NARRATIVE: Use this section to describe the method(s) that will be used to lower the sludge
depth. -If microbe use is planned, specify the product to be used.
Sludge ManagementfOperation Plan
Sludge Management Guide
Lagoon evaluation data developed by NCSU and a review of lagoon management records of several lagoons
showed that treatment capacity of the swine lagoons evaluated In NC was not significantly adversely affected
by sludge accumulations of 50% or more of the planned treatment volume of the lagoon . Therefore It is felt
that it is permissible to allow sludge accumulation into the planned treatment zone of properly monitored and
managed lagoons provided that:
• Nutrient values of the lagoon effluent are within the normal operating range.
There Is no noticeable increase in lagoon odor.
• Nutrients land applied from the lagoon are properly accounted for in the application plan (WUP)
Sludge Management
Sludge in my lagoon will be managed by the following
• Adequately monitor to define sludge volume, location, and rate of accumulation by conducting an
annual sludge survey.
• Maintain a minimum 2.5 feet deep zone, free of sludge at the pump intake during irrigation.
• Position the pump intake and manage the Irrigation operation such that the material irrigated is not
more concentrated than the nutrient analysis samples.
• Sufficient monitoring to address concerns that nutrients are not over applied.
• Other items as required by DWQ.
I hereby certify that I have reviewed the information listed above and included within the attached
Plan of Action, and to the best of my knowledge and ability, the information is accurate and
correct.
�Phone: �
Facility OwnertManager (print)
Dater
Fac
ility Owner/Manager (signature)
Return this form to:
NC Division of Water Quality
1617 Mail Service Center
Raleigh, NC 27699-1617
SPOA 5-18-04 Page 2 of 2
PLAN OF ACTION (POA) FOR LAGOON SLUDGE REDUCTIOMAY 3 0 2023
NC DEQ/DWR
Facility Number: 82-47 County: Sam son Central Office
Facility Name: Bob Thornton 5-8
Certified Operator Name: �I Operator M 1 2
Compliance Timeframes:
If .the sludge level is equal to or higher than the stop pump level of the lagoon or if the sludge level
results -in an elevated waste analysis, a sludge management plan that meets the requirements of SIB
Interagency Group Guidance Document 1.26 must be prepared by a technical specialist and submitted to
DWQ within 180 days. Work to reduce the sludge level must begin within another 180 days.
Compliance with NRCS Standard 359 must be achieved by the expiration date of the current permit, July
1, 2007.
If the sludge level is non -compliant, but below the stop pump level of the lagoon, compliance with NRCS
Standard 359 must be achieved by the expiration date of the current permit, July 1, 2007. If future
sludge surveys do not show improvement in sludge levels, DWQ may require the owner to develop a
sludge management plan that meets the requirements of SB Interagency Group Guidance Document
1.26.
SPOA 5-18-04 Page 1 of 2