HomeMy WebLinkAbout20020730 Ver 4_More Info Received_20221221From:
Mcdaniel, Chonticha
To:
Snider, Hollev; Davis. Erin B
Subject:
RE: [External] RE: NCDCR - USS Battleship, Major Permit Application Status - On Hold
Date:
Wednesday, December 21, 2022 10:20:26 AM
Attachments:
imaae002.ona
imaae005.pnna
Hi Holley,
I just had a chance to finish my review for this project. According to their original application and
responses to your additional information request, I do see this project as an improvement to the
current condition regarding stormwater retention and treatment (even if they do not meet the
MDC). They can easily claim the "re -development" status with the post -construction BUA being LESS
than the current BUA and do nothing extra for stormwater management. I'm glad they didn't choose
that route because the main purpose of this project is to address flooding. It seems to me their
proposed measures are reasonable (bioswale/SW wetland/permeable pavement at the overflow
parking lot). However, we may be able to ask for the O&M plan and agreement for these measures
and include them as part of the 401 permit requirements. Since they already have the wetland
monitoring plan, they can add 0&M to it.
Thanks,
Chonticha McDaniel (she/her/hers)
401 Stormwater Engineer, Division of Water Resources
North Carolina Department of Environmental
Quality
Office: (919) 707-3634
chonticha.mcdanielCcDncdenr.gov
NORTH CA�NAA_
Depa"meM of Environmental Dual ;11441�
Email correspondence to and from this address is subject to the North
Carolina Public Records Law and may be disclosed to third parties.
From: Snider, Holley <holley.snider@ncdenr.gov>
Sent: Friday, December 9, 2022 11:52 AM
To: Mcdaniel, Chonticha <chonticha.mcdaniel@ncdenr.gov>; Davis, Erin B <erin.davis@ncdenr.gov>
Subject: RE: [External] RE: NCDCR - USS Battleship, Major Permit Application Status - On Hold
Good morning and happy Friday,
I am working on a request to the USACE to extend the reasonable period of time for this project to
one year from the date of receipt (8/17). The USACE has a pending RFAI to which the applicant has
yet to respond. I am hope the request will be granted. A denial from the DWR for CAMA projects
can become quickly problematic from a processing standpoint. I am hopeful the request to extend
the RPOT will be granted. Let me know if you have any questions.
Sincerely,
Holley Snider ,������°>•, .. ..><((((°>.• -
Environmental Specialist II
Division of Water Resources
North Carolina Department of Environmental Quality
Phone: (910) 796-7303
-., �,D- E
N TII .t
Ik a �
mo-
127 Cardinal Drive Ext.
Wilmington, NC 28405
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties
From: Mcdaniel, Chonticha <chonticha.mcdanielPncdenr.gov>
Sent: Thursday, December 8, 2022 9:10 AM
To: Snider, Holley <holley.sniderCcDncdenr.gov>; Davis, Erin B <erin.davis(@ncdenr.gov>
Subject: RE: [External] RE: NCDCR - USS Battleship, Major Permit Application Status - On Hold
Hi Holley,
What's your timeframe for this project? I'll try to squeeze this in my project list for review next
week. Thanks!
Chonticha McDaniel (she/her/hers)
401 Stormwater Engineer, Division of Water Resources
North Carolina Department of Environmental
Quality
Office: (919) 707-3634
chonticha.mcdaniel(@ncdenr.gov
NORTH CAROLINAD_ E Q�1�
Department of En,imnmantal Qual;1`11�
Email correspondence to and from this address is subject to the North
Carolina Public Records Law and may be disclosed to third parties.
From: Snider, Holley <holley.snider(@ncdenr.gov>
Sent: Friday, December 2, 2022 12:01 PM
To: Mcdaniel, Chonticha<chonticha.mcdaniel(@ncdenr.gov>; Davis, Erin B <erin.davis(@ncdenr.gov>
Subject: FW: [External] RE: NCDCR - USS Battleship, Major Permit Application Status - On Hold
Good afternoon Chonticha and Erin,
I am hopeful you may have a moment to look over this project (DWR#20020730v4) and provide
some comments. There is a substantial amount of wetland alteration and improvements to
stormwater treatment. I am concerned that the constructed wetland may not provide sufficient
treatment to protect downstream waters which are designated as PNA and EFH. If you do not have
access to LF please let me know and I can send a link to the files. Any assistance you can provide
would be greatly appreciated, thanks in advance.
