HomeMy WebLinkAboutSW3220302_email_20221206
Peck, Kaitlin
From:DeBerry, Margie
Sent:Tuesday, December 6, 2022 7:25 AM
To:julian.wilson@jjech.com; jay@hensonfoley.com; kennedy@hensonfoley.com
Cc:Khan, Zahid; Farkas, Jim J
Subject:RE: Denver Defense, Denver, Lincoln County
Good morning,
We received your additional information for a minor modification post-construction stormwater permit on 12/5/2022.
At this time, the submission is not administratively complete and cannot be accepted for review in its current condition.
Please provide the following submittal item by close of business on 12/14/2022 so that we may accept the project and
begin the review process, otherwise, the project will be returned as administratively incomplete.
1x hard copy of the Application with the following corrections made (This item is required per Part B, 1 of the
Application):
Part D – Please provide an original (wet) signature in this section of the Application. – Only one hard
copy of the application with an original signature was provided with the 12/5/2022 submittal and two
hard copies are required.
NOTE: This is an administrative completeness review, not a detailed engineering review, there may be other issues that
may be brought up during the engineering review.
Hard copies should be mailed to the following address:
For FedEx/UPS:
Jim Farkas
512 N. Salisbury Street, Office 640E
Raleigh, NC 27604
For USPS:
Jim Farkas
1612 Mail Service Center
Raleigh, NC 27699-1612
If you have any questions, please contact Margie DeBerry at Margie.DeBerry@ncdenr.gov or 919-707-9209.
Thank you,
Margie DeBerry
Environmental Specialist, Division of Energy, Mineral, and Land Resources
North Carolina Department of Environmental Quality
Office: (919) 707-9209
margie.deberry@ncdenr.gov
1
From: DeBerry, Margie
Sent: Monday, November 14, 2022 9:29 AM
To: julian.wilson@jjech.com; jay@hensonfoley.com; kennedy@hensonfoley.com
Cc: Khan, Zahid <zahid.khan@ncdenr.gov>; Farkas, Jim J <Jim.Farkas@ncdenr.gov>
Subject: Denver Defense, Denver, Lincoln County
Good morning,
We received your application for a minor modification post-construction stormwater permit on 10/26/2022. At this
time, the submission is not administratively complete and cannot be accepted for review in its current condition. Please
provide the following submittal items within 30 calendar days (by close of business on 12/14/2022) so that we may
accept the project and begin the review process, otherwise, the project will be returned as administratively incomplete.
2x hard copies of the Application with the following corrections made (This item is required per Part B, 1 of the
Application):
Part D – Please provide an original (wet) signature in this section of the Application. – The provided hard
copies of the Application did not include original signatures.
NOTE: This is an administrative completeness review, not a detailed engineering review, there may be other issues that
may be brought up during the engineering review.
Hard copies should be mailed to the following address:
For FedEx/UPS:
Jim Farkas
512 N. Salisbury Street, Office 640E
Raleigh, NC 27604
For USPS:
Jim Farkas
1612 Mail Service Center
Raleigh, NC 27699-1612
If you have any questions, please contact Margie DeBerry at Margie.DeBerry@ncdenr.gov or 919-707-9209.
Thank you,
Margie DeBerry
Environmental Specialist, Division of Energy, Mineral, and Land Resources
North Carolina Department of Environmental Quality
Office: (919) 707-9209
margie.deberry@ncdenr.gov
2
3