20210364 Ver1_20230511 - PNG Line 142 Bi-Weekly Permit Report_20230511
Project Name: PNG Line 142 Date: 05/11/2023 Feature ID Start Date Completion Date Notes Stream S1 3-1-2023 Matted crossing removed Stream S2 3-1-2023 Matted crossing removed Stream S3 3-1-2023 Matted crossing removed Stream S4 4-18-2023 Matted crossing removed Stream S5 4-18-2022 Matted crossing removed Stream S6 3-3-2023 Matted crossing removed Stream S7 11-25-2022 11-25-2022 Pipe installation complete (HDD) Stream S8 4-26-2023 Clearing complete Stream S9 4-26-2023 Clearing complete Stream S10 5-8-2023 Pipe installation complete Stream S11 4-26-2023 Clearing complete Stream S12 11-29-2022 11-29-2022 Pipe installation complete Stream S13 8-26-2022 False ROW for HDD Clearing complete Stream S14 8-26-2022 False ROW for HDD Clearing complete Stream S15 3-1-2023 Matted crossing removed Stream S16 3-1-2023 Matted crossing removed Stream S17 3-8-2023 Matted crossing removed Stream S18 9-19-2022 12-10-2022 Pipe installation complete (HDD) Stream S19 1-17-2023 1-18-2023 Pipe installation complete Stream S20 1-17-2023 1-18-2023 Pipe installation complete Stream S21 5-10-2023 Matted crossing removed Stream S22 4-29-2023 Matted crossing removed Stream S23 3-20-2023 Matted crossing removed Stream S24 3-22-2023 Matted crossing removed Stream S25 3-22-2023 Matted crossing removed Stream S26 3-23-2023 Matted crossing removed Stream S27 3-20-2023 Matted crossing removed Stream S28 4-3-2023 Matted crossing removed Stream S29 4-3-2023 Matted crossing removed Stream S30 4-3-2023 Matted crossing removed Stream S31 3-30-2023 Matted crossing removed Stream S32 3-30-2023 Matted crossing removed Stream S33/34 3-16-2023 Matted crossing removed Stream S35 3-16-2023 Matted crossing removed Stream S36 3-21-2023 Matted crossing removed Stream S37/38 3-16-2023 Matted crossing removed Project Name: PNG Line 142 Date: 05/11/2023 Feature ID Start Date Completion Date Notes Wetland W1 3-28-2023 Matted crossing removed Wetland W1A 9-19-2022 False ROW for HDD Clearing complete Wetland W1B 03-01-2023 Matted crossing removed Wetland W2 11-30-2022 11-30-2022 Pipe installation complete (HDD) Wetland W3 03-01-2023 Matted crossing removed Wetland W4A-A 5-10-2023 Pipe installation complete Wetland W4A-B 5-10-2023 Pipe installation complete Wetland W4D 5-10-2023 Pipe installation complete Wetland W4C 5-10-2023 Pipe installation complete Wetland W4E 4-26-2023 Clearing complete Wetland W4F 11-29-2022 11-29-2022 Pipe installation complete Wetland W5-A 11-29-2022 11-29-2022 Pipe installation complete Wetland W5-B 11-29-2022 11-29-2022 Pipe installation complete Wetland W6-A 9-19-2022 12-10-2022 Pipe installation complete (HDD) Wetland W5B-A 3-1-2023 Matted crossing removed Wetland W5B-B 3-1-2023 Matted crossing removed Wetland W6-A1 11-29-2022 11-29-2022 Pipe installation complete Wetland W6-B1 11-29-2022 11-29-2022 Pipe installation complete Wetland W7-A 3-15-2023 Matted crossing removed Wetland W7-B 3-15-2023 Matted crossing removed Wetland W7C-A 3-22-2023 Matted crossing removed Wetland W7C-B 3-22-2023 Matted crossing removed Wetland W7D-A 3-22-2023 Matted crossing removed Wetland W7D-B 3-22-2023 Matted crossing removed Wetland W7E-A 3-24-2023 Matted crossing removed Wetland W7E-B 3-24-2023 Matted crossing removed Wetland W8-A 3-23-2023 Matted crossing removed Wetland W8-B 3-23-2023 Matted crossing removed Wetland W9-A 3-21-2023 Matted crossing removed Wetland W9-B 3-21-2023 Matted crossing removed Wetland W9C-A 4-3-2023 Matted crossing removed Wetland W9C-B 4-3-2023 Matted crossing removed Wetland W9D-A 4-3-2023 Matted crossing removed Wetland W9D-B 4-3-2023 Matted crossing removed Wetland W9E-A 4-5-2023 Matted crossing removed Wetland W9E-B 4-5-2023 Matted crossing removed Project Name: PNG Line 142 Date: 05/11/2023 Stream S-36 Project Name: PNG Line 142 Date: 05/11/2023 Stream S-10 Stream S-4 Stream S-35