Sincerely,
Holley Snider . " ,><((((�>•' ' . ..><((((°>. '-
Environmental Specialist 11
Division of Water Resources
North Carolina Department of Environmental Quality
Phone: (910) 796-7303
0 E Q�*
^^^��� �j
R1PN1nMIK M N Oaall
127 Cardinal Drive Ext.
Wilmington, NC 28405
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties
From: York, Dawn <dyork(@moffattnichol.com>
Sent: Friday, November 11, 2022 11:31 AM
To: Luck, Cameron A <Cameron.Luck(@ncdenr.gov>
Cc: Currey, Gregory E CIV USARMY CESAD (USA) <Gregory.E.CurreyC@usace.army.mil>; Snider, Holley
<holley.snider(@ncdenr.gov>; MacPherson, Tara <tara.macphersonPncdenr.gov>; Martinez, Jose
<iosemartinezC@moffattnichol.com>; Ryan Smith <rsmith(@swiftcg.com>; DeMeo, Terry A
<terry.demeo(@ncdcr.gov>; Vargo, Christopher <Christopher.Vargo(@ncdcr.gov>; Johnson, Kelly
<kelly_p.johnson(@ncdenr.gov>; Marchisin, Samantha <smarchisin(@moffattnichol.com>; Huggett,
Douglas <dhuggett(@moffattnichol.com>
Subject: RE: [External] RE: NCDCR - USS Battleship, Major Permit Application Status - On Hold
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an
attachment to Report Spam.
Hello Cameron, we have addressed the comments and questions provided by the Division of Water
Resources (email dated 10/18/22) and the NC Wildlife Resources Commission (comments provided
10/19/22) in the attached letter.
Please let us know if this information is sufficient to take the project off hold and allow for the
permit review process to continue.
We appreciate your time and look forward to continuing to work with you and the agencies on the
Battleship NC's Living with Water project.
Thank you and hope you have a good holiday weekend,
Dawn
Dawn York
Senior Coastal Planner
Moffatt & Nichol
238 Princess St. I Wilmington, NC 28401
P 910.218.7087 1 C 910.612.1152
From: Luck, Cameron A <Cameron.Luck(@ncdenr.gov>
Sent: Wednesday, October 19, 2022 5:27 PM
To: York, Dawn <dyork(@moffattnichol.com>
Cc: Currey, Gregory E CIV USARMY CESAD (USA) <Gregor)I.E.CurreyCcDusace.army.mil>; Snider, Holley
<holley.sniderPncdenr.gov>; MacPherson, Tara <tara.macpherson(@ncdenr.gov>; Martinez, Jose
<iosemartinezr@moffattnichol.com>; Ryan Smith <rsmith(@swiftcg.com>
Subject: RE: [External] RE: NCDCR - USS Battleship, Major Permit Application Status - On Hold
My apologies. See attached for WRC comment sheet.
Best,
Cameron Luck
Assistant Major Permits Coordinator
North Carolina Division of Coastal Management
North Carolina Department of Environmental Quality
(252) 515-5419 - office
Cameron.Lucka-ncdenr.gov
NORT �RCLINA
D,p —ffl of E,,I--I Quality
400 Commerce Avenue
Morehead City, NC 28557
http://portal.ncdenr.org/web/cm/dcm-home
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
From: York, Dawn <dvork(@moffattnichol.com>
Sent: Wednesday, October 19, 2022 4:37 PM
To: Luck, Cameron A <Cameron.Luck(@ncdenr.gov>
Cc: Currey, Gregory E CIV USARMY CESAD (USA) <Gregory.E.Currey(@usace.army.mil>; Snider, Holley
<holley.sniderPncdenr.gov>; MacPherson, Tara <tara.macphersonC@ncdenr.gov>; Martinez, Jose
<iosemartinez(@moffattnichol.com>; Ryan Smith <rsmith(@swiftcg.com>
Subject: [External] RE: NCDCR - USS Battleship, Major Permit Application Status - On Hold
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an
attachment to Report Spam.
Thank you Cameron, email received. The attached letter references comments by NCWRC however
they are not attached or included in the letter. Can you please provide NCWRC's comments?
Thank you,
Dawn
Dawn York
Senior Coastal Planner
Moffatt & Nichol
238 Princess St. I Wilmington, NC 28401
P 910.218.7087 1 C 910.612.1152
From: Luck, Cameron A <Cameron.Luck(@ncdenr.gov>
Sent: Wednesday, October 19, 2022 4:24 PM
To: York, Dawn <dvork(@moffattnichol.com>
Cc: Currey, Gregory E CIV USARMY CESAD (USA) <Gregor)I.E.CurreyCcDusace.army.mil>; Snider, Holley
<holley.snider(@ncdenr.gov>; MacPherson, Tara <tara.macpherson(@ncdenr.gov>
Subject: NCDCR - USS Battleship, Major Permit Application Status - On Hold
CAUTION: This email originated from outside of the organization.
Good Afternoon,
This email has been sent to notifying you that the Major Permit Application for NCDCR is currently
on hold while the DWR request for additional information is being completed. I have the NCWRC
comments for reference. Any new comments will be provided as they are received.
Feel free to let me know if you have any questions,
Best
Cameron Luck
Assistant Major Permits Coordinator
North Carolina Division of Coastal Management
North Carolina Department of Environmental Quality
(252) 515-5419 - office
Cameron. Luck&ncdenr.gov
N-T111CAR-ND_E
oenann,em or eem.oememai ouar� /�
400 Commerce Avenue
Morehead City, NC 28557
http://portal.ncdenr.org/web/cm/dcm-home
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.