Peck, Kaitlin
From:Farkas, Jim J
Sent:Tuesday, February 21, 2023 11:46 AM
To:Moseley, Alan, PE; Raelene St. Clair
Cc:CHURCH, AARON; Eplin, Jerry W
Subject:Rowan County RV Dealership in Salisbury, Rowan County
Good Morning,
We received your application for a new Fast-Track ATC post-construction stormwater permit on 2/10/2023. At this time,
the submission is not administratively complete and cannot be accepted for review in its current condition. Please
provide the following submittal items within 30 calendar days (by close of business on 3/23/2023) so that we may
accept the project and begin the review process, otherwise, the project will be returned as administratively incomplete.
2x hard copies of the Application Form (or pages) with the following corrections made (A complete application is
required per 15A NCAC 02H .1043(3)(a)):
Part C2 – Please indicate the post-construction program that this project is subject to (Urbanizing Areas
(Phase 2)).
Part E1 – Please indicate the density of this project (this project appears to be a high-density project).
1x original signed and notarized/sealed hard copy of Parts G, H, & I of the Application. 2x original signed hard
copies of this form are required and only one was provided (the other copy appears to be a photocopy).
2x hard copies of a construction sequence discussing how any future development on the project may be
phased. This item is required per 15A NCAC 02H .1043(3)(g). The construction sequence does not need to be
lengthy, just a brief description of how future development on the project (beyond what is shown on the
plans) will be phased. If no future development is planned for the project, you can simply state that in the
construction sequence. This item is different than the E&SC sequence of construction.
2x hard copies of a plan sheet with the following corrections made:
Wetland delineation or a note on the plans stating that there are no wetlands located on-site. This item
is required per 15A NCAC 02H .1043(3)(f) and Part F4 of the Application. Please also list the name of the
individual that made this determination in a note on the plans.
NOTE: This is an administrative completeness review, not a detailed engineering review, there may be other issues that
may be brought up during the engineering review. While not required for administrative completeness, the following
items were noted during review:
- This project is located within 5 miles of a public airport. It is recommended to use SCMs that do not promote
standing water in accordance with G.S. 143-214.7(c3)
https://www.ncleg.gov/EnactedLegislation/Statutes/HTML/BySection/Chapter_143/GS_143-214.7.html.
Alternative SCMs that can be used within the 5 mile radius of a public airport are outlined in Part E-4 of the
Manual https://deq.nc.gov/media/9977/download.
nd
NOTE: The Standard Application for this project received by our office on February 2, 2023 is being returned as a
project can only be accepted into one review queue/permitting path. The submittal items associated with the Standard
Application (and not needed for the Fast-Track ATC Application) will be returned to the Applicant (except for the roll of
plans, that is too large for us to return my mail, but it can be arranged to be picked up if you would like it back). If you
would like the items returned to a different address/individual, please let me know by close of business Friday,
2/24/2023.
If these items are received within the stipulated timeframe, we can accept the project and begin the review process.
Once accepted, reviews under the Fast-Track permitting process can take up to 30 calendar days per statute (one of our
two reviewer positions is currently vacant).
1
Hard copies should be mailed to the following address:
For FedEx/UPS:
Jim Farkas
512 N. Salisbury Street, Office 640M
Raleigh, NC 27604
For USPS:
Jim Farkas
1612 Mail Service Center
Raleigh, NC 27699-1612
If you have any questions, please contact Jim Farkas at jim.farkas@ncdenr.gov or 919-707-3646.
Thank you,
Jim Farkas
State Stormwater Engineer
North Carolina Department of Environmental Quality
Office: (919) 707-3646
Jim.farkas@ncdenr.gov