HomeMy WebLinkAbout20190661 Ver 1_Sassarixa Swamp II MY2 Adaptive Management Follow Up Report_20230601
June 1, 2023
CREDIT RELEASE REQUEST FORM
To: NCDEQ-DWR Nutrient Offset & Buffer Banking Coordinator
From: Kaitlyn Hogarth (khogarth@wildlandseng.com, 540-907-9432)
Through: Wildlands Holdings III, LLC
We formally request the remainder of the credit release for the Sassarixa Swamp II Nutrient Offset
and Buffer Mitigation Bank Parcel for completion of Task 5 per the approved credit release schedule,
which is included in the Attachments with this request. The following documents have been
submitted to DWR for Task 5 and are pending review: Sassarixa Swamp II Nutrient Offset and
Buffer Mitigation Bank Parcel Monitoring Year 2 Supplemental Report.
Credits requested for release are detailed below:
Credit Type % Release Credit Amount
(include Units)
Notes/Comments
Buffer Restoration 5% 14,187.600 Square Feet
Buffer Preservation NA NA
Buffer Enhancement 5% 1,714.381 square feet1
3,116.487 Square feet2
Enhancement and
enhancement via
cattle exclusion1
Coastal headwater2
Generated Nitrogen Nutrient
Offset
5% 1,675.600 pounds
Delivered Nitrogen Nutrient
Offset (Jordan sites only)
NA NA
Generated Phosphorus Nutrient
Offset
NA NA
Delivered Phosphorus Nutrient
Offset (Jordan sites only)
NA NA
Signature:
Attachments: 1) Approved Project Credit Table (include the most recent Asset Table approved by
DWR, whether it is the BPDP table or the As-Built table), 2) Approved Credit Release Schedule
Include the approved credit release schedule, whether it is the credit release schedule from the
MBI/UMBI or from the BPDP,
Project Area
N Credit Conversion Ratio (ft2/pound)
P Credit Conversion Ratio (ft2/pound)
Credit Type Location
Subject?
(enter NO if
ephemeral or
ditch 1)
Feature Type Mitigation Activity
Min-Max
Buffer
Width (ft)
Feature Name Total Area (ft2)
Total
(Creditable)
Area of Buffer
Mitigation (ft2)
Initial
Credit
Ratio
(x:1)
% Full
Credit
Final
Credit
Ratio (x:1)
Convertible
to Riparian
Buffer?
Riparian Buffer
Credits
Convertible
to Nutrient
Offset?
Delivered
Nutrient
Offset: N
(lbs)
Delivered
Nutrient
Offset: P
(lbs)
Buffer Rural No Ephemeral Restoration 0-100 T3 25,770 25,770 1 100%1.00000 Yes 25,770.000 Yes 1,344.713 —
Buffer Rural Yes Coastal Headwater Restoration 0-100 T5C 29,697 29,697 1 100% 1.00000 Yes 29,697.000 No — —
Buffer Rural Yes Coastal Headwater Restoration 101-200 T5C 98,887 98,887 1 33% 3.03030 Yes 32,632.743 No — —
Buffer Rural Yes I / P Restoration 0-100
T1, T1A, T1B,
T3, T4, T5, T5A,
T5B, T6
257,982 257,982 1 100% 1.00000 Yes 257,982.000 Yes 13,461.846 —
Nutrient Offset Rural Yes I / P Restoration 101-200
T1, T1A, T1B,
T3, T4, T5, T5A,
T5B, T6
506,891 1 33%No —Yes 26,450.250 —
Buffer Rural Yes I / P Enhancement via
Cattle Exclusion 0-100 T1, T1A, T3, T6 53,353 53,353 2 100% 2.00000 Yes 26,676.500 No — —
Buffer Rural Yes I / P
Enhancement via
Cattle Exclusion 101-200 T1, T1A, T3, T6 46,128 46,128 2 33% 6.06061 Yes 7,611.115 No — —
Nutrient Offset Rural No Ditch Restoration 0-200 T3 135,331 135,331 1 100%1.00000 No —Yes 7,061.752 —
Totals (ft2):1,154,039 647,148 380,369.358 48,318.561 0.000
Total Buffer (ft2):511,817 511,817
Total Nutrient Offset (ft2):642,222 N/A
Square Feet Credits
919,227 513,355.940
99,481 34,287.615
0 0.000
1,018,708 547,643.555
Square Feet Credits
Nitrogen:7,061.752
Phosphorus:0.000
Nutrient Offset:135,331
Enhancement:
Preservation:
Total Riparian Buffer:
TOTAL NUTRIENT OFFSET MITIGATION
Mitigation Totals
#N/A
TOTAL AREA OF BUFFER MITIGATION (TABM)
Mitigation Totals
Restoration:
Table 1. Buffer Project Areas and Assets
Sassarixa Swamp II Nutrient Offset and Buffer Mitigation Bank Parcel
Monitoring Year 0 - 2021
Neuse 03020201 - Outside Falls Lake
19.16394
