Something will need to be done immediately to prevent this from occurring) Samples of the wastewater should be taken ASAP and follow up with both stormwater and wastewater(again)at the next stormevent. Please provide me with samples as soon as they are recieved and provide an update within 30 days of the plan for rectifing the submerged discharge pipe problem Page 2 of 3 Permit: NCG140516 Owner-Facility:L&L Concrete LLC Inspection Date: 07/07/2023 Inspection Type:Compliance Evaluation Reason for Visit: Routine Stormwater Pollution Prevention Plan Yes No NA NE Does the site have a Stormwater Pollution Prevention Plan? ❑ ❑ ❑ #Does the Plan include a General Location (USGS) map? ❑ ❑ ❑ #Does the Plan include a"Narrative Description of Practices"? ❑ ❑ ❑ #Does the Plan include a detailed site map including outfall locations and drainage areas? ❑ ❑ ❑ #Does the Plan include a list of significant spills occurring during the past 3 years? ❑ ❑ ❑ #Has the facility evaluated feasible alternatives to current practices? ❑ ❑ ❑ #Does the facility provide all necessary secondary containment? ❑ ❑ ❑ #Does the Plan include a BMP summary? ❑ ❑ ❑ #Does the Plan include a Spill Prevention and Response Plan (SPRP)? ❑ ❑ ❑ #Does the Plan include a Preventative Maintenance and Good Housekeeping Plan? ❑ ❑ ❑ #Does the facility provide and document Employee Training? ❑ ❑ ❑ #Does the Plan include a list of Responsible Party(s)? ❑ ❑ ❑ # Is the Plan reviewed and updated annually? ❑ ❑ ❑ #Does the Plan include a Stormwater Facility Inspection Program? ❑ ❑ ❑ Has the Stormwater Pollution Prevention Plan been implemented? ❑ ❑ 0 ❑ Comment: I concentrated most of my time on the site inspection. There were many serious issues that nneded to be reviewed and discussed whuile the owner and consultants were on site. We did talk about what they needed to put together for the stormwater pollution prevention plan (SP3) so that it will be complete and function as intended Qualitative Monitoring Yes No NA NE Has the facility conducted its Qualitative Monitoring? ❑ 0 ❑ ❑ Comment: No qualitative samples were taken. I asked them again, to go ahead and get samples of the stormwater and wastewater. The wastewater samples can be taken at any time Analytical Monitoring Yes No NA NE Has the facility conducted its Analytical monitoring? ❑ 0 ❑ ❑ #Has the facility conducted its Analytical monitoring from Vehicle Maintenance areas? ❑ 0 ❑ ❑ Comment: Once again asked for samples to be taken. Wastewater can be taken immediately Permit and Outfalls Yes No NA NE # Is a copy of the Permit and the Certificate of Coverage available at the site? ❑ ❑ ❑ #Were all outfalls observed during the inspection? ❑ ❑ ❑ # If the facility has representative outfall status, is it properly documented by the Division? ❑ ❑ ❑ #Has the facility evaluated all illicit(non stormwater)discharges? ❑ 0 ❑ ❑ Comment: The outfalls were observed and discussed. Page 3 of 3