HomeMy WebLinkAbout20050150 Ver 3_Emails_20071019Re: Green Oaks Parkway. Town of Holly Springs
Subject: Re: Green Oaks Parkway. Town of Holly Springs
From: Cyndi Karoly <cyndi.karoly@ncmail.neV
Date: Fri, 19 Oct 2007 12:56:23 -0400
To: "Manuele, Jean B SAW" <Jean.B.Manuele@saw02.usace.army.mil>
CC: Harlan.Britt@kimley-horn.com, Chad.Evenhouse@kimley-horn.com, "Matthews, Monte K SAW"
<Monte.K.Matthews@saw02.usace.army.mil>, "McCorcle, Justin P SAW" <Justin.P.McCorcle@saw02.usace.army.mil>,
Danny Smith <danny.smith@ncmail.net>, Ian McMillan <ian.mcmillan@ncmail.net>, Laurie J Dennison
<Laurie.J.Dennison@ncmail.neV
Harlan - considering that the verdict is still out on what type of permit will ultimately be applied to
this project, we cannot proceed with issuance of the 401 as you requested, nor is is waived. Furthermore,
please note that you should include DWQ in your correspondence reflecting the decision the Town intends to
take with regards to the existing and proposed actions at the site. When you arrive at your conclusion,
please be sure to provide us five copies of your updated application materials reflecting the corrected
impacts and project description details. We would anticipate treating this application in a similar
fashion regarding enforcement versus an Individual Certification. Please advise of the Town's decision.
Thanks very much, and I hope you have a great weekend as well.
Manuele, Jean B SAW wrote:
Harlan,
I have spoken with Justin and while we recognize that the impacts for permanent impacts at one crossing
now total 306 feet of permanent impacts versus the permitted 294', and that the Corps now has the
ability to require a Department of the Army (DA) individual permit. However, while we might tend toward
proceeding with the remediation through enforcement protocol versus the individual permit, we would
prefer an official response from the town prior to finalizing that decision.
My apologies for not having gotten to this the yesterday, but i got tied up with other issues and it
slipped my mind until it was after 5 and likely wouldn't have helped at that point.
Hope you have a great weekend,
Jean
*From:* Harlan.Britt~kimley-horn.com [mailto:Harlan.Britt@kimley-horn.
*Sent:* Wednesday, October 17, 2007 4:05 PM
*TO:* Manuele, Jean B SAW
*Cc:* Chad.Evenhouse@kimley-horn.com
*Subject:* Green Oaks Parkway. Town of Holly Springs
Jean, could you provide me with a response to the following question related to the subject project?
Has the Corps made a decision as to whether or not the agency will require an Individual Permit for the
project under construction at this time and if so what can I tell the town related to that decision?
Thank you for your help in bringing this situation closer to resolution and I we will be getting you
the survey information on the as-built vs.. permitted impacts within the next couple of days. I will be
out of the office until next Monday but will have Chad Evenhouse coordinate getting information to you
and Monte and if you have questions, please feel free to call Chad at 677-2121.
Harlan
**Harlan K. Britt, P.E.**
Kimley-Horn and Associates, Inc
P.O. Box 33068
Raleigh, North Carolina 27636-3068
(919) 677-2209
harlan.britt@kimley-horn.com