HomeMy WebLinkAboutSW6211205_email_20221222
Peck, Kaitlin
From:DeBerry, Margie
Sent:Thursday, December 22, 2022 2:39 PM
To:charlescmorris@gmail.com; Scott Brown
Cc:Lawyer, Mike; Farkas, Jim J
Subject:SW6211205 Brookstone Village
Follow Up Flag:Follow up
Flag Status:Flagged
Good afternoon,
We received your post-construction stormwater permit minor modification application for the above mentioned project
on 12/22/2022. Reviews under the standard permitting process generally take 75 calendar days, but can take up to 90
calendar days per statute (our other reviewer, Corey Anen, no longer works for the State, so this review may exceed 75
days). Please upload all documents that you mailed into our office through the link provided below. Be sure to choose
the Central Office as the Primary Contact office.
https://edocs.deq.nc.gov/Forms/SW-Supplemental-Upload
IMPORTANT NOTE: Please ensure that each file is uploaded under its appropriate file type. Additional file types can be
entered into the electronic form by clicking on the “Add Another Post-Construction File Upload” link directly below the
“State Stormwater Information Uploads” section of the form. Please do not upload entire plan sets through this form,
but rather upload the relevant individual sheets under the appropriate file type. Selecting the correct file type ensures
that the files are properly named in the electronic repository and it helps expedite the review process.
Please type in permit #: SW6211205
If you have any questions, please contact Jim Farkas Jim.Farkas@ncdenr.gov 919-707-3646.
Thank you,
Margie DeBerry
Environmental Specialist, Division of Energy, Mineral, and Land Resources
North Carolina Department of Environmental Quality
Office: (919) 707-9209
margie.deberry@ncdenr.gov
1