Hello IRT,
The below referenced FINAL As-Built/Record Drawing review has been requested by NCDMS. Per Section 332.8(o)(9) of the 2008 Mitigation Rule, this review follows the streamlined review
process, which requires an IRT review period of 15 calendar days from this email notification. Please provide any comments by 5 PM on the 15-day comment deadline shown below. When
providing comments please indicate if your concerns are great enough that you recommend not issuing the credit release. Comments provided after the 15-day comment deadline (shown below)
may not be considered. Please note, if a site visit is requested by the IRT, comments will be due 15-days following the visit. At the conclusion of this comment period, a copy of all
comments will be provided to NCDMS and the NCIRT along with District Engineer's intent to approve or disapprove this Final Record Drawing and initial credit release.
15-Day Comment Start Date: June 20, 2023
15-Day Comment Deadline: July 5, 2023
45-Day Credit Release Approval Deadline: August 4, 2023
2023 is Monitoring Year 1 for this project.
Project information and location of the FINAL As-Built Baseline Monitoring Report (MY0):
Sliver Moon II
DMS Project# 100077
RFP# 16-007401—Issued 12/07/2017
Institution Date: 06/15/2018—Full Delivery
SAW-2018-01761
DWR# 20181156
Neuse River Basin
Cataloging Unit 03020202
Craven County, North Carolina
Mitigation Plan Credits:
30.447 Non-Riparian WMUs
As-Built-MY0 Credits:
30.447 Non-Riparian WMUs
Mitigation Plan Area:
30.447 acres
As-Built-MY0 Area:
30.447 acres
Please note:
Construction was completed in October 2021 and planting was completed in December 2021. The MY0 report was completed in the fall of 2022, but due to an easement encroachment discovered
at that time resulting in the need to replant 0.892 acres and install additional easement marking, the MY0 report was delayed to the following spring in 2023. 2023 will be Monitoring
Year 1 for this project. There is no change in wetland acreage from mitigation plan to as-built – 30.447 acres – and no change in project credits is requested.
Provider: Restoration Systems, LLC, Ray Holz, Raymond.Holz@davey.com <mailto:Raymond.Holz@davey.com> , 919-604-9314
NCDEQ - DMS PM: Jeremiah Dow, jeremiah.dow@deq.nc.gov <mailto:jeremiah.dow@deq.nc.gov> , 919-218-0226
USACE Bank Manager: Todd Tugwell, todd.tugwell@usace.army.mil <mailto:todd.tugwell@usace.army.mil> , (919) 210-6265
USACE Mitigation Specialist: Erin Davis, Erin.B.Davis@usace.army.mil <mailto:Erin.B.Davis@usace.army.mil> , (919) 930-1887
FINAL As-Built Baseline Monitoring Report and Record Drawings can be accessed directly on the RIBITS and DMS SharePoint site here:
RIBITS Link: https://ribits.ops.usace.army.mil/ords/f?p=107:278:171517103963:::RP,278:P278_BANK_ID:5271 <https://ribits.ops.usace.army.mil/ords/f?p=107:278:171517103963:::RP,278:P278_BANK_ID:5271>
IRT-DMS SharePoint Page: https://ncconnect.sharepoint.com/sites/IRT-DMS/SitePages/Home.aspx <https://ncconnect.sharepoint.com/sites/IRT-DMS/SitePages/Home.aspx>
Thank you,
Erin
Erin B. Davis
Mitigation Specialist, Regulatory Division I U.S. Army Corps of Engineers l (919) 930-1887