Loading...
HomeMy WebLinkAbout20210364 Ver 1_20230622 - PNG Line 142 Bi-Weekly Permit Report_20230622 Project Name: PNG Line 142 Date: 06/22/2023 Feature ID Start Date Completion Date Notes Stream S1 3-1-2023 Matted crossing removed Stream S2 3-1-2023 Matted crossing removed Stream S3 3-1-2023 Matted crossing removed Stream S4 4-18-2023 Matted crossing removed Stream S5 4-18-2022 Matted crossing removed Stream S6 3-3-2023 Matted crossing removed Stream S7 11-25-2022 11-25-2022 Pipe installation complete (HDD) Stream S8 6-21-2023 Pipe installation complete (HDD) Stream S9 6-21-2023 Pipe installation complete (HDD) Stream S10 5-8-2023 Matted crossing removed Stream S11 6-22-2023 Matted crossing removed Stream S12 6-22-2023 Matted crossing removed Stream S13 8-26-2022 False ROW for HDD Matted crossing removed Stream S14 8-26-2022 False ROW for HDD Matted crossing removed Stream S15 3-1-2023 Matted crossing removed Stream S16 3-1-2023 Matted crossing removed Stream S17 3-8-2023 Matted crossing removed Stream S18 9-19-2022 12-10-2022 Pipe installation complete (HDD) Stream S19 1-17-2023 5-16-2023 Matted crossing removed Stream S20 1-17-2023 5-16-2023 Matted crossing removed Stream S21 5-10-2023 Matted crossing removed Stream S22 4-29-2023 Matted crossing removed Stream S23 3-20-2023 Matted crossing removed Stream S24 3-22-2023 Matted crossing removed Stream S25 3-22-2023 Matted crossing removed Stream S26 3-23-2023 Matted crossing removed Stream S27 3-20-2023 Matted crossing removed Stream S28 4-3-2023 Matted crossing removed Stream S29 4-3-2023 Matted crossing removed Stream S30 4-3-2023 Matted crossing removed Stream S31 3-30-2023 Matted crossing removed Stream S32 3-30-2023 Matted crossing removed Stream S33/34 3-16-2023 Matted crossing removed Stream S35 3-16-2023 Matted crossing removed Stream S36 3-21-2023 Matted crossing removed Stream S37/38 3-16-2023 Matted crossing removed Project Name: PNG Line 142 Date: 06/22/2023 Feature ID Start Date Completion Date Notes Wetland W1 3-28-2023 Matted crossing removed Wetland W1A 9-19-2022 False ROW for HDD Clearing complete Wetland W1B 03-01-2023 Matted crossing removed Wetland W2 11-30-2022 11-30-2022 Pipe installation complete (HDD) Wetland W3 03-01-2023 Matted crossing removed Wetland W4A-A 5-10-2023 Pipe installation complete Wetland W4A-B 5-10-2023 Pipe installation complete Wetland W4D 5-10-2023 Pipe installation complete Wetland W4C 5-10-2023 Pipe installation complete Wetland W4E 5-23-2023 Matted crossing removed Wetland W4F 5-23-2023 Matted crossing removed Wetland W5-A 5-24-2023 Matted crossing removed Wetland W5-B 5-24-2023 Matted crossing removed Wetland W6-A 9-19-2022 12-10-2022 Pipe installation complete (HDD) Wetland W5B-A 3-1-2023 Matted crossing removed Wetland W5B-B 3-1-2023 Matted crossing removed Wetland W6-A1 5-31-2023 Matted crossing removed Wetland W6-B1 5-31-2023 Matted crossing removed Wetland W7-A 3-15-2023 Matted crossing removed Wetland W7-B 3-15-2023 Matted crossing removed Wetland W7C-A 3-22-2023 Matted crossing removed Wetland W7C-B 3-22-2023 Matted crossing removed Wetland W7D-A 3-22-2023 Matted crossing removed Wetland W7D-B 3-22-2023 Matted crossing removed Wetland W7E-A 3-24-2023 Matted crossing removed Wetland W7E-B 3-24-2023 Matted crossing removed Wetland W8-A 3-23-2023 Matted crossing removed Wetland W8-B 3-23-2023 Matted crossing removed Wetland W9-A 3-21-2023 Matted crossing removed Wetland W9-B 3-21-2023 Matted crossing removed Wetland W9C-A 4-3-2023 Matted crossing removed Wetland W9C-B 4-3-2023 Matted crossing removed Wetland W9D-A 4-3-2023 Matted crossing removed Wetland W9D-B 4-3-2023 Matted crossing removed Wetland W9E-A 4-5-2023 Matted crossing removed Wetland W9E-B 4-5-2023 Matted crossing removed Project Name: PNG Line 142 Date: 06/22/2023 Stream S-11 Stream S-12-W4F Project Name: PNG Line 142 Date: 06/22/2023 Wetland W5-A Wetland W6-A1