Loading...
HomeMy WebLinkAbout20180134 Ver 2_Lake Tahoma IP DEQ additional information 6.8.2023_20230608 CLearWaLer An EnviroScience Company g ClearWater Environmental Consultants, Inc. www.cwenv.com June 8, 2023 Ms. Sue Homewood NC Division of Water Resources 401 & Buffer Permitting Branch 1611 Mail Service Center Raleigh, North Carolina, 27699-1611 Sue.Homewood(a)-ncdenr.gov RE: Response to DEQ Comments Lake Tahoma Dredge Project Individual Permit Application McDowell County, North Carolina SAW-1997-02095 Dear Ms. Homewood, Regarding Lake Tahoma, Inc.'s Individual Permit application for the Lake Tahoma Dredge Project, ClearWater, an EnviroScience Company (ClearWater) provides the following information in response to DWR's request letter dated May 12, 2023. DWR 1. The application states that the justification for the dredging material to be placed in treatment cells in Orchard Meadow is that the hydraulic dredging method requires adjacent disposal. It is unclear if the dredge material from the mechanical dredging to occur behind the cofferdams within Buck Creek and Little Buck Creek is also proposed to be disposed in the Orchard Meadow Treatment Cells. Further avoidance and minimization of secondary impacts to Orchard Creek and Lake Tahoma are possible by minimizing the use of the treatment cells in Orchard Meadow and continuing to use prior disposal areas for areas that are mechanically dredged. Response: The disposal area for the Buck Creek cofferdam, Miller Farm, is only a temporary site where material is temporarily stored for processing and sale to the public. Miller Farm was used for disposal because the field adjacent to Buck Creek is too small for long term storage. This site is also approximately two miles south, which increases the overall cost of the project for trucks traveling back and forth. The disposal area for the Little Buck Creek cofferdam was permitted for 3,000 yds3 (SAW- 1997-02095). Continued mechanical dredging from behind the cofferdam will use this site for disposal until full. This is a small area and it is expected that 3,000 to 5,000 additional yds3 could be stored there in the future; this small storage area does not have enough volume to reduce the size and need for storage at the Orchard Meadows site. DWR 2. The project application states "At the mouth of Orchard Creek with Lake Tahoma, a Type 3, double floating silt curtain turbidity barrier will be placed approximately 80 feet into the lake to prevent any silt created by dredging discharge or construction operations from flushing into the lake (Attachment A). The curtain will be elevated above the lake bottom more than two feet." It appears you expect elevated turbidity within Orchard Creek as a result of dewatering discharge and are proposing to use Orchard Creek(WS-11,B;HQW) as a treatment zone for the dredge slurry discharge. The dredge slurry must be adequately treated prior to discharge into Orchard Creek to ensure that all water quality standards for WS-11; 8; HQW are met at the discharge point. Please provide a proposed dewatering plan and/or return water treatment plan that will not cause a violation of the water quality standard for turbidity in Orchard Creek, which is 50 NTU in accordance with 15A NCAC 028.0211(21). Response: The applicant doesn't expect to use Orchard Creek as a treatment zone, the floating silt curtain is just an added precaution. The applicant is using the two-chamber sediment basin as required by DWR under NWP 16, which we expect would be the appropriate NWP if this was not an Individual Permit application due to previous permits. The applicant is willing to remove the silt curtain if DWR prefers. No turbidity issues are expected from dredging activities and disposal in the storage cells. The cells will have protective measures that include phase separation dikes, riser outlets surrounded by rock filter, rock protected culvert outlets that dissipate discharge, and a 25-foot stream buffer. The dewatering plan would be as follows: • For cells 1 to 6, dredged material would be pumped into each cell up to a 2-foot freeboard from the cell's containment crest. For cells 7 and 8, dredged material would be pumped to the height of the phase separation dike (10 feet). • Cell performance would be monitored during dredging disposal and the discharge moved as needed to manage spoils accumulation. • For cells 7 and 8, the phase separator dike would be raised in 10-foot increments to accommodate new material. • Once a cell is full, the hydro-dredge pipe would be moved to discharge material into a new cell. • Dredge material would be allowed to dry through ground infiltration, evaporation, and flow-through. • Once a cell is full and dry, the remaining freeboard would be filled in with dry sediment from adjacent cells, the top of the containment cell would be graded to achieve positive drainage, and the cell vegetated for permanent stabilization. DWR 3. The applicant is proposing to hydraulically dredge the lake (i.e., excavate "in the wet'). The application states that turbidity impacts are not expected to go below the dam, however, the water quality standard for turbidity in Lake Tahoma (WS-11, 8; Tr, HQW) is 10 NTU in accordance with 15A NCAC 02B .0211(21). The remaining area of the lake should not be used as a treatment zone for any turbidity created during dredging activities. Please provide a hydraulic dredge plan that includes a turbidity curtain proposed around the dredge area during all dredging operations to prevent turbidity outside the immediate work area. Response: Hydraulic dredging involves the suction of silt, sediment and debris from the bottom of the lake into the disposal tube; it should not cause movement of material away from the suction head. Therefore, we do not expect dredging activities to exceed turbidity standards in Orchard, Creek, Lake Tahoma, or downstream of the dam; and installing a turbidity curtain around the lake dredge area would not be practical. To prevent backflush of silt each time hydro-dredging activities stop, the suction head would be lifted off the lake bottom to pump only water through the pipe and flush any remaining material into an Orchard Meadow containment cell. DWR 4. The application states that a temporary stream crossing is necessary to construct Cell 8 but will be removed and reinstalled when Cell 8 is needed. Please explain why construction of Cell 8 is necessary prior to the time it is required. Please explain how long the temporary crossing is proposed to be in place during construction. Response: Cell 8 would be the last storage cell used for discharge material and will not be constructed until needed. The construction sequence will be revised so the access road culvert and cell 8 are constructed simultaneously. The access road culvert would only be in place as long as required to fill the cell with dredge material and complete the dewatering closure steps described in Response #1 above. Using a bridge instead of a culvert was not considered a viable alternative due to the bridge's higher cost. A bridge would also be a permanent feature to the landscape whereas the culvert would be temporary and allow the landscape and stream to recover to current conditions. Removing cell 8 from the project design was also not considered a practical alternative. The current Orchard Meadow discharge site design accommodates the estimated volume of lake sediments found during the 2020 bathymetric survey as well as anticipated dredging over the permit period. The applicant believes the information submitted in this letter addresses the comments provided by DWR. Should you have any further questions or comments, please contact me anytime at eromaniszyn@enviroscienceinc.com or 828-698-9800. Thank you. Sincerely, Eric Romaniszyn Senior Scientist Copy issued: Amanda Jones - US Army Corps of Engineers Stephanie Goss - NC Department of Environmental Quality Joey Winston - NC Department of Environmental Quality Andrea Leslie - NC Wildlife Resources Commission Paul Coughlin - President, Lake Tahoma, Inc. Robert Cottam — Porus, LLC Clement Riddle - ClearWater, an EnviroScience Company