Sassarixa Swamp Credit Release Schedule
Task Project Milestone
% Credit
Available
for Sale
% Riparian Buffer Credit
Release within Coastal
Headwaters Areas
1 Instrument and BPDP Approved by DWR, Conservation Easement Recorded,
Financial Assurance Posted, and Draft Stream Mitigation Plan Approved by IRT 20 None
2 Mitigation Site Earthwork, Planting and Installation of Monitoring Devices
Completed, and all Applicable Permits Obtained 20 None
3 Monitoring Financial Assurance Posted and Approval of As‐Built Report 10 25
4 Monitoring Report #1: Approved by the DWR * & financial assurance renewed 10 10
5 Monitoring Report #2: Approved by the DWR * & financial assurance renewed 10 10
6 Monitoring Report #3: Approved by the DWR * & financial assurance renewed 10 5
7 Item B(1) of Section X in this Instrument has been completed and approved by
DWR 5 5
No remaining credits will be released until the conservation easement has
been assigned to an approved land trust or stewardship
8 Monitoring Report #4: Approved by the DWR * & financial assurance renewed 5 5
9
Monitoring Report #5: Approved by the DWR* & financial assurance renewed
for coastal headwater buffer areas, and final site visit by DWR has been
conducted for nutrient offset areas
10 20
10 Monitoring Report #6: Approved by the DWR* & financial assurance renewed
for coastal headwater buffer areas N/A 10
11 Monitoring Report #7: Approved by the DWR* & final site visit by DWR has
been conducted for coastal headwater buffer areas N/A 10
Total 100% 100%
Sassarixa Swamp II Nutrient Offset and Buffer Mitigation Bank Parcel
DWR ID# 2019-0661
Wildlands Holdings III, LLC’s Sassarixa Swamp II Nutrient Offset and Buffer Mitigation Bank
Monitoring Year 2
Supplemental Report
June 2023
PREPARED BY:
Wildlands Engineering, Inc.
312 West Millbrook Road, Suite 225
Raleigh, NC 27609
Phone: 919-851-9986
_____________________________________________________________________________________
Sassarixa Swamp II Nutrient Offset and Buffer Mitigation Bank Parcel Page ii
Monitoring Year 2 Supplemental Report
MONITORING YEAR 2 REPORT
Supplemental Report
Sassarixa Swamp II Nutrient Offset and Buffer Mitigation Bank Parcel
Wildlands Holdings III, LLC’s Sassarixa Swamp II Nutrient Offset and Buffer Mitigation Bank
TABLE OF CONTENTS
1.0 Introduction ..............................................................................................................................1
2.0 Adaptive Management Activities ...............................................................................................1
2.1 Supplemental Planting .................................................................................................................. 1
2.2 Soil Conditions .............................................................................................................................. 2
2.3 Conclusion ..................................................................................................................................... 2
3.0 References ................................................................................................................................3
LIST OF TABLES
Table 1 Adaptive Management History
Table 2 Planting Density by Area
Table 3 Tree Species Selected for Supplemental Planting
ATTACHMENTS
Figure 1 Adaptive Management Map
Adaptive Management Photographs
_____________________________________________________________________________________
Sassarixa Swamp II Nutrient Offset and Buffer Mitigation Bank Parcel Page 1
Monitoring Year 2 Supplemental Report
1.0 Introduction
The Sassarixa Swamp II Nutrient Offset and Buffer Mitigation Bank Parcel (Parcel) Monitoring Year 2
(MY2) Report was submitted to the North Carolina Division of Water Resources (NCDWR) on October 17,
2022. Within the MY2 Report, a supplemental planting for the Parcel was outlined (Wildlands, 2022).
Wildlands Engineering received a request from NCDWR on January 18, 2023, to provide additional
documentation on the supplemental planting. Wildlands submitted a Technical Memorandum in
response, outlining in detail the proposed adaptive management actions. NCDWR issued a partial credit
release of 5% on May 1, 2023. The remainder 5% of credits will be released when NCDWR receives
confirmation that Wildlands fully implemented the actions documented in the Technical Memorandum.
A list of management actions outlined in the MY2 Report, along with their completion date are shown in
Table 1.
Table 1. Adaptive Management History
Activity Completion Date
Supplemental Planting February 2023
Ring Sprays with
Root Stimulator and Fish Emulsion April 2023
Soil Amendments April 2023
2.0 Adaptive Management Activities
2.1 Supplemental Planting
During MY2 tree mortality occurred across portions of the Parcel at a rate that suggested the
performance standards may not be met. This mortality was not noted in the MY2 report, as the extent
was unknown to Wildlands at the time. This is due to a combination of dense herbaceous vegetation,
characteristically low tree height, and comparatively lower rates of mortality within vegetation plots.
Following the submittal of the MY2 report herbaceous vegetation began to die-off, allowing for a better
assessment of Parcel conditions. Additional site walks were then conducted in which Wildlands noted
varying degrees of tree mortality along parts of T1, the ditch above T3, T4, T5A, and T5C due to dry
conditions within the Parcel.
Bruton Landscaping completed a supplemental planting of 8.51 acres across the Parcel on February 13,
2022. Due to non-uniform tree mortality across the Parcel, a range of planting densities was
implemented in the February 2023 supplemental planting. A visual depiction of the planted area can be
seen in Figure 1.
Table 2. Planting Density by Area
Area Acres Planting Density Per Acre
UT1 – Right Bank 0.75 200
UT1 – Left Bank 2.16 400
UT3 1.34 250
UT4 0.96 250
UT5A 1.00 100
UT5C 2.30 300
Total 8.51 ---
_____________________________________________________________________________________
Sassarixa Swamp II Nutrient Offset and Buffer Mitigation Bank Parcel Page 2
Monitoring Year 2 Supplemental Report
Species selected for planting were those that were approved by NCDWR in the Sassarixa Swamp II
Nutrient Offset and Buffer Mitigation Bank Parcel Development Package (Wildlands, 2019). Table 2
below lists species selected along with their planted quantities and composition. Photographs following
the supplemental planting are in the attachments.
Table 3. Tree Species Selected for Supplemental Planting
Species Common Name Type Stems per Species Planting Composition
Populus deltoides Eastern Cottonwood Bare Root 172 7%
Magnolia virginiana Sweetbay Magnolia Bare Root 147 6%
Acer negundo Box Elder Bare Root 245 10%
Quercus nigra Water Oak Bare Root 172 7%
Quercus michauxii Swamp Chestnut Oak Bare Root 367 15%
Platanus occidentalis Sycamore Bare Root 490 20%
Quercus phellos Willow Oak Bare Root 367 15%
Betula nigra River Birch Bare Root 490 20%
Totals 2,450 100%
2.2 Soil Conditions
It is suspected that tree mortality was due to high floodplain elevations compared to the stream portion
of the project, causing low soil moisture within the Parcel. Additionally, several years of drought that
occurred after the original planting might have further exacerbated stem die-off. It is not believed that
species selection or poor soil nutrient or pH levels were the cause of tree mortality. To ensure better
tree survival with the February 2023 supplemental planting, Wildlands implemented additional
management actions throughout the spring. Ring sprays were conducted within supplemental planting
areas on April 15th and 16th to reduce herbaceous competition. A root stimulator and fish emulsion were
also sprayed at the base of each supplementally planted tree when ring sprays were conducted. The
root stimulator and fish emulsion are expected to help retain soil moisture. While soil nutrient levels
were not believed to be a factor in stem loss, soil amendments were applied in a localized manner
around planted trees in late April in case higher nutrient content aids in tree growth and survival.
2.3 Conclusion
An 8.51-acre supplemental planting occurred in February 2023. The suspected cause of widespread
planted stem fatality was dry Parcel conditions due to landscape position. Wildlands does not believe
species selection or soil conditions related to nutrient content or pH were factors in stem loss. It is
anticipated that the new stems that were treated with root stimulator, fish emulsion, and soil
amendments will have a greater chance of survival.
Throughout the remainder of the Parcel adaptive measures will be developed, or appropriate remedial
actions will be implemented if the Parcel or a specific component of the Parcel fails to achieve the
success criteria outlined in the Bank Parcel Development Package. Parcel maintenance will be
performed to correct any identified problems that have a high likelihood of affecting project success.
Going forward, Wildlands will notify DWR of any adaptive management actions needed.
_____________________________________________________________________________________
Sassarixa Swamp II Nutrient Offset and Buffer Mitigation Bank Parcel Page 3
Monitoring Year 2 Supplemental Report
3.0 References
Wildlands Holdings III, LLC (2022). Sassarixa Swamp II Nutrient Offset and Buffer Mitigation Bank Parcel
Monitoring Year 2 Report. NCDWR, Raleigh NC.
http://portal.ncdenr.org/web/wq/nutrientbufferbanks
Wildlands Holdings III, LLC (2019). Sassarixa Swamp II Nutrient Offset and Buffer Mitigation Bank Parcel
Development. NCDWR, Raleigh NC. http://portal.ncdenr.org/web/wq/nutrientbufferbanks
[
[
[
[
[
[[
[
[
[
[
[
[[[[[[[
[
[
[
[
[
[
[
[
[
[
[
[
[[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[[
[
[
[
[
[
[
[
[
[[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[[[
[
[
[
[
[[
[
[
[
[
[[[[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[[
[
[
[
[
[
[
[
[[
[[
[[[
[[
[[
[
[
[
[
[
[
[
[
[
[
[
[[[[[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[
[[[
[
[
[
[[[[
[[[
[
[
[
[
[[[
[
[
[[
[
[[[
[
[
[
[[[[
[[
[
[
[
[
[
[
[[[[
[
[
ÛÚ
ÛÚ ÛÚ
ÛÚÛÚ
ÛÚ
ÛÚ
ÛÚ
ÛÚ
ÛÚ
ÛÚ
ÛÚ
ÛÚ
ÛÚ
ÛÚ
ÛÚ
ÛÚ
ÛÚ
ÛÚ
ÛÚ ÛÚÛÚ
ÛÚ
ÛÚ ÛÚ
ÛÚ
T2
T
5
A
T5C
T
5
B
T1A
T1
C
T
1
B
T4
S
a
s
s
a
r
i
x
a
C
r
e
e
k
T3 T6
T5
T1
T1DT1
Figure 1. Adaptive Management Map
Sassarixa Swamp II Nutrient Offset and
Buffer Mitigation Bank Parcel
February 2023 Supplemental Planting
Neuse River Basin (03020201)
2021 Aerial Photography
¹0 1,000500 Feet
Johnston County, NC
NCDMS Conservation Easement
Bank Conservation Easement
Project Stream
Project Ephemeral Channel
Project Ditch
Mitigation Approach
Buffer Restoration
Coastal Headwaters
Cattle Exclusion
Nutrient Offset
Not for Credit
Utility Easement
Vegetation Plots
Supplemental Planting
Surveyed Treeline
[Fencing
ÛÚ Gates
ADAPTIVE MANAGEMENT PHOTOGRAPHS
Sassarixa Swamp II Nutrient Offset and Buffer Mitigation Bank Parcel
Adaptive Management Photographs
Vegetation Plot - Blue Flagging Denotes Supplemental Stems (2/27/2023)
Supplementally Planted Stem (3/7/2023)
Sassarixa Swamp II Nutrient Offset and Buffer Mitigation Bank Parcel
Adaptive Management Photographs
Ring Sprays with Root Stimulator and Fish Emulsion (5/31/2023)
Overview Photograph Depicting Ring Sprays (5/31/2023)