HomeMy WebLinkAboutSWA000211_Construction Sequence_20230613BASIC CONSTRUCTION SEQUENCE
1. GRADING AVAILABLE AREA
1)
OBTAIN EROSION AND SEDIMENT CONTROL PERMIT
2)
GRADE DEVELOPMENT AREAS 1 & 2
3)
ESTABLISH TEMPORARY ACCESS TO LOT 75/76 AND/OR 76/77 AS
2. SECONDARY
EMERGENCY ENTRANCE
3. BUILD OUT DEVELOPMENT AREA 1
1.
CONSTRUCT SEWER RUN A-B-C, PARTIAL D
2.
INSTALL WATER DISTRIBUTION FOR DEVELOPMENT AREA 1
3.
CONSTRUCT OFFSITE ROADWAY IMPROVEMENTS
4.
OBTAIN AUTHORIZATION TO CONSTRUCT FROM NCDEQ STORMWATER
5.
INSTALL CURB AND GUTTER AND ROAD IMPROVEMENTS FOR RICELAND WAY, PLUMMER
COURT, AND PORTION OF MAYA LANE
6.
CONSTRUCT HOUSES ON AVAILABLE LOTS
4. GRADING DEVELOPMENT AREA 3
1.
STREAM CROSSINGS IN CONSECUTIVE ORDER
5. BUILD OUT 2ND ENTRANCE TO SW CORNER OF MUDDY CREEK ROAD
6. CONNECTION AS THE NEW SECONDARY EMERGENCY ACCESS.
1.
THEN REMOVE LOT 75/76/77 PREVIOUS SECONDARY ACCESS
7. BUILD OUT DEVELOPMENT AREA 2
1.
INSTALL SEWER WITHIN DEVELOPMENT AREA
2.
INSTALL WATER DISTRIBUTION FOR DEVELOPMENT AREA
3.
OBTAIN AUTHORIZATION TO CONSTRUCT FROM NCDEQ STORMWATER
4.
INSTALL CURB AND GUTTER AND ROAD IMPROVEMENTS FOR FORAGER PLACE AND
REMAINDER OF MAYA LANE
5.
CONSTRUCT HOUSES ON AVAILABLE LOTS
8. BUILD OUT DEVELOPMENT AREA 3
1.
INSTALL SEWER WITHIN DEVELOPMENT AREA
2.
INSTALL WATER DISTRIBUTION FOR DEVELOPMENT AREA
3.
OBTAIN AUTHORIZATION TO CONSTRUCT FROM NCDEQ STORMWATER
4.
INSTALL CURB AND GUTTER AND ROAD IMPROVEMENTS FOR MIDLAND CROSSING
DRIVE AND MUDDY CREEK ROAD
5.
CONSTRUCT HOUSES ON AVAILABLE LOTS