HomeMy WebLinkAboutSW4210501_Email_20221123
Peck, Kaitlin
From:DeBerry, Margie
Sent:Wednesday, November 23, 2022 9:17 AM
To:gbarnes@vanguardpg.com; wwilsonsr@realtyworldtriad.com; mlowder@bowman.com
Cc:Eplin, Tamera; Farkas, Jim J
Subject:SW4210501 Dollar General - Burlington
Good morning,
We received your post-construction stormwater permit transfer application for the above mentioned project on
11/18/2022. Reviews under the standard permitting process generally take 75 calendar days, but can take up to 90
calendar days per statute (our other reviewer, Corey Anen, no longer works for the State, so this review may exceed 75
days). Please upload all documents that you mailed into our office through the link provided below. Be sure to choose
the Central Office as the Primary Contact office.
https://edocs.deq.nc.gov/Forms/SW-Supplemental-Upload
IMPORTANT NOTE: Please ensure that each file is uploaded under its appropriate file type. Additional file types can be
entered into the electronic form by clicking on the “Add Another Post-Construction File Upload” link directly below the
“State Stormwater Information Uploads” section of the form. Please do not upload entire plan sets through this form,
but rather upload the relevant individual sheets under the appropriate file type. Selecting the correct file type ensures
that the files are properly named in the electronic repository and it helps expedite the review process.
Please type in permit #: SW4210501
If you have any questions, please contact Jim Farkas Jim.Farkas@ncdenr.gov 919-707-3646.
Thank you,
Margie DeBerry
Environmental Specialist, Division of Energy, Mineral, and Land Resources
North Carolina Department of Environmental Quality
Office: (919) 707-9209
margie.deberry@ncdenr.gov